Second Notice | | 1/13/2013 | 1/8/2013 | | DONE |
|
|
|
This permit finaled on the web by Jim Macfarlane
|
First Notice | 12/20/2012 | 12/20/2012 | 1/3/2013 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 12/19/2012 | 12/20/2012 | 12/20/2012 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
DOC - Permit Finaled | 12/20/2012 | 12/20/2012 | 12/20/2012 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Cert of completion was issued.
|
BLD-Final | 12/11/2012 | 12/12/2012 | 12/12/2012 | P | FAIL |
Mike Jordan
|
|
|
jim Phone #: ###-####. Needs to provide tempered glazing at existing window were a new door has been installed placing existing window in a hazordous location.
|
FIRE-Final Inspection | 12/11/2012 | 12/12/2012 | 12/12/2012 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 12/10/2012 | 12/10/2012 | 12/10/2012 | P | FAIL |
Troy Cobbley
|
|
|
Repair the exit signs and emergency lights as discussed and provide the additional exit sign at the door to the lobby as shown on the approved plans. Also the fire alarm panel is in a "trouble condition". Per phone call from Mark at Alarmco the panel will be repaired, if needed, by tomorrow and he will call me on status.
|
BLD-Final | 12/7/2012 | 12/11/2012 | 12/10/2012 | A | NR |
Mike Jordan
|
|
|
Please call ahead for access - Jim Phone #: ###-####. Needs fire/life/safety first.
|
BLD-Framing/Rough-in | 10/24/2012 | 10/26/2012 | 10/26/2012 | A | PASS |
Mike Jordan
|
|
|
request first thing//Jim Phone #: ###-####. Interior steel stud walls ok.
|
Issue PAID IN FULL permit | | | 9/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 8/24/2012 | 8/24/2012 | 9/27/2012 | | PASS |
Carl Westfall
|
|
|
EPI SCIENCES INC (20 days - Sept 19)
|
Routing - PLAN CHECK | 9/26/2012 | | 9/27/2012 | | DONE |
Carl Westfall
|
|
|
Routed to the permits desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/27/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/27/2012 | | DONE |
Christina Prado
|
|
|
Called Robert to advise permit is ready, gave fees due and advised GC is required prior to issuance
|
Permit Ready to Issue | | | 9/27/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 9/26/2012 | 9/26/2012 | 9/26/2012 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
1st review completed | | | 9/26/2012 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/28/2012 | | 9/26/2012 | | PASS |
Carl Westfall
|
|
|
The IBC plan review was started on Sept 24 and was finished on Sept 26. The drawings were approved with "red lines". See the plan review report.
|
Routing - Design Review | 8/27/2012 | | 8/28/2012 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - Minor exterior door/window relocations
Approved.
|
Routing - Addressing | 8/24/2012 | | 8/27/2012 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2012 | | 8/27/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 8/24/2012 | | 8/27/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 8/23/2012 | | 8/24/2012 | | DONE |
Jason Blais
|
|
|
|
Application received | | 8/23/2012 | 8/23/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/23/2012 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/23/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/23/2012 | | DONE |
Tisha Gallop
|
|
|
|