First Notice | | 1/27/2013 | 1/28/2013 | | DONE |
|
|
|
Mailed 1-28-13
|
Permanent Occupancy | | | 1/17/2013 | | DONE |
|
|
|
|
BLD-Final | 1/15/2013 | 1/16/2013 | 1/16/2013 | P | PASS |
Jim Storey
|
|
|
Robert please call before going out Phone #: ###-####
|
FIRE-Final Inspection | 1/15/2013 | 1/15/2013 | 1/15/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
FIRE-Sprinkler Rough-in | 1/2/2013 | 1/2/2013 | 1/2/2013 | A | NR |
Forrest France
|
|
|
|
BLD-Final | 12/24/2012 | 12/24/2012 | 12/24/2012 | A | CANC |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 12/24/2012 | 12/24/2012 | 12/24/2012 | A | PASS |
Jim Storey
|
|
|
|
Plan assigned to (TLW) | 12/20/2012 | | 12/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 12/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Override - Parcel Holds | | | 12/21/2012 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/21/2012 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/21/2012 | | |
|
|
|
|
Print Occupancy Form | | | 12/21/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/21/2012 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 12/20/2012 | | |
|
|
|
Plan modification accepted for one of the small single toilet rooms to include a shower. A plan modification application and 2 sheet A3.1 were submitted. No new cert of value
|
BLD-Conference | 11/29/2012 | 12/3/2012 | 12/3/2012 | A | PASS |
Jim Storey
|
|
|
robert Phone #: ###-#### - call 30 mins prior
|
CHANGE STATUS TO (ISS) | | | 11/27/2012 | | DONE |
Darla L Downs
|
|
|
|
Issue PAID IN FULL permit | | | 11/27/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/27/2012 | | DONE |
|
|
|
|
Routing - FIRE | 9/27/2012 | | 10/2/2012 | | PASS |
Scott Arellano
|
|
|
Attached plan review report to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 9/12/2012 | | 10/2/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Permit Ready to Issue | | | 10/2/2012 | | DONE |
Darla L Downs
|
|
|
|
Routing - PLAN CHECK | 9/27/2012 | | 9/27/2012 | | PASS |
Tim L. Woodard
|
|
|
Resubmittals approved. TLW
|
1st review completed | | | 9/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/12/2012 | | 9/20/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved in E plan review. TLW
|
Routing - PUBLIC WORKS | 9/12/2012 | | 9/20/2012 | | PASS |
Connie Baumgartner
|
|
|
Approved in eplan review
|
Routing - FIRE | 9/12/2012 | | 9/18/2012 | | FAIL |
Scott Arellano
|
|
|
Attached IFC plan review comments to case and sent to Architect.
|
Routing - Addressing | 9/12/2012 | | 9/13/2012 | | PASS |
April Wing
|
|
|
|
Routing PW Environmental | 9/12/2012 | | 9/12/2012 | | PASS |
Walt Baumgartner
|
|
|
|
Routing PW Sewer Rating | 9/12/2012 | | 9/12/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 9/12/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Payment Received | | | 9/11/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Telephone call | | | 9/11/2012 | | DONE |
Christina Prado
|
|
|
sent Scott email giving plan intake fees due
|
Application received | | | 9/5/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2012 7:49AM
|