BLD-Final | 5/17/2013 | 5/17/2013 | 5/17/2013 | P | PASS |
Jim Sly
|
|
|
eric Phone #: ###-####
|
DOC - Permit Finaled | 5/17/2013 | 5/17/2013 | 5/17/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 5/14/2013 | 5/14/2013 | 5/14/2013 | P | CANC |
Jim Sly
|
|
|
Eric phone ###-####
|
BLD-Final | 5/13/2013 | 5/14/2013 | 5/14/2013 | A | FAIL |
Jim Sly
|
|
|
eric Phone #: ###-#### Need Fireplace final.
|
BLD-Final | 5/8/2013 | 5/9/2013 | 5/10/2013 | A | NR |
Jim Sly
|
|
|
chad Phone #: ###-####
|
BLD-Framing/Rough-in | 3/5/2013 | 3/6/2013 | 3/6/2013 | P | PASS |
Jim Sly
|
|
|
chad Phone #: ###-#### Energy code ........OK.
|
BLD-Energy code compliance | 3/5/2013 | 3/5/2013 | 3/6/2013 | P | NR |
Jim Sly
|
|
|
Chad phone ###-####
|
BLD-Framing/Rough-in | 3/4/2013 | 3/5/2013 | 3/5/2013 | P | CANC |
Jim Sly
|
|
|
chad Phone #: ###-####
|
BLD-Framing/Rough-in | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PASS |
Jim Sly
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 2/25/2013 | 2/26/2013 | 2/27/2013 | A | FAIL |
Jim Sly
|
|
|
chad Phone #: ###-#### C/N posted.
|
Plan resubmittals received | | | 1/28/2013 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 1/28/2013 | | 1/28/2013 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
CHANGE STATUS TO (ISS) | | | 1/28/2013 | | DONE |
|
|
|
approved resubmitted acca report
|
BLD-Wall Bracing | 1/23/2013 | 1/24/2013 | 1/24/2013 | A | PASS |
Jim Sly
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 12/11/2012 | 12/12/2012 | 12/12/2012 | P | PART |
Jim Sly
|
|
|
bill - around 3 please Phone #: ###-#### Footing at front patio was formed 20" wide. This area was overdug and packed with hoe. Drain rock was installed last 12". I asked for compaction tests. No compaction tests where done at Contractors request. Proceeding at own risk.
|
BLD-Foundation | 11/21/2012 | 11/26/2012 | 11/26/2012 | P | PASS |
Jim Sly
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 11/15/2012 | 11/16/2012 | 11/16/2012 | P | PART |
Jim Sly
|
|
|
Bill Phone #: ###-#### Footings for normal basement East side. MTI inspection and approval of subgrade fill.
|
BLD-Foundation | 10/26/2012 | 10/26/2012 | 10/26/2012 | P | PART |
Jim Sly
|
|
|
BILL Phone #: ###-#### 20' high walls OK.
|
BLD-Foundation | 10/23/2012 | 10/24/2012 | 10/24/2012 | A | PART |
Jim Sly
|
|
|
bill Phone #: ###-#### Rebar in all 20' walls OK...OK to pour.
|
BLD-Footing | 10/16/2012 | 10/17/2012 | 10/17/2012 | A | PART |
Jim Sly
|
|
|
Bill Friend Phone #: ###-#### Footings for Sports area of basement.....OK
|
Issue PAID IN FULL permit | | | 10/2/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 8/22/2012 | 8/22/2012 | 9/24/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/24/2012 | | 9/24/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 9/24/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/24/2012 | | DONE |
|
|
|
|
Telephone call | | | 9/24/2012 | | DONE |
Christina Prado
|
|
|
Called Chad to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 9/24/2012 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 9/21/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked 5 & 7 as well as two sets of Limited Geotechnical Engineering Reports: gave to Carl Madsen for further review
|
1st review completed | | | 9/18/2012 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/27/2012 | | 9/18/2012 | | FAIL |
Carl D Madsen
|
|
|
Beams and geotechnical report. E-Mailed and takled to Chad. 9-18-12 CDM
|
Route to Impact Fee Review | 8/22/2012 | 8/27/2012 | 9/7/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 9/4/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked 3 & 5.1. Also received two sets of Stamped structural calcs. Gave plans and calcs to Carl for further review
|
Routing - MECHANICAL | 8/30/2012 | | 8/30/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 8/29/2012 | | 8/29/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Teds Heating
|
Routing - MECHANICAL | 8/24/2012 | | 8/27/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Teds Heating
|
Routing - PLANNING | 8/24/2012 | | 8/24/2012 | | PASS |
Sue Cummings
|
|
|
See redline on site plan SAC
|
Routing - PUBLIC WORKS | 8/22/2012 | | 8/24/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 8/21/2012 | 8/22/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/22/2012 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/22/2012 | | DONE |
|
|
|
|
Intake Approval | | | 8/22/2012 | | PASS |
|
|
|
|
Routing - Addressing | 8/22/2012 | | 8/22/2012 | | PASS |
Terry Records
|
|
|
|