CHANGE STATUS TO (FNL) | | | 10/16/2017 | | DONE |
Christina Prado
|
|
|
Per passing inspections
|
Letter of compliance/Occupancy | | | 10/16/2017 | | DONE |
|
|
|
|
BLD-Final | 12/22/2016 | 12/22/2016 | 12/22/2016 | P | PASS |
Dave Hannah
|
|
|
Requesting permit be finaled and closed. Phone #: ###-#### Inspection requested via web by Joe Borelli
|
BLD-Other | 6/25/2015 | 6/26/2015 | 6/26/2015 | A | PASS |
Dave Hannah
|
|
|
Nathan// rise run compliance on pioneer stairs Phone #: ###-####
|
BLD-Conference | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | DONE |
Dave Hannah
|
|
|
Requesting a consult meeting to discuss upcoming JUMP TCO plans. Please stop by the Hoffman Office.
Thanks, Noelle Phone #: ###-#### Inspection requested via web by Noelle Idehara
|
BLD-Other | 6/16/2015 | 6/17/2015 | 6/17/2015 | A | PASS |
Dave Hannah
|
|
|
Pioneer Stairs ONLY (lv. 2- lv. 2.5); Nathan Phone #: ###-####
|
BLD-Conference | 6/10/2015 | 6/11/2015 | 6/12/2015 | A | PASS |
Dave Hannah
|
|
|
Inspect cast-in place Pioneer stair rise/run for first stair section at Level 3. Contact Nate with MCI. ###-####. Phone #: ###-#### Inspection requested via web by Noelle Idehara
|
Plan resubmittals received | | | 9/10/2014 | | DONE |
Christina Prado
|
|
|
Received three sets of deferred submital sheets and calcs for Metal Column Covers
|
BLD-Conference | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | PASS |
Dave Hannah
|
|
|
Requesting a consult with Dave and the special inspector. Please contact Al at ###-####. Phone #: ###-#### Inspection requested via web by Noelle Idehara
|
CHANGE STATUS TO (ISS) | | | 3/6/2014 | | DONE |
Tisha Gallop
|
|
|
picked up approved plan mod, no fees
|
Expiration Notice | 3/5/2014 | 3/26/2014 | 3/5/2014 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2014 | | DONE |
|
|
|
|
Pending Assignment by JCM | 7/18/2013 | | 3/3/2014 | | PASS |
John Menard
|
|
|
|
Plan assigned to (JCM) | 3/28/2013 | | 3/3/2014 | | PASS |
John Menard
|
|
|
1st Review for Plan Mod completed 4/4/2013. JCM
|
Routing Off Site - STRUCTURAL | 11/27/2013 | | 12/6/2013 | | PASS |
|
|
|
Pioneer stair plan mod passed.
|
Routing - PLAN CHECK | 11/21/2013 | | 12/6/2013 | | PASS |
John Menard
|
|
|
Pioneer Stair Plan mod apporved.
|
Plan resubmittals received | | | 11/21/2013 | | DONE |
|
|
|
REceived second submittal for Pioneer stair modification. Calcs and sheet S3-03-A-R.
|
BLD-Concrete | 10/7/2013 | 10/10/2013 | 10/14/2013 | A | PEND |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
BLD-Concrete | 10/7/2013 | 10/8/2013 | 10/9/2013 | A | PEND |
Dave Hannah
|
|
|
Brian Phone #: ###-#### talked with al from strata
|
BLD-Concrete | 9/25/2013 | 9/26/2013 | 9/26/2013 | A | PART |
Dave Hannah
|
|
|
Brian Phone #: ###-#### walked project with al from strata
|
BLD-Foundation | 9/17/2013 | 9/17/2013 | 9/23/2013 | P | PEND |
Dave Hannah
|
|
|
brian Phone #: ###-####
|
Routing Off Site - STRUCTURAL | 8/15/2013 | | 8/30/2013 | | FAIL |
John Menard
|
|
|
|
Telephone call | | | 8/15/2013 | | DONE |
Christina Prado
|
|
|
called Action Couriers for pick up
|
Plan resubmittals received | | | 8/14/2013 | | DONE |
Christina Prado
|
|
|
received three sets of revised structural calcs, response letter and plans marked S3-01-A, S3-03-A-R, S3-51 & S5-01; Plans inserted by arch rep and taken to John for review
|
BLD-Concrete | 7/22/2013 | 7/25/2013 | 7/25/2013 | A | PASS |
Dave Hannah
|
|
|
brian murphy Phone #: ###-####
|
BLD-Concrete | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PASS |
Dave Hannah
|
|
|
brian murphy Phone #: ###-####
|
OVERRIDE | | | 7/11/2013 | | |
|
|
|
|
BLD-Concrete | 7/10/2013 | 7/10/2013 | 7/11/2013 | P | PART |
Dave Hannah
|
|
|
brian Phone #: ###-#### column placement al on site for strata doing inspection
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2013 | | DONE |
John Menard
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/11/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 7/11/2013 | | DONE |
Tisha Gallop
|
|
|
called Noelle and told her plan mod is ready and fee due.
|
Routing - PLAN CHECK | 5/7/2013 | | 5/14/2013 | | PASS |
John Menard
|
|
|
Deferred submittal for post tension concrete. Was reviewed and approved by consulting structural engineer without comment. JCM
|
Plan Reviewer's activity | | | 5/14/2013 | | DONE |
John Menard
|
|
|
I gave the issue copy of the deferred submittal plans, specs. and calculations for the post tension concrete to Noelle Spencer to deliver to the job site. JCM
|
Routing Off Site - STRUCTURAL | 5/7/2013 | | 5/13/2013 | | PASS |
John Menard
|
|
|
Received and e-mail from cosulting structural engineer approving the post-tension concrete deferred submittal without comment. JCM
|
Plan resubmittals received | | | 5/7/2013 | | |
|
|
|
Recieved 2 plan modification applications, 3 copies of post tension calcs, 3 copies of PT-01, PT-02, PT-03, PT-04, PT-05, PT-06, PT-07, PT-08, PT-09, PT-10, PT-11, PT-12, PT-13, PT14, PT-15, PT-16, PT-17, PT-18 and taken to John Menard as a deffered submittal
|
BLD-Conference | 5/1/2013 | 5/2/2013 | 5/6/2013 | A | DONE |
Dave Hannah
|
|
|
joe - 10 am meeting Phone #: ###-####
|
Routing - PLAN CHECK | 3/28/2013 | | 4/24/2013 | | |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 3/28/2013 | | 4/24/2013 | | FAIL |
John Menard
|
|
|
called Action Couriers for plan mod pick up - Received comment list from consulting structural engineer for the plan mod. JCM
|
Plan resubmittals requested | | | 4/24/2013 | | DONE |
John Menard
|
|
|
E-mailed the applicant a copy of the structural review for the plan modification on the Pioneer stair and skylight. JCM
|
Plan Modification Accepted | | | 3/28/2013 | | DONE |
Christina Prado
|
|
|
Plan Mod for changes to cast-in-place Pioneer stair & Pioneer room skylight - Received three sets of structural calcs as well as plans marked S3-02-A, S3-03-A, S3-08-A, S3-51, S4-12, S5-32 & S6-21;Taken to John Menard for review
|
Issue PAID IN FULL permit | | | 12/4/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JCM) | 8/30/2012 | 8/30/2012 | 11/28/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/19/2012 | | 11/28/2012 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2012 | | DONE |
John Menard
|
|
|
|
Inspection Record Card- Bld | | | 11/28/2012 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
Called Noelle to advise permit is ready for pick up pending payment and GC form
|
Permit Ready to Issue | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 11/27/2012 | | DONE |
Christina Prado
|
|
|
Received two copies of plans marked - S0-02, S0-03, S1-01, S1-02, S3-01-A, S3-01-B, S3-02-A, S3-02-C, S3-03-A-R, S3-03-B, S3-03-B-R, S3-03-C-R, S3-04-A-R, S3-04-B, S3-04-B-R, S3-04-C-R, S3-05-A-R, S3-05-B-R, S3-05-C-R, S3-06-A, S3-06-C, S3-07-A, S3-08-A, S4-12, S4-13, S5-01, S5-03, S5-21, S5-22, S5-25, S6-01, S6-11, S6-12 & S6-21; Sheet inserted by Noelle and given back to John for review
|
Routing Off Site - STRUCTURAL | 11/8/2012 | | 11/20/2012 | | PASS |
John Menard
|
|
|
Called Action Courier for pick up @ 8:45am//BAS
Received comments from consulting engineer. The two comments were minor in nature and did not require a response. JCM
|
Plan resubmittals received | | | 11/7/2012 | | DONE |
Tisha Gallop
|
|
|
received resopnse from architect, three copies of structural calcs and three copies of plan sheets S0-02, S0-03, S1-01, S1-02, S3-01-A, S3-01-B, S3-02-A, S3-02-C, S3-03-A-R, S3-03-B, S3-03-B-R, S3-03-C-R, S3-04-A-R, S3-04-B, S3-04-B-R, S3-04-C-R, S3-05-A-R, S3-05-B-R, S3-05-C-R, S3-06-A, S3-06-C, S3-07-A, S3-08-A, S4-12, S4-13, S5-01, S5-03, S5-21, S5-22, S5-25, S6-01, S6-11, S6-12, S6-21; inserted by arch rep and taken back to John Menard.
|
Route to Impact Fee Review | 10/16/2012 | 10/19/2012 | 10/19/2012 | | PASS |
Cindy M. Gould
|
|
|
will put the impact fees on the shell and core permit cmg
|
Routing - FIRE | 10/15/2012 | 10/15/2012 | 10/19/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached for this permit. Subsequent plans will have Fire Comments attached.
|
1st review completed | | | 10/19/2012 | | FAIL |
|
|
|
Failed Structural
|
Plan resubmittals requested | | | 10/16/2012 | | DONE |
John Menard
|
|
|
E-mailed the applicant a copy of the structural review requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/10/2012 | | 10/15/2012 | | FAIL |
John Menard
|
|
|
9-10-12 called Action Couriers for pick up - Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 9/5/2012 | | 10/15/2012 | | |
John Menard
|
|
|
John Menard
|
Routing - PLANNING | 9/4/2012 | | 9/5/2012 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH10-00178 and subsequent work sessions.
|
Routing - PUBLIC WORKS | 8/30/2012 | | 9/4/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/4/2012 | | 9/4/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Refer to ESC12-00403
|
Routing - Addressing | 8/31/2012 | | 8/31/2012 | | PASS |
Terry Records
|
|
|
|
Routing PW Sewer Rating | 8/31/2012 | | 8/31/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 8/31/2012 | | 8/31/2012 | | PASS |
Brian Murphy
|
|
|
|
Application received | | 8/29/2012 | 8/30/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 8/30/2012 | | 8/30/2012 | | PASS |
Dave Abo
|
|
|
PARCEL "J' OF ROS #9185. Boise City ROS12-00014.
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/29/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | | | | | |
John Menard
|
|
|
|