First Notice | | 8/1/2013 | 8/16/2013 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
BLD-Final | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | PASS |
Jim Sly
|
|
|
Brandon Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 7/22/2013 | | DONE |
Tisha Gallop
|
|
|
|
Zoning Approval | 7/19/2013 | 7/19/2013 | 7/19/2013 | | PASS |
Josh Wilson
|
|
|
Bike rack installed.
|
BLD-Final | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PART |
Jim Sly
|
|
|
Brandon Phone #: ###-#### OK for Temp Occ. OK for Perm Occ when Zoning perms and when Final affidavit letter of approval is provided........including Stamp and signature from Engineer of record. This document to be archived.
|
FIRE-Final Inspection | 7/1/2013 | 7/2/2013 | 7/2/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | FAIL |
Troy Cobbley
|
|
|
Project was not quite ready for fire life safety but we verified all of the emergency light was funtional and found three light that did not work but two of which were repaired while I waited. We also went over fire dept access curb painting.
|
PubWorks Occupancy Approval | 6/26/2013 | 6/26/2013 | 6/26/2013 | | DONE |
Tiffany Lowery
|
|
|
|
PubWorks Occupancy Approval | 6/25/2013 | 6/25/2013 | 6/25/2013 | | DONE |
Jason C. Taylor
|
|
|
|
Zoning Approval Temp | 6/25/2013 | 6/25/2013 | 6/25/2013 | | PASS |
Josh Wilson
|
|
|
Needs bike rack prior to permanent occ.
|
BLD-Framing/Rough-in | 5/6/2013 | 5/6/2013 | 5/7/2013 | P | PASS |
Jim Sly
|
|
|
Jeff Ceiling grid inspection please Phone #: ###-#### Ceiling grid pass.
|
BLD-Ceiling Grid Inspection | 4/24/2013 | 4/24/2013 | 4/24/2013 | A | PART |
Mike Jordan
|
|
|
North half, missing some clips. Will check on final. pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 1/16/2013 | 1/16/2013 | 1/16/2013 | P | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Exterior shear wall....OK
|
BLD-Footing | 11/26/2012 | 11/27/2012 | 11/27/2012 | A | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### North wall OK pending MTI insp, tests and approval.
|
BLD-Footing | 11/20/2012 | 11/21/2012 | 11/21/2012 | A | DEFR |
Mike Jordan
|
|
|
jeff Phone #: ###-####. Special inspector on site.
|
BLD-Foundation | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | CANC |
Jim Sly
|
|
|
Jeff Phone #: ###-#### CANCELLED BY CONTR.
|
BLD-Foundation | 11/14/2012 | 11/15/2012 | 11/15/2012 | A | PART |
Jim Sly
|
|
|
Fauldation wall - Jeff Phone #: ###-#### South and West walls OK pending MTI insp, tests and approvals. MTI inspectors so far....Roy Green and Kevin Schroeder. Both verified as certified in thieir dicipline.
|
BLD-Foundation | 11/9/2012 | 11/13/2012 | 11/13/2012 | A | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Mti on site.
|
BLD-Foundation | 11/7/2012 | 11/8/2012 | 11/8/2012 | A | PART |
Jim Sly
|
|
|
pouring at 2 - Jeff Phone #: ###-#### East wall ....OK pend MTI insp,tests and approvals.
|
Print Occupancy Form | | | 10/26/2012 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 10/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/24/2012 | | DONE |
Barbara Stitt
|
|
|
E-mailed Brandon the fees due and that we need ACHD info on 10-24-12 @ 2:15pm//BAS
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2012 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 8/20/2012 | | 10/23/2012 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 10/17/2012 | | 10/22/2012 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 10/18/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved requested revisions. JCM
|
Routing - PLAN CHECK | 10/17/2012 | | 10/18/2012 | | PASS |
John Menard
|
|
|
|
Routing - Design Review | 10/17/2012 | | 10/17/2012 | | PASS |
Josh Wilson
|
|
|
OK per revised landscape plan L1.0
|
1st review completed | | | 9/27/2012 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 9/26/2012 | | 9/27/2012 | | PASS |
Scott Arellano
|
|
|
8-26-12 *Pending quantification of buildng occupant load by Builidng Official.
9-27-12 * Pass attached review comments to plans.
|
Routing - PLAN CHECK | 8/20/2012 | | 9/25/2012 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 8/20/2012 | | 9/10/2012 | | FAIL |
John Menard
|
|
|
Sent structural comments to AHJ Chris Holiday.
|
Routing - PUBLIC WORKS | 8/20/2012 | | 9/7/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Street Lights | 8/20/2012 | | 8/27/2012 | | PASS |
Mike D Hedge
|
|
|
|
Routing - Design Review | 8/20/2012 | | 8/24/2012 | | FAIL |
Josh Wilson
|
|
|
Sheet L1.0 Add plant materials to all planter beds containing only rock mulch.
|
Routing PW Sewer Design | 8/20/2012 | | 8/23/2012 | | PASS |
Mike Sheppard
|
|
|
Connect to existing 6" service
|
Routing PW Sewer Rating | 8/20/2012 | | 8/23/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 8/20/2012 | | 8/23/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 8/21/2012 | | 8/21/2012 | | PASS |
April Wing
|
|
|
|
Routing - Erosion and Sediment | 8/20/2012 | | 8/21/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Route to Impact Fee Review | 8/20/2012 | 8/23/2012 | 8/20/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLUMBING | 8/20/2012 | | 8/20/2012 | | PASS |
Daryl Spivey
|
|
|
May require additional backflow protection.
Per plans and 2003 UPC.
|
Routing - PLANNING Land Div | 8/20/2012 | | 8/20/2012 | | PASS |
Dave Abo
|
|
|
Parcel "A" Record of Survey.
|
Routing PW Solid Waste | 8/20/2012 | | 8/20/2012 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 8/20/2012 | | 8/20/2012 | | PASS |
Walt Baumgartner
|
|
|
|
Pending Assignment by JCM | 8/20/2012 | | 8/20/2012 | | DONE |
John Menard
|
|
|
|
Telephone call | | | 8/13/2012 | | DONE |
Tisha Gallop
|
|
|
sent e-mail to applicant for pln chk fee
|
Intake Approval | | | 8/9/2012 | | FAIL |
John Menard
|
|
|
Please submit Form #310 - Statement of Special Inspection filled out and stamped and signed by the project structural engineer. The building owner is also required to sign and date the form. The structural plans should also indicate all required special inspections.
Please submit competed and final Civil Plans that are approved for construction. The current uploads Civil Plans indicate "not for construction".
Please submit plan information on the proposed Mechanical Equipment (Mechanical Schedule).
Form #304 - Registered Design Professional Form should be signed by the building owner.
|
Intake Approval | | | 8/7/2012 | | FAIL |
John Menard
|
|
|
The submittal is not complete enough to do a prescreen for this project.
Please complete and submit a #502 Plan Intake Submittal Requirements Checklist, as well as, all applicable items required by that checklist. http://pds.cityofboise.org/home/documents/
Please review the Electronic File Submittal Standard and comply with all required standards. http://pds.cityofboise.org/pds-online/e-services/eplanreview/
A portion of the standards require:
1. Each plan sheet must to be uploaded under a separate file name (not all in one file).
Review file naming requirements. Please add a file name for each document as outlined in the Submittal Standard. Each plan file name should coincide with the plan name on the cover sheet.
2. Bottom right hand corner of plans to be left blank for City stamps. Not all plan sheets have the required space for City approval stamps.
3. The energy ComCheck sheets are to be submitted on plan sheets, not as small documents.
4. Please review other requirements.
You also have the option of submitting your project using paper plans and documents.
|
Application received | | | 8/3/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2012 8:29AM
|
Intake Approval | | | 8/3/2012 | | FAIL |
John Menard
|
|
|
The submittal is not complete enough to do a prescreen for this project.
Please complete a #502 Plan Intake Submittal Checklist and submit all applicable items
required by that checklist. http://pds.cityofboise.org/home/documents/
Please review the Electronic File Submittal Standard and comply with all required standards.
http://pds.cityofboise.org/pds-online/e-services/eplanreview/
A portion of the standards require:
1. Each plan sheet must to be uploaded under a separate file name (not all in one file).
Review file naming requirements.
2. Bottom right hand corner of plans to be left blank for City stamps.
3. Please review other requirements.
You also have the option of submitting your project using paper plans and documents.
|