Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-02334
StatusFinaled
Name PERKINS CONSTRUCTION
Site Address 12598 W EXPLORER DR
Project NameICON CREDIT UNION
Customer Number 
ePlanReviewNo
Description
Icon Credit Union - To construct a new 4,495 square foot, one story, wood framed credit union office building with covered drive-thru teller. The drive-thru teller area is approximately 960 square feet. This permit also includes related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  10/3/2013 DONE
First Notice 7/20/20138/1/2013 DONE
Faxed 8/1/13
Permanent Occupancy  7/10/2013 DONE
DetailsChristina Prado
BLD-Final6/28/20137/1/20137/1/2013PPASS
DetailsJim Sly
Please call 30mins ahead - Harvey Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection7/1/20137/1/20137/1/2013PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection6/28/20137/1/20137/1/2013AFAIL
DetailsTroy Cobbley
Duct detector is missing the sample tubes and all of them are not wired to provide immediate shut down as required byIMC
PubWorks Occupancy Approval7/1/20137/1/20137/1/2013 DONE
DetailsTiffany Lowery
BLD-Conference6/28/20136/28/20136/28/2013PDONE
DetailsJim Sly
Nick Phone #: ###-####
FIRE-Final Inspection6/27/20136/28/20136/28/2013AFAIL
DetailsTroy Cobbley
Repair the exit sign over the main exit door, repair the emergency lighting at the north end of the lobby and provide testing for the three duct smoke detectors.
Zoning Approval6/28/20136/28/20136/28/2013 DONE
DetailsAndrea Tuning
BLD-Ceiling Grid Inspection5/29/20135/30/20135/30/2013APASS
DetailsMike Jordan
Nick Phone #: ###-####. Grid ok.
BLD-Energy code compliance3/14/20133/14/20133/14/2013PPASS
DetailsJim Sly
nick Phone #: ###-####
BLD-Framing/Rough-in3/11/20133/11/20133/11/2013PPASS
DetailsJim Sly
Phone #: ###-####
BLD-Framing/Rough-in3/7/20133/7/20133/8/2013PNR
DetailsJim Sly
nick Phone #: ###-####
Walk thru.....with contractor.
BLD-Wall Bracing2/15/20132/19/20132/19/2013APASS
DetailsJim Sly
Nick Phone #: ###-####
BLD-Footing12/5/201212/6/201212/6/2012APART
DetailsJim Sly
Rebar - Ed Phone #: ###-####
Internal....and Drive thru (column) footings OK pending MTI inspection, tests and approvals.
BLD-Foundation11/7/201211/8/201211/8/2012APASS
DetailsJim Sly
Nick Phone #: ###-####
OK pending MTI insp, tests and approvals.
BLD-Footing11/5/201211/5/201211/5/2012PPASS
DetailsJim Sly
late afternoon - Nick Phone #: ###-####
OK pending MTI special insp, tests and approvals.
Issue PAID IN FULL permit  10/12/2012 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK10/3/2012 10/11/2012 PASS
DetailsJohn Menard
Plan Reviewer's activity  10/11/2012 PASS
DetailsJohn Menard
Reviewed and approved structural and nonstructural revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  10/11/2012 DONE
DetailsJohn Menard
Print Occupancy Form  10/11/2012 DONE
DetailsBarbara Stitt
Telephone call  10/11/2012 DONE
DetailsChristina Prado
called Mike to advise permit is ready, gave fees due and advised GC & ACHD are required prior to issuace
Permit Ready to Issue  10/11/2012 DONE
DetailsChristina Prado
Plan assigned to (JCM)8/31/2012 10/11/2012 PASS
DetailsJohn Menard
Routing - PLANNING Land Div10/10/2012 10/10/2012 PASS
DetailsDave Abo
Resolution No. 21858 signed on September 11, 2012 by Mayor for partial vacation of Boise City Sewer Easement on Lot 11 of Research Center No. 3 Subdivision.
Plan resubmittals received  10/8/2012  
Recieved 2 copies of sheets A3.1, A5.0, A5.1, A5.3, A5.4, A5.5, A6.2, A6.3, A7.1 and taken to John Menard
Route to Impact Fee Review10/1/201210/4/201210/5/2012 PASS
DetailsCindy M. Gould
Routing - FIRE10/1/201210/1/201210/3/2012 PASS
DetailsScott Arellano
Attached comments to plans.
1st review completed  10/3/2012 FAIL
Failed plan check, planning, and structural.
Plan resubmittals requested  10/1/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals received  10/1/2012 DONE
DetailsTisha Gallop
received three copies of structural review response, structural calculations and plan sheet S2.2; inserted by arch. rep. and taken back to Fire review.
Routing - PLAN CHECK8/31/2012 10/1/2012 FAIL
DetailsJohn Menard
Routing - PLUMBING9/13/2012 9/14/2012 PASS
DetailsDaryl Spivey
Per plans and 2003 UPC.
Routing - PLANNING9/14/2012 9/14/2012 PASS
DetailsDavid Moser
Plan resubmittals requested  9/14/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing - Design Review9/14/2012 9/14/2012 PASS
DetailsAndrea Tuning
Routing Off Site - STRUCTURAL8/31/2012 9/13/2012 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PUBLIC WORKS9/4/2012 9/12/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment9/12/2012 9/12/2012 PASS
DetailsKimberly M. Johnson
Routing PW Sewer Rating9/12/2012 9/12/2012 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste9/10/2012 9/10/2012 PASS
DetailsPeter J. McCullough
Approved for carts only, no dumpsters allowed.
Routing PW Sewer Design9/7/2012 9/10/2012 PASS
DetailsMike Sheppard
Connect onto existing service provided
Routing PW Drainage9/5/2012 9/6/2012 PASS
DetailsBrian Murphy
Routing - Addressing9/4/2012 9/4/2012 PASS
DetailsTerry Records
Application received 8/31/20128/31/2012 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  8/31/2012 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  8/31/2012 DONE
DetailsTisha Gallop
Intake Approval  8/31/2012 PASS
DetailsSam Zahorka
Pending Assignment by JCM8/31/2012 8/31/2012 DONE
DetailsJohn Menard
Routing - PLANNING Land Div8/31/2012 8/31/2012 FAIL
DetailsDave Abo
Prior to issuance of building permit. Resolution must be recorded vacating 8 feet of Boise City sewer easement per SOS12-00008.
Telephone call  8/31/2012 DONE
DetailsTisha Gallop
called Action Couriers for pick up.