Second Notice | | 8/9/2013 | 8/9/2013 | | DONE |
|
|
|
|
Print Statement | | | 8/9/2013 | | DONE |
Tisha Gallop
|
|
|
mailed to Dave Evans Construction
|
First Notice | | 7/27/2013 | 7/30/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/17/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 7/12/2013 | 7/15/2013 | 7/16/2013 | A | PASS |
Jim Sly
|
|
|
dave Phone #: ###-#### OK for Perm Occ.
|
Temporary Occupancy | 6/6/2013 | 9/4/2013 | 6/6/2013 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 6/4/2013 | 6/4/2013 | 6/4/2013 | P | PART |
Dave Hannah
|
|
|
dave Phone #: ###-#### ok for temp occ ok for perm occ after med gas is finaled
|
FIRE-Final Inspection | 5/30/2013 | 5/31/2013 | 5/31/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed and passed.
|
PubWorks Occupancy Approval | 5/31/2013 | 5/31/2013 | 5/31/2013 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 5/31/2013 | 5/31/2013 | 5/31/2013 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 5/8/2013 | 5/9/2013 | 5/9/2013 | A | PASS |
Dave Hannah
|
|
|
Ceiling grid inspection please--Dave Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/7/2013 | 5/8/2013 | 5/8/2013 | A | NH |
Jim Sly
|
|
|
dave Phone #: ###-#### Called contractor.....No access.
|
BLD-Ceiling Grid Inspection | 5/3/2013 | 5/3/2013 | 5/3/2013 | P | FAIL |
Dave Hannah
|
|
|
dave Phone #: ###-#### needs wires to speakers
|
FIRE-Conference | 4/1/2013 | 4/1/2013 | 4/1/2013 | P | DONE |
Forrest France
|
|
|
|
FIRE-Conference | 3/19/2013 | 3/19/2013 | 3/19/2013 | A | DONE |
Forrest France
|
|
|
|
BLD-Energy code compliance | 3/11/2013 | 3/12/2013 | 3/12/2013 | A | PASS |
Dave Hannah
|
|
|
dave Phone #: ###-####
|
Plan Modification Accepted | | | 3/6/2013 | | DONE |
Tisha Gallop
|
|
|
plan modifiation started in eplanreview in order to reroute plans to Brian Murphy because he was missed in the original review. No holds place on parcel or permit. No additional sheets will be submitted.
|
Routing PW Drainage | 3/6/2013 | | 3/6/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 3/6/2013 | | 3/6/2013 | | PASS |
Mike Sheppard
|
|
|
|
BLD-Framing/Rough-in | 3/1/2013 | 3/1/2013 | 3/1/2013 | A | PASS |
Dave Hannah
|
|
|
ok to insulate contractor will fix one hour walls around med gas room
|
BLD-Conference | 2/26/2013 | 2/27/2013 | 3/1/2013 | A | PART |
Dave Hannah
|
|
|
please call ahead - dave Phone #: ###-#### met arch and contractor on site they will remove fur down so they can build one hour walls around med gas room;
|
BLD-Framing/Rough-in | 2/21/2013 | 2/22/2013 | 2/22/2013 | A | NR |
Jim Storey
|
|
|
dave Phone #: ###-####
|
BLD-Other | 2/4/2013 | 2/4/2013 | 2/4/2013 | P | PASS |
Dave Hannah
|
|
|
dave - fire rated eaves Phone #: ###-#### east and west side eaves ok to cover
|
BLD-Other | 1/17/2013 | 1/17/2013 | 1/17/2013 | P | PASS |
Dave Hannah
|
|
|
exterior sheer wall inspection >> Inspection requested via web by Dave Bashista
|
BLD-Other | 1/9/2013 | 1/10/2013 | 1/10/2013 | A | DONE |
Dave Hannah
|
|
|
roof nail inspection Phone #: ###-#### >> Inspection requested via web by Dave Bashista roof covered with snow but no inspection needed
|
BLD-Foundation | 12/13/2012 | 12/13/2012 | 12/13/2012 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 12/11/2012 | 12/12/2012 | 12/13/2012 | P | NR |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 12/5/2012 | 12/7/2012 | 12/7/2012 | A | CANC |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/7/2012 | 12/7/2012 | 12/7/2012 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Footing | 12/5/2012 | 12/6/2012 | 12/6/2012 | P | CANC |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Permit Ready to Issue | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan Reviewer's activity | | | 10/26/2012 | | PASS |
John Menard
|
|
|
reviewed and approved structural revisions. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2012 | | DONE |
John Menard
|
|
|
|
Telephone call | | | 10/26/2012 | | DONE |
Tisha Gallop
|
|
|
spoke to Scott Grady from Dave Evans Construction. The initial values are from the GC since arch. is in-house. Told him fees due and still need ACHD and GC form.
|
Plan assigned to (JCM) | 9/5/2012 | | 10/26/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/12/2012 | | 10/26/2012 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 10/12/2012 | | 10/22/2012 | | FAIL |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 10/18/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved requested revisions. JCM
|
Routing - PLUMBING | 10/12/2012 | | 10/16/2012 | | PASS |
Daryl Spivey
|
|
|
Provide RPBP on filtered water.
Per plans and 2003 UPC.
|
1st review completed | | | 10/3/2012 | | FAIL |
John Menard
|
|
|
Building, Structural & Plumbing
|
Routing - PLAN CHECK | 9/5/2012 | | 10/3/2012 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 9/5/2012 | | 9/18/2012 | | FAIL |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 9/5/2012 | | 9/12/2012 | | PASS |
Todd Tucker
|
|
|
|
Routing - PLUMBING | 9/5/2012 | | 9/12/2012 | | FAIL |
Daryl Spivey
|
|
|
Provide complete set of drawings for plumbing and mechanical for mechanical basement and show access.
|
Routing - Addressing | 9/5/2012 | | 9/10/2012 | | PASS |
Terry Records
|
|
|
|
Routing - FIRE | 9/6/2012 | | 9/10/2012 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Route to Impact Fee Review | 9/5/2012 | | 9/7/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 9/6/2012 | | 9/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 9/5/2012 | | 9/6/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/5/2012 | | 9/6/2012 | | PASS |
Kimberly M. Johnson
|
|
|
approved per conditions
|
Pending Assignment by JCM | 9/5/2012 | | 9/5/2012 | | DONE |
John Menard
|
|
|
|
Routing - Design Review | 9/5/2012 | | 9/5/2012 | | PASS |
Josh Wilson
|
|
|
|
Application received | | | 8/23/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2012 10:27AM
|