BLD-Final | 5/21/2013 | 5/22/2013 | 5/22/2013 | A | PASS |
Jim Sly
|
|
|
travis Phone #: ###-#### C/c issued
|
DOC - Permit Finaled | 5/22/2013 | 5/22/2013 | 5/22/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 3/25/2013 | 3/25/2013 | 3/26/2013 | P | PASS |
Jim Sly
|
|
|
TRAVIS Phone #: ###-####
|
BLD-Framing/Rough-in | 3/21/2013 | 3/21/2013 | 3/21/2013 | P | PASS |
Jim Sly
|
|
|
travis Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2013 | 3/19/2013 | 3/19/2013 | P | CANC |
Jim Sly
|
|
|
travis Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2013 | 2/15/2013 | 2/15/2013 | A | PASS |
Jim Sly
|
|
|
Shear inspection--Travis Phone #: ###-####
|
BLD-Framing/Rough-in | 1/2/2013 | 1/3/2013 | 1/3/2013 | A | PART |
Jim Sly
|
|
|
Shear inspection please-Travis Phone #: ###-#### Exterior shear nailing ....OK
|
BLD-Footing | 10/30/2012 | 10/30/2012 | 10/31/2012 | P | PASS |
Jim Sly
|
|
|
Travis Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/30/2012 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 10/5/2012 | | |
|
|
|
|
Plan assigned to (CDM) | 8/30/2012 | 8/30/2012 | 10/5/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 10/5/2012 | | 10/5/2012 | | PASS |
Susan Riggs
|
|
|
|
Routing - MECHANICAL | 10/5/2012 | | 10/5/2012 | | PASS |
Troy James
|
|
|
|
Inspection Record Card- Bld | | | 10/5/2012 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2012 | | |
|
|
|
|
Permit Ready to Issue | | | 10/5/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 10/4/2012 | | 10/4/2012 | | PASS |
Carl D Madsen
|
|
|
New plans were submitted requireing a new plan review and routing to Planning and Mechanical. 10-4-12 CDM
|
Routing - Addressing | 9/7/2012 | | 9/7/2012 | | PASS |
Terry Records
|
|
|
|
1st review completed | | | 9/6/2012 | | |
|
|
|
|
Routing - PLAN CHECK | | | 9/6/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 8/30/2012 | | 8/30/2012 | | FAIL |
Troy James
|
|
|
eplan
|
Intake Approval | | | 8/30/2012 | | PASS |
Christina Prado
|
|
|
|
Route to Impact Fee Review | 8/24/2012 | 8/29/2012 | 8/29/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/29/2012 | | 8/29/2012 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2012 | | 8/29/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/29/2012 | | 8/29/2012 | | FAIL |
April Wing
|
|
|
Site plan and addresses do not match. Talk to Pinnacle and they said they would make the correction.
|
Payment Received | | | 8/28/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | 8/24/2012 | | | |
|
|
|
|
Routing - PLANNING | 9/7/2012 | | | | FAIL |
|
|
|
|