Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-02128
StatusFinaled
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 521 W MCGREGOR DR
Project NameFederal Way Building #4 - Matt
Customer Number 
ePlanReviewYes
Description
(MATTRESS FIRM TI - Federal Way Building #4) Permit to remodel an empty shell space for the first time. This building shell was constructed under BLD07-02854. Work to include: [construction of interior nonbearing walls to create: one office, one break room, a foyer, and two family assited use restrooms], installation of new doors and hardware as indicated on plans, installation of new millwork w/sink, installation of new electrical, installation of a new mechanical system to supply the office and restrooms, installation of a new drinking fountain / mop sink, and installation of interior finishes in compliance with chapter 8 of the IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 1/13/20131/3/2013 DONE
First Notice 12/10/20121/3/2013 DONE
faxed 1-3-13
Permanent Occupancy  11/30/2012 DONE
BLD-Final11/19/201211/19/201211/19/2012PPASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Brian McCoy
FIRE-Final Inspection11/16/201211/16/201211/16/2012PPASS
DetailsForrest France
Fire life safety final approved pending door hardware at two storefront doors is revised to meet min. code requirements prior to structural final as agreed.
FIRE-Conference11/16/201211/16/201211/16/2012ADONE
DetailsForrest France
Regarding C/N items and project completion schedule.
BLD-Final11/15/201211/19/201211/15/2012ACANC
DetailsJim Storey
Call Brian McCoy for Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy Inspection cancelled from web by: Brian McCoy
BLD-Final11/15/201211/16/201211/15/2012ACANC
DetailsJim Storey
Please call Brian McCoy for Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy Inspection cancelled from web by: Brian McCoy
FIRE-Final Inspection11/15/201211/15/201211/15/2012PFAIL
DetailsForrest France
Provide exit signs per approved plan review notes, door hardware needs revised at two locations.
BLD-Ceiling Grid Inspection11/6/201211/7/201211/7/2012APASS
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Brian McCoy
BLD-Ceiling Grid Inspection11/5/201211/6/201211/6/2012PNR
DetailsJim Storey
Please call Brian for entry ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
BLD-Energy code compliance10/16/201210/17/201210/17/2012APASS
DetailsJim Storey
Call Brian for Accsess ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
BLD-Framing/Rough-in10/10/201210/11/201210/11/2012APASS
DetailsJim Storey
Call Brian McCoy for Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
Permit Ready to Issue  9/24/2012 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  9/24/2012 DONE
DetailsBarbara Stitt
Print Occupancy Form  9/24/2012 DONE
DetailsBarbara Stitt
Routing - FIRE  9/14/2012 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/14/2012 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)8/21/2012 9/14/2012 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK8/21/2012 9/6/2012 PASS
DetailsTim L. Woodard
Approved with redlines in eplan review. TLW
1st review completed  9/6/2012 DONE
DetailsTim L. Woodard
Routing PW Sewer Rating8/22/2012 8/23/2012 PASS
DetailsConnie Baumgartner
Plan Reviewer's activity  8/22/2012 DONE
Emailed RP Fire Review
Routing - PUBLIC WORKS8/21/2012 8/22/2012 PASS
DetailsBeverly Mountain
Routing - Addressing8/21/2012 8/22/2012 PASS
DetailsApril Wing
Routing - FIRE8/21/2012 8/22/2012 FAIL
DetailsScott Arellano
Intake Approval  8/21/2012 PASS
DetailsTim L. Woodard
Telephone call  8/20/2012 DONE
DetailsChristina Prado
Emailed Damon intake fees due
Application received  8/14/2012 DONE
Application submitted via PDS Online on Aug 14 2012 9:24AM