Third Notice | | 11/5/2013 | 4/1/2014 | | DONE |
|
|
|
|
Second Notice | | 10/20/2013 | 10/31/2013 | | DONE |
|
|
|
11-8-13 from yellow sticker on returned mail envelope David Thompsom P O BOX 5677 is Temporarily Away. I will resend this notice again December 8th ///dld
|
First Notice | | 8/3/2013 | 10/10/2013 | | DONE |
|
|
|
Faxed 10-1-13
|
BLD-Final | 7/23/2013 | 7/24/2013 | 7/24/2013 | A | PASS |
Jim Sly
|
|
|
Ken Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 7/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
Temporary Occupancy | 5/6/2013 | 8/4/2013 | 5/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/3/2013 | 5/3/2013 | 5/3/2013 | P | PART |
Jim Sly
|
|
|
RICK Phone #: ###-#### OK for Temp Occ. OK for Perm Occ. when rubber cove base is installed in restrooms and in Kitchen.
|
Zoning Approval | 5/3/2013 | 5/3/2013 | 5/3/2013 | | DONE |
Joshua Johnson
|
|
|
|
FIRE-Final Inspection | 4/26/2013 | 4/29/2013 | 4/29/2013 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Door #2, west facing door, per the plans is required to have panice hardware. Before the building inspection the door is to be provided with the approved hardware or the keyed hardware needs to be approved by plan review.
|
BLD-Framing/Rough-in | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | PASS |
Jim Sly
|
|
|
rick Phone #: ###-####
|
BLD-Conference | 2/8/2013 | 2/11/2013 | 2/11/2013 | A | DONE |
Jim Sly
|
|
|
rick Phone #: ###-####
|
BLD-Foundation | 2/7/2013 | 2/8/2013 | 2/8/2013 | A | PASS |
Jim Sly
|
|
|
greg Phone #: ###-####
|
BLD-Footing | 2/5/2013 | 2/6/2013 | 2/7/2013 | A | PASS |
Jim Sly
|
|
|
late morning - Greg Phone #: ###-####
|
OVERRIDE | | | 12/21/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 12/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 12/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/19/2012 | | DONE |
Tisha Gallop
|
|
|
e-mailed Liz at Matter Arch.; need Cert of Value, RP & ACHD.
|
Plan assigned to (CJW) | 9/14/2012 | 9/14/2012 | 11/13/2012 | | PASS |
Carl Westfall
|
|
|
IDAHO COFFEE & YOGURT (20 days - Oct 9) ePlanReview case
|
Routing - PLAN CHECK | 11/7/2012 | | 11/13/2012 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines" after the 2nd IBC review.
|
Routing - FIRE | 11/9/2012 | | 11/13/2012 | | DONE |
Scott Arellano
|
|
|
Move "red lines" on Sheet A1.1 to the most recent version.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/13/2012 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/7/2012 | | |
|
|
|
|
Routing - PLAN CHECK | 9/14/2012 | | 10/10/2012 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on Oct 8 and was finished on Oct 10. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 9/14/2012 | | 10/10/2012 | | PASS |
Connie Baumgartner
|
|
|
Wasn't discovered until 10-10-12 that PW routing had not occured. Routing and review then happened in record time. CJW
|
1st review completed | | | 10/10/2012 | | FAIL |
|
|
|
Failed Building.
|
Routing PW Sewer Rating | 10/10/2012 | | 10/10/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 10/10/2012 | | 10/10/2012 | | PASS |
|
|
|
|
Route to Impact Fee Review | 9/14/2012 | 9/19/2012 | 9/25/2012 | | PASS |
Cindy M. Gould
|
|
|
TENANT IMPROVEMENT
|
Routing - PLANNING | 9/14/2012 | | 9/24/2012 | | PASS |
Joshua Johnson
|
|
|
Josh Johnson - CUP09-00049 & CVA09-00026
|
Routing - Design Review | 9/14/2012 | | 9/24/2012 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - DRH09-00246
|
Routing - FIRE | 9/14/2012 | | 9/20/2012 | | PASS |
Scott Arellano
|
|
|
No attached plan review report. Plans are approved with comments.
|
Routing - PLUMBING | 9/14/2012 | | 9/17/2012 | | PASS |
Bill VanDegrift
|
|
|
Per plans and 2003 UPC.
|
Routing - Addressing | 9/14/2012 | | 9/14/2012 | | PASS |
April Wing
|
|
|
|
Routing - Erosion and Sediment | 9/14/2012 | | 9/14/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Plan Reviewer's activity | | | 9/14/2012 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD for evaluation of impact fees. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
|
Intake Approval | | | 9/12/2012 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Alexandra DeYoung and plan review fees paid.
|
Intake Approval | | | 9/7/2012 | | FAIL |
Tim L. Woodard
|
|
|
Bill;
Please review the drawings for compliance with the Electronic submittal standards. The only issue that I saw with that would be the required stamping area on one of your sheets and all of the MEP sheets.
Secondly, please correct all items bracketed on the #520 Major TI Submittal Checklist that was uploaded into the documents folder. As we discussed over the phone this will be a Major TI.
Thanks and call with any questions. TIM W
|
Application received | | | 9/5/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2012 4:44PM
|
Routing Off Site - C.D.H | | | 8/20/2012 | | PASS |
|
|
|
Drawings stamped by Deb Carney before they were uploaded by the Architect.
|