BLD-Final | 8/13/2013 | 8/13/2013 | 8/19/2013 | P | DONE |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
BLD-Final | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
DOC - Permit Finaled | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 8/5/2013 | 8/5/2013 | 8/5/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved engineers project approval letter. Project is compelte and occupancy is approved. Jason Taylor ###-####
|
Plan resubmittals received | | | 7/31/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 7/31/2013 | | 7/31/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Energy code compliance | 2/19/2013 | 2/20/2013 | 2/20/2013 | A | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
BLD-Framing/Rough-in | 2/11/2013 | 2/12/2013 | 2/12/2013 | A | PASS |
Tom Arcoraci
|
|
|
Eric Phone #: ###-####
|
Plan resubmittals received | | | 2/11/2013 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 2/11/2013 | | 2/11/2013 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
CHANGE STATUS TO (ISS) | | | 2/11/2013 | | DONE |
|
|
|
|
BLD-Wall Bracing | 1/10/2013 | 1/10/2013 | 1/14/2013 | P | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
BLD-Wall Bracing | 1/11/2013 | 1/11/2013 | 1/14/2013 | A | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
BLD-Foundation | 11/1/2012 | 11/2/2012 | 11/2/2012 | A | PASS |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
BLD-Footing | 10/10/2012 | 10/11/2012 | 10/12/2012 | P | PASS |
Dave Hannah
|
|
|
BOB Phone #: ###-####
|
Inspection Record Card- Bld | | | 9/28/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/28/2012 | | DONE |
Tisha Gallop
|
|
|
called Jeff and told him permit is ready and fees
|
Issue PAID IN FULL permit | | | 9/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 8/29/2012 | 8/29/2012 | 9/27/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/18/2012 | | 9/27/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/27/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 9/27/2012 | | DONE |
|
|
|
|
Routing - FIRE | 9/17/2012 | | 9/18/2012 | | PASS |
Scott Arellano
|
|
|
The driveway width must be 20 feet to comply with Fire Department Vehicle Access requirements.
|
Routing - MECHANICAL | 9/17/2012 | | 9/17/2012 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 9/11/2012 | | 9/12/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 9/5/2012 | | 9/11/2012 | | FAIL |
Troy James
|
|
|
sent email to TML
|
Routing - PLANNING | 9/4/2012 | | 9/5/2012 | | PASS |
David Moser
|
|
|
CFH12-24 David Moser
|
Routing - PUBLIC WORKS | 8/31/2012 | | 9/4/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 8/29/2012 | 9/4/2012 | 8/31/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Grading-Hillside | 8/30/2012 | | 8/31/2012 | | PASS |
Terry Records
|
|
|
|
Routing - Addressing | 8/30/2012 | | 8/31/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 8/29/2012 | 8/30/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/29/2012 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/29/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 9/12/2012 | | | | |
Carl D Madsen
|
|
|
|