BLD-Final | 1/17/2013 | 1/18/2013 | 1/18/2013 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
DOC - Permit Finaled | 1/18/2013 | 1/18/2013 | 1/18/2013 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 11/7/2012 | 11/8/2012 | 11/8/2012 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Framing/Rough-in | 11/6/2012 | 11/6/2012 | 11/6/2012 | P | PART |
Tony Young
|
|
|
Inspect late in the afternoon...thanks Phone #: ###-#### >> Inspection requested via web by Ken Litzinger,, need mech full pass,,, ok to insulate walls
|
BLD-Wall Bracing | 10/29/2012 | 10/29/2012 | 10/30/2012 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Wall Bracing | 10/25/2012 | 10/26/2012 | 10/26/2012 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger,, need to add 8 foot to garage rear wall,, then ok
|
BLD-Wall Bracing | 10/25/2012 | 10/25/2012 | 10/25/2012 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger,,, out of time
|
BLD-Foundation | 9/20/2012 | 9/20/2012 | 9/20/2012 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
BLD-Footing | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ken Litzinger
|
Issue PAID IN FULL permit | | | 9/19/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 9/18/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/18/2012 | | DONE |
|
|
|
|
Telephone call | | | 9/18/2012 | | DONE |
Christina Prado
|
|
|
Called and gave Ken fees due
|
Permit Ready to Issue | | | 9/18/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 8/21/2012 | 8/21/2012 | 9/17/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/28/2012 | | 9/17/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/17/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 9/17/2012 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/27/2012 | | 8/28/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/24/2012 | | 8/27/2012 | | PASS |
Susan Riggs
|
|
|
|
Routing - PUBLIC WORKS | 8/22/2012 | | 8/24/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 8/21/2012 | 8/24/2012 | 8/23/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Application received | | 8/21/2012 | 8/22/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 8/22/2012 | | 8/22/2012 | | PASS |
Terry Records
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/21/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/21/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/21/2012 | | PASS |
Tisha Gallop
|
|
|
|