BLD-Final | 1/10/2013 | 1/11/2013 | 1/11/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin
|
DOC - Permit Finaled | 1/11/2013 | 1/11/2013 | 1/11/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 1/9/2013 | 1/10/2013 | 1/10/2013 | P | FAIL |
Mike Jordan
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin. Provide the required energy cert and blower door test results anmd post.
|
BLD-Conference | 11/25/2012 | 11/26/2012 | 11/26/2012 | A | CANC |
Mike Jordan
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin
|
BLD-Energy code compliance | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin
|
BLD-Framing/Rough-in | 10/30/2012 | 10/30/2012 | 10/30/2012 | P | PASS |
Jim Sly
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin
|
BLD-Wall Bracing | 10/28/2012 | 10/29/2012 | 10/29/2012 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: 6088231 >> Inspection requested via mobile web by Rustin
|
BLD-Wall Bracing | 9/18/2012 | 9/18/2012 | 9/18/2012 | P | CANC |
Mike Jordan
|
|
|
As early as possible Phone #: 9411915 >> Inspection requested via mobile web by jay
|
BLD-Foundation | 9/18/2012 | 9/18/2012 | 9/18/2012 | P | PASS |
Mike Jordan
|
|
|
As early as possible Phone #: 9411915 >> Inspection requested via mobile web by jay
|
BLD-Footing | 9/17/2012 | 9/17/2012 | 9/17/2012 | P | PASS |
Mike Jordan
|
|
|
Stan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/17/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 8/16/2012 | 8/16/2012 | 9/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/14/2012 | | 9/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 9/14/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/14/2012 | | DONE |
|
|
|
|
Telephone call | | | 9/14/2012 | | |
|
|
|
9-14-12 called Stetson Homes permit ready for pick up
|
Plan resubmittals received | | | 9/12/2012 | | |
|
|
|
received 1 11x17 roof plan & 1 copy of design/header garage door sent to Carl M
|
1st review completed | | | 9/7/2012 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 9/7/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/27/2012 | | 9/7/2012 | | FAIL |
Carl D Madsen
|
|
|
Headers Sent E-Mail to Stetson Homes
|
Routing - MECHANICAL | 8/27/2012 | | 8/27/2012 | | FAIL |
Troy James
|
|
|
sent email corrections to teds heating
|
Routing - MECHANICAL | 8/27/2012 | | 8/27/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 8/17/2012 | | 8/24/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to teds heating
|
Route to Impact Fee Review | 8/16/2012 | 8/21/2012 | 8/17/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/17/2012 | | 8/17/2012 | | PASS |
Susan Riggs
|
|
|
|
Routing - PUBLIC WORKS | | | 8/17/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 8/16/2012 | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Addressing | 8/16/2012 | | 8/16/2012 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 8/16/2012 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/16/2012 | | DONE |
Barbara Stitt
|
|
|
|