Routing PW Sewer Rating | 2/19/2013 | | 12/16/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Third Notice | | 8/4/2013 | 8/22/2013 | | DONE |
|
|
|
|
Third Notice | | 7/6/2013 | 7/30/2013 | | DONE |
|
|
|
mailed to 15th st address
|
Third Notice | | 4/29/2013 | 7/1/2013 | | DONE |
Tisha Gallop
|
|
|
mailed to Walt Kerpa at 15th street address.
|
Second Notice | | 4/1/2013 | 4/24/2013 | | DONE |
|
|
|
mailed to Walt Kerpa at Garden City address//5/20/13 returned mail from 4744 Fenton St, Garden City 83714 -- remailed to 495 S. 15th St, Boise 83702
|
First Notice | | 3/17/2013 | 3/22/2013 | | DONE |
|
|
|
returned mail for Kerpa Construction//remailed to Walt Kerpa (applicant) at 4744 Fenton address.--3/29/13 leg
|
BLD-Final | 3/6/2013 | 3/7/2013 | 3/7/2013 | A | PASS |
Dave Hannah
|
|
|
Walt Phone #: ###-####
|
FIRE-Final Inspection | 3/6/2013 | 3/6/2013 | 3/7/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
Permanent Occupancy | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 3/5/2013 | 3/5/2013 | 3/5/2013 | P | NR |
Forrest France
|
|
|
Project related fire alarm permit is in "ready to issue" status. Fire alarm and fire sprinkler permits must be inspected and finaled prior to building fire life safety approvals.
|
Zoning Approval | 3/1/2013 | 3/1/2013 | 3/1/2013 | | PASS |
Josh Wilson
|
|
|
|
Plan Reviewer's activity | | | 2/26/2013 | | DONE |
Sam Zahorka
|
|
|
Revolution Vodka is good to go. I have signed a “no discharge” permit effective March 1st. It basically requires notification and approval by us in the event spillage or firewater had to go to sewer. You may move forward w/ final occupancy approval as you see fit.
|
Routing - FIRE | 2/25/2013 | | 2/25/2013 | | PASS |
Scott Arellano
|
|
|
OK.
|
Routing - PLUMBING | 2/20/2013 | | 2/20/2013 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2009 ISPC.
|
Routing PW Environmental | 2/19/2013 | | 2/19/2013 | | PASS |
Walt Baumgartner
|
|
|
Zero Discharge Pretreatment permit will be issued for tank room operations.
|
Additional plans submitted | | | 2/19/2013 | | DONE |
Sam Zahorka
|
|
|
The architect emailed plan modification sheets A1.1, A1.3, and P1.0. He requested I upload these for him. SRZ
|
Meeting | | | 2/15/2013 | | DONE |
Sam Zahorka
|
|
|
Meeting with the architect, Wault Baumgartner, Daryl Spivey, Scott Arellano, and myself to discuss Plan Modifications. Plan modification sheets were requested and Wault requested a Sewer discharge permit. Waiting for the architect to submit plan modification drawings.
|
Print Occupancy Form | | | 2/14/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/14/2013 | | DONE |
Christina Prado
|
|
|
|
Meeting | | | 2/13/2013 | | DONE |
Sam Zahorka
|
|
|
Scheduled a meeting for 2/15/13 to discuss possible plan modifications identified per Wault Baumgartner.
|
OVERRIDE | | | 1/8/2013 | | |
|
|
|
|
Plan assigned to (SRZ) | 1/3/2013 | 1/3/2013 | 1/7/2013 | | DONE |
Sam Zahorka
|
|
|
Deferred Tank submittals.
|
Plan Reviewer's activity | | | 1/7/2013 | | DONE |
Sam Zahorka
|
|
|
Deferred tank design submittals are approved by Fire and Building plan review. The design engineer shall verify the installation during construction and provide a final letter indicating compliant installation per the engineered design when completed to the City of Boise Planning and Development department. I telephoned the architect and Engineer Reese Leavitt and requested Final Letter when Tank installation is complete. I also called the structural inspector and let him know.
|
Telephone call | | | 1/7/2013 | | DONE |
Sam Zahorka
|
|
|
Called the architect and the engineer. Requested the design engineer to verify the installation of the deferred tanks during construction and provide a final letter indicating compliant installation per the engineered design when completed to the City of Boise Planning and Development department prior to permit final. Jimmy Church with leavitt engineers stated he would provide the letter.
|
Routing - PLAN CHECK | 1/7/2013 | | 1/7/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - FIRE | 1/3/2013 | | 1/4/2013 | | PASS |
Scott Arellano
|
|
|
Attached Plan review report to plans.
|
Routing - PLAN CHECK | 1/3/2013 | | 1/3/2013 | | PEND |
Sam Zahorka
|
|
|
Pending Fire to PASS.
|
Routing - FIRE | 12/10/2012 | | 12/12/2012 | | FAIL |
Scott Arellano
|
|
|
The Fire Marshal has reviewed the submitted tank design and has questions relating to IFC requirements for tank venting. Added correction items to electronic case using change marks and sent architect the updated plan review report.
|
BLD-Framing/Rough-in | 12/3/2012 | 12/4/2012 | 12/4/2012 | A | PASS |
Dave Hannah
|
|
|
walt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/14/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/14/2012 | | DONE |
|
|
|
|
OVERRIDE | | | 11/13/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 11/13/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 8/21/2012 | 8/21/2012 | 11/9/2012 | | PASS |
Sam Zahorka
|
|
|
ePlanReview -
1st review completed.
2nd review completed.
3rd review completed.
4th review completed. Failed.
|
Plan resubmittals received | | | 11/9/2012 | | DONE |
Sam Zahorka
|
|
|
ePlanReview
|
Routing - PLAN CHECK | 11/9/2012 | | 11/9/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - MECHANICAL | 11/7/2012 | | 11/7/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/1/2012 | | 11/5/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLUMBING | 10/16/2012 | | 10/16/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
May require additional backflow protection.
|
Routing - MECHANICAL | 10/12/2012 | | 10/12/2012 | | FAIL |
Troy James
|
|
|
exhuast duct requirements need be shown on plans per section 510.8 IMC
|
Routing - PLAN CHECK | 10/12/2012 | | 10/12/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 10/12/2012 | | 10/12/2012 | | FAIL |
Scott Arellano
|
|
|
Tank Design under review for IFC compliance. Additional Information is required on plans. Change Marks are indicated on Tank Plans within E-Plan Review.
|
Routing - FIRE | 9/26/2012 | | 10/1/2012 | | FAIL |
Scott Arellano
|
|
|
Sent architect resubmittal items. Attached plan review report to e-plan review case, tidemark, and emailed to architect.
|
Routing - Design Review | 9/26/2012 | | 10/1/2012 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 9/26/2012 | | 9/28/2012 | | FAIL |
Daryl Spivey
|
|
|
Need to have a 1 1/4 inch cold supply to emergency show and eye wash.
|
Routing - PLAN CHECK | 9/25/2012 | | 9/28/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Routing PW Environmental | 9/26/2012 | | 9/26/2012 | | PASS |
Walt Baumgartner
|
|
|
Facility operations subject to sewer pretreatment inspection program. Formal Accidental Spill Prevention Plan may be required after start up of operations. Contact Walt at 384- 3991 for more information.
|
Plan resubmittals received | | | 9/26/2012 | | DONE |
Sam Zahorka
|
|
|
Initial plan designs have changed and the tenant layout and square footage has changed. A new review is required from all reviewing departments.
|
Routing - Erosion and Sediment | 9/26/2012 | | 9/26/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Sewer Rating | 9/26/2012 | | 9/26/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 8/21/2012 | | 9/25/2012 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 9/25/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing PW Environmental | 8/22/2012 | | 8/29/2012 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - Design Review | 8/21/2012 | | 8/24/2012 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - CZC12-00164
|
Routing - FIRE | 8/21/2012 | | 8/24/2012 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to architect. Uploaded IFC plan review report into e-plan review case.
|
Routing PW Sewer Rating | 8/22/2012 | | 8/23/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/21/2012 | | 8/23/2012 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 8/21/2012 | | 8/22/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 8/21/2012 | | 8/22/2012 | | FAIL |
Bill VanDegrift
|
|
|
Provide complete set of plumbing prints with all water, waste and venting and all plumbing piping sized.
|
Routing - Erosion and Sediment | 8/21/2012 | | 8/22/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Waiver Request approved
|
Intake Approval | | | 8/21/2012 | | PASS |
Jason Blais
|
|
|
Prescreen passed on 8/13/12. Plan Review Fees paid on 8/21/12.
|
Pending Assignment by JCB | 8/21/2012 | | 8/21/2012 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 8/21/2012 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to evaluate if any impact fees are due. Written verification from ACHD will need to be provided to our Permit Counter prior to the building permit being issued.
|
Intake Approval | | | 8/13/2012 | | FAIL |
Tim L. Woodard
|
|
|
Pat:
Please review the attached “marked up” checklist. Additional items are required prior to review of this project. Two things that are not mentioned on a checklist, but will be required, are: a technical opinion report and re-upload sheet A1.1 (keynote designations are blacked out). For all other items the checklist will show required re-submittal issues. Thank you!
Tim Woodard
twoodard@cityofboise.org
###-####
|
Telephone call | | | 8/13/2012 | | DONE |
Barbara Stitt
|
|
|
Emailed Pat McKeegan that plan check fees are due on 8-13-12 @ 3:35pm///BAS
|
Application received | | | 8/10/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 10 2012 11:54AM
|