Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-02306
StatusFinaled
Name TAHOE HOMES LLC
Site Address 4283 E HARDESTY COURT
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 2,686 sq. ft., one story single dwelling with 4 bedrooms, 3 bathrooms, approximately 500 sq. ft. of covered patio/porch and a 1,061sq. ft. attached garage per approved plans, plan review report, wall bracing engineering, and any notations. SP-01 zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/1/20134/1/20134/1/2013PPASS
DetailsDave Hannah
plans are by the furnace Phone #: ###-#### >> Inspection requested via web by John Dyche
DOC - Permit Finaled4/1/20134/1/20134/1/2013PPASS
DetailsDave Hannah
DOC - Permit Finaled4/1/20134/1/20134/1/2013PPASS
DetailsDave Hannah
BLD-Energy code compliance1/24/20131/25/20131/25/2013APASS
DetailsDave Hannah
thanks, Ashley Phone #: ###-#### >> Inspection requested via web by Tony Luchini
BLD-Framing/Rough-in1/23/20131/23/20131/23/2013APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by John Dyche
BLD-Wall Bracing12/26/201212/27/201212/28/2012APASS
DetailsDave Hannah
rudy Phone #: ###-####
BLD-Wall Bracing12/27/201212/28/201212/28/2012APASS
DetailsDave Hannah
Leonard would like to meet with the inspector. Please call him at ###-####, it will take him a half hour to get to the site. Leonard has the amended engineering with him. Phone #: ###-#### >> Inspection requested via web by Leonard Dooms
BLD-Foundation11/5/201211/5/201211/6/2012PPASS
DetailsDave Hannah
concrete at 12:30//Anton Phone #: ###-####
BLD-Footing11/2/201211/2/201211/2/2012PPASS
DetailsDave Hannah
alvardo Phone #: ###-####
Issue PAID IN FULL permit  10/16/2012 DONE
OVERRIDE  10/10/2012  
Plan assigned to (CDM) 8/28/201210/10/2012 PASS
DetailsCarl D Madsen
Telephone call  10/10/2012 DONE
lm permit ready fees given
Routing - PLAN CHECK10/10/2012 10/10/2012 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  10/10/2012  
Case Summary (BLD)  10/10/2012 DONE
Inspection Record Card- Bld  10/10/2012 DONE
DetailsChristina Prado
Inspection Record Card- Bld  10/10/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  10/10/2012 DONE
Plan resubmittals received  10/8/2012 DONE
DetailsTisha Gallop
received two copies of plan sheet A4.1 (roof framing); taken to Carl Madsen
1st review completed  10/1/2012 FAIL
Routing - PLAN CHECK9/6/2012 10/1/2012 FAIL
DetailsCarl D Madsen
Wall bracing. E-Mailed applicant 10-1-12 CDM
Routing - MECHANICAL8/31/2012 9/6/2012 PASS
DetailsTroy James
Routing - PLANNING8/29/2012 8/31/2012 PASS
DetailsTodd Tucker
Route to Impact Fee Review8/28/20128/31/20128/29/2012 PASS
DetailsShauna Surgeon
Routing - Addressing8/28/2012 8/29/2012 PASS
DetailsTerry Records
Routing - PUBLIC WORKS8/29/2012 8/29/2012 PASS
DetailsConnie Baumgartner
Application received 8/28/20128/28/2012 DONE
Details
Plans ACCEPTED BY PLAN TECH  8/28/2012 DONE
DetailsChristina Prado
Intake Approval  8/28/2012 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  8/28/2012 DONE
DetailsChristina Prado