BLD-Final | 12/20/2012 | 12/21/2012 | 12/21/2012 | A | PASS |
Mike Jordan
|
|
|
jared Phone #: ###-####
|
DOC - Permit Finaled | 12/21/2012 | 12/21/2012 | 12/21/2012 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 12/19/2012 | 12/20/2012 | 12/20/2012 | P | FAIL |
Mike Jordan
|
|
|
jared Phone #: ###-####. Provide blower door test results and post or the 3rd party inspection airseal report. Post the required energy cert. Correction notice posted.
|
BLD-Final | 12/18/2012 | 12/19/2012 | 12/19/2012 | P | NR |
Mike Jordan
|
|
|
call for access code -Jared Phone #: 8. Stilll has open electrical and mech permits that ned finaled first.
|
BLD-Framing/Rough-in | 10/12/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Mike Jordan
|
|
|
Insulation as well - Jared Phone #: ###-####
|
BLD-Energy code compliance | 10/15/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Mike Jordan
|
|
|
Insulation as well - Jared Phone #: ###-####
|
BLD-Framing/Rough-in | 10/10/2012 | 10/11/2012 | 10/11/2012 | A | FAIL |
Tom Arcoraci
|
|
|
Jared Phone #: ###-#### notice posted
|
BLD-Wall Bracing | 9/27/2012 | 9/28/2012 | 9/28/2012 | A | PART |
Mike Jordan
|
|
|
jared Phone #: ###-####. Exterior wall bracing ok. Needs to provide CS-PF over openings at master bath. Will check at framing inspection.
|
BLD-Foundation | 9/10/2012 | 9/11/2012 | 9/11/2012 | A | PART |
Mike Jordan
|
|
|
chris Phone #: ###-####
|
BLD-Footing | 9/7/2012 | 9/10/2012 | 9/10/2012 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
OVERRIDE | | | 8/31/2012 | | |
|
|
|
|
Plan assigned to (CDM) | | 8/15/2012 | 8/31/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/22/2012 | | 8/31/2012 | | PASS |
Carl D Madsen
|
|
|
|
Issue PAID IN FULL permit | | | 8/31/2012 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 8/31/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/31/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/31/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/31/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 8/17/2012 | | 8/22/2012 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/15/2012 | 8/20/2012 | 8/17/2012 | | PASS |
Shauna Surgeon
|
|
|
|
Routing - PUBLIC WORKS | | | 8/17/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 8/17/2012 | | 8/17/2012 | | PASS |
Sue Cummings
|
|
|
See redlines on site plan SAC
|
Routing - Addressing | 8/15/2012 | | 8/16/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 8/15/2012 | 8/15/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/15/2012 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (REV) | | | 8/15/2012 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/15/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/15/2012 | | PASS |
Christina Prado
|
|
|
|