Permanent Occupancy | | | 12/24/2015 | | DONE |
|
|
|
|
BLD-Final | 1/20/2014 | 1/21/2014 | 1/21/2014 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike Wilson final ok pending hvac sign off
|
FIRE-Final Inspection | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety okayed for final. Balance of trade related work finished.
|
FIRE-Conference | 11/29/2013 | 11/29/2013 | 11/29/2013 | P | DONE |
Forrest France
|
|
|
Regarding items to be finished prior to final.
|
BLD-Final | 11/22/2013 | 11/25/2013 | 11/25/2013 | P | PASS |
Jim Storey
|
|
|
Call prior to going Phone #: 8711581 >> Inspection requested via mobile web by Mike Wilson or Brandon F temp ok
|
FIRE-Final Inspection | 11/25/2013 | 11/25/2013 | 11/25/2013 | P | PART |
Forrest France
|
|
|
Final pending project related fire alarm permit work. TCO approved for a period of 30 days per agreement.
|
FIRE-Final Inspection | 11/21/2013 | 11/22/2013 | 11/25/2013 | A | NR |
Forrest France
|
|
|
Final pending project related fire alarm and fire sprinkler permit finals.
|
Zoning Approval | 11/21/2013 | 11/22/2013 | 11/22/2013 | | PASS |
Josh Wilson
|
|
|
|
Plan Reviewer's activity | | | 10/23/2013 | | DONE |
John Menard
|
|
|
After discussions with Bill Vandegrift, I have approved the submitted roof drainage calculations. JCM
|
Plan Modification Accepted | | | 10/15/2013 | | DONE |
Tisha Gallop
|
|
|
plan mod workflow started to reconfigure the roof drainage that was submitted under the deferred submittals.
|
BLD-Framing/Rough-in | 10/1/2013 | 10/2/2013 | 10/2/2013 | A | PASS |
Jim Storey
|
|
|
West and South Exterior wall framing on stair #1 for exterior dense glass install Phone #: ###-#### >> Inspection requested via web by Mike Wilson
|
BLD-Framing/Rough-in | 9/12/2013 | 9/16/2013 | 9/16/2013 | A | PASS |
Jim Storey
|
|
|
Big D roof framing inspection on East Half Phone #: ###-#### >> Inspection requested via web by Mike Wilson
|
BLD-Framing/Rough-in | 8/19/2013 | 8/20/2013 | 8/20/2013 | P | PASS |
Jim Storey
|
|
|
Exterior wall framing for cover on Stair #2 Phone #: ###-#### >> Inspection requested via web by Mike Wilson west stair framing.
|
BLD-Framing/Rough-in | 7/23/2013 | 7/24/2013 | 7/24/2013 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-#### roof framing in progress ok/ reports ok
|
BLD-Framing/Rough-in | 7/23/2013 | 7/23/2013 | 7/23/2013 | P | DEFR |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
Routing - PLAN CHECK | 5/31/2013 | | 6/13/2013 | | PASS |
John Menard
|
|
|
|
Plan assigned to (JCM) | 6/13/2013 | | 6/13/2013 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2013 | | DONE |
John Menard
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/13/2013 | | DONE |
Tisha Gallop
|
|
|
permit was changed to rev status when deferred submittals routed to Plan Review. Deferred submittal approved, per JCM no fees due.
|
Routing Off Site - STRUCTURAL | 5/31/2013 | | 6/10/2013 | | PASS |
John Menard
|
|
|
|
Plan Modification Accepted | | | 5/30/2013 | | DONE |
Tisha Gallop
|
|
|
started plan mod workflow in eplanreveiw for deferred submittal.
|
BLD-Concrete | 5/15/2013 | 5/16/2013 | 5/16/2013 | P | PASS |
Jim Storey
|
|
|
Phone #: 8711581 >> Inspection requested via mobile web by Mike Wilson 3rd floor center west ok to place// west stair fo exit of old bldg. ok to use to maintane exit stairs for demo of south west exit stair.
|
BLD-Concrete | 4/30/2013 | 5/1/2013 | 5/1/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: 8711581 >> Inspection requested via mobile web by Mike Wilson west end 1st elavated deck ok
|
BLD-Concrete | 4/19/2013 | 4/22/2013 | 4/22/2013 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: 8711581 >> Inspection requested via mobile web by Mike Wilson
|
BLD-Concrete | 3/13/2013 | 3/14/2013 | 3/14/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: 8711581 >> Inspection requested via mobile web by Mike Wilson
|
BLD-Foundation | 2/27/2013 | 2/28/2013 | 2/28/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: 2088711581 >> Inspection requested via mobile web by Mike Wilson pending si report
|
BLD-Footing | 2/20/2013 | 2/21/2013 | 2/21/2013 | P | PASS |
Jim Storey
|
|
|
Phone #: 2088711581 >> Inspection requested via mobile web by Mike Wilson
|
BLD-Footing | 2/8/2013 | 2/11/2013 | 2/11/2013 | P | PASS |
Jim Storey
|
|
|
Phone #: 2088711581 >> Inspection requested via mobile web by Mike Wilson
|
Plan Reviewer's activity | | | 2/1/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved deferred submittal for the precast concrete stair tower. JCM
|
Print Occupancy Form | | | 12/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 12/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 12/5/2012 | | |
|
|
|
|
Telephone call | | | 12/5/2012 | | DONE |
Christina Prado
|
|
|
E-mailed Brandon fees due and ACHD requirements
|
Permit Ready to Issue | | | 12/5/2012 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2012 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 10/2/2012 | | 12/4/2012 | | PASS |
John Menard
|
|
|
|
Routing - Erosion and Sediment | 12/3/2012 | | 12/3/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - PLAN CHECK | 11/2/2012 | | 11/13/2012 | | PASS |
John Menard
|
|
|
|
Routing - AIRPORT | 11/13/2012 | | 11/13/2012 | | |
John Menard
|
|
|
Received and e-mail from Matt Petija indicating that he did not need to review this project. JCM
|
Routing Off Site - STRUCTURAL | 11/2/2012 | | 11/12/2012 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 11/2/2012 | | 11/9/2012 | | PASS |
Scott Arellano
|
|
|
Attached updated Fire Comments to plans. These plan review comments are part of the approved building plan set and required to be onsite.
|
Routing - Erosion and Sediment | 11/2/2012 | | 11/2/2012 | | FAIL |
Kimberly M. Johnson
|
|
|
Need SWPPP or ESC plan submitted. TAlked to Hummel Architects.
|
Plan resubmittals requested | | | 10/25/2012 | | DONE |
John Menard
|
|
|
Requested revisions through ProjectDox. JCM
|
1st review completed | | | 10/25/2012 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/2/2012 | | 10/25/2012 | | FAIL |
John Menard
|
|
|
|
Route to Impact Fee Review | 10/2/2012 | | 10/19/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 10/2/2012 | | 10/16/2012 | | FAIL |
John Menard
|
|
|
|
Routing PW Drainage | 10/8/2012 | | 10/8/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 10/2/2012 | | 10/8/2012 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Routing - PUBLIC WORKS | 10/2/2012 | | 10/5/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 10/2/2012 | | 10/3/2012 | | FAIL |
Kimberly M. Johnson
|
|
|
Need submittal of ESC narrative or SWPPP.
|
Routing - Addressing | 10/2/2012 | | 10/3/2012 | | PASS |
Terry Records
|
|
|
|
Routing - Design Review | 10/2/2012 | | 10/3/2012 | | PASS |
Josh Wilson
|
|
|
OK per DRH12-00229
|
Pending Assignment by JCM | 10/2/2012 | | 10/2/2012 | | DONE |
John Menard
|
|
|
|
Routing - PLUMBING | 10/2/2012 | | 10/2/2012 | | PASS |
Daryl Spivey
|
|
|
per plans and 2003 upc
|
Routing - PLANNING Land Div | 10/2/2012 | | 10/2/2012 | | PASS |
Dave Abo
|
|
|
Parcel is over 5 acres.
|
(F) Reprint permit | | | 10/1/2012 | | DONE |
|
|
|
|
Application received | | | 9/6/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2012 1:09PM
|