Print Statement | | | 10/3/2013 | | DONE |
|
|
|
|
First Notice | | 7/20/2013 | 8/1/2013 | | DONE |
|
|
|
Faxed 8/1/13
|
Permanent Occupancy | | | 7/10/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 6/28/2013 | 7/1/2013 | 7/1/2013 | P | PASS |
Jim Sly
|
|
|
Please call 30mins ahead - Harvey Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 6/28/2013 | 7/1/2013 | 7/1/2013 | A | FAIL |
Troy Cobbley
|
|
|
Duct detector is missing the sample tubes and all of them are not wired to provide immediate shut down as required byIMC
|
PubWorks Occupancy Approval | 7/1/2013 | 7/1/2013 | 7/1/2013 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Conference | 6/28/2013 | 6/28/2013 | 6/28/2013 | P | DONE |
Jim Sly
|
|
|
Nick Phone #: ###-####
|
FIRE-Final Inspection | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | FAIL |
Troy Cobbley
|
|
|
Repair the exit sign over the main exit door, repair the emergency lighting at the north end of the lobby and provide testing for the three duct smoke detectors.
|
Zoning Approval | 6/28/2013 | 6/28/2013 | 6/28/2013 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Ceiling Grid Inspection | 5/29/2013 | 5/30/2013 | 5/30/2013 | A | PASS |
Mike Jordan
|
|
|
Nick Phone #: ###-####. Grid ok.
|
BLD-Energy code compliance | 3/14/2013 | 3/14/2013 | 3/14/2013 | P | PASS |
Jim Sly
|
|
|
nick Phone #: ###-####
|
BLD-Framing/Rough-in | 3/11/2013 | 3/11/2013 | 3/11/2013 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 3/7/2013 | 3/7/2013 | 3/8/2013 | P | NR |
Jim Sly
|
|
|
nick Phone #: ###-#### Walk thru.....with contractor.
|
BLD-Wall Bracing | 2/15/2013 | 2/19/2013 | 2/19/2013 | A | PASS |
Jim Sly
|
|
|
Nick Phone #: ###-####
|
BLD-Footing | 12/5/2012 | 12/6/2012 | 12/6/2012 | A | PART |
Jim Sly
|
|
|
Rebar - Ed Phone #: ###-#### Internal....and Drive thru (column) footings OK pending MTI inspection, tests and approvals.
|
BLD-Foundation | 11/7/2012 | 11/8/2012 | 11/8/2012 | A | PASS |
Jim Sly
|
|
|
Nick Phone #: ###-#### OK pending MTI insp, tests and approvals.
|
BLD-Footing | 11/5/2012 | 11/5/2012 | 11/5/2012 | P | PASS |
Jim Sly
|
|
|
late afternoon - Nick Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|
Issue PAID IN FULL permit | | | 10/12/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 10/3/2012 | | 10/11/2012 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 10/11/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2012 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/11/2012 | | DONE |
Christina Prado
|
|
|
called Mike to advise permit is ready, gave fees due and advised GC & ACHD are required prior to issuace
|
Permit Ready to Issue | | | 10/11/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JCM) | 8/31/2012 | | 10/11/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 10/10/2012 | | 10/10/2012 | | PASS |
Dave Abo
|
|
|
Resolution No. 21858 signed on September 11, 2012 by Mayor for partial vacation of Boise City Sewer Easement on Lot 11 of Research Center No. 3 Subdivision.
|
Plan resubmittals received | | | 10/8/2012 | | |
|
|
|
Recieved 2 copies of sheets A3.1, A5.0, A5.1, A5.3, A5.4, A5.5, A6.2, A6.3, A7.1 and taken to John Menard
|
Route to Impact Fee Review | 10/1/2012 | 10/4/2012 | 10/5/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 10/1/2012 | 10/1/2012 | 10/3/2012 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 10/3/2012 | | FAIL |
|
|
|
Failed plan check, planning, and structural.
|
Plan resubmittals requested | | | 10/1/2012 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Plan resubmittals received | | | 10/1/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of structural review response, structural calculations and plan sheet S2.2; inserted by arch. rep. and taken back to Fire review.
|
Routing - PLAN CHECK | 8/31/2012 | | 10/1/2012 | | FAIL |
John Menard
|
|
|
|
Routing - PLUMBING | 9/13/2012 | | 9/14/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
|
Routing - PLANNING | 9/14/2012 | | 9/14/2012 | | PASS |
David Moser
|
|
|
|
Plan resubmittals requested | | | 9/14/2012 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - Design Review | 9/14/2012 | | 9/14/2012 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 8/31/2012 | | 9/13/2012 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing - PUBLIC WORKS | 9/4/2012 | | 9/12/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/12/2012 | | 9/12/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Sewer Rating | 9/12/2012 | | 9/12/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 9/10/2012 | | 9/10/2012 | | PASS |
Peter J. McCullough
|
|
|
Approved for carts only, no dumpsters allowed.
|
Routing PW Sewer Design | 9/7/2012 | | 9/10/2012 | | PASS |
Mike Sheppard
|
|
|
Connect onto existing service provided
|
Routing PW Drainage | 9/5/2012 | | 9/6/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 9/4/2012 | | 9/4/2012 | | PASS |
Terry Records
|
|
|
|
Application received | | 8/31/2012 | 8/31/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/31/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/31/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/31/2012 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCM | 8/31/2012 | | 8/31/2012 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 8/31/2012 | | 8/31/2012 | | FAIL |
Dave Abo
|
|
|
Prior to issuance of building permit. Resolution must be recorded vacating 8 feet of Boise City sewer easement per SOS12-00008.
|
Telephone call | | | 8/31/2012 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up.
|