Second Notice | | 8/10/2013 | 8/16/2013 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | 7/25/2013 | 7/25/2013 | 7/31/2013 | | DONE |
Jim Sly
|
|
|
mailed 8/1
|
PubWorks Occupancy Approval | 7/26/2013 | 7/26/2013 | 7/26/2013 | | DONE |
Brian Murphy
|
|
|
|
BLD-Final | 7/25/2013 | 7/26/2013 | 7/25/2013 | A | PASS |
Jim Sly
|
|
|
brandon Phone #: ###-#### I got a verbal From Brian Murphy for the Public Works Final.
|
DOC - Permit Finaled | 7/25/2013 | 7/25/2013 | 7/25/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | NR |
Jim Sly
|
|
|
need to close out grading permit...you finaled the new building under Bld12-02045 Called Dave .........Told him to get Public Works final......... Then call for Erosion control and Structural final.
|
BLD-Ceiling Grid Inspection | 4/23/2013 | 4/24/2013 | 4/24/2013 | A | CANC |
Mike Jordan
|
|
|
jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/17/2013 | 4/17/2013 | 4/17/2013 | P | PART |
Jim Sly
|
|
|
jeff Phone #: ###-#### Select rooms...... OK
|
BLD-Framing/Rough-in | 2/28/2013 | 3/1/2013 | 3/1/2013 | A | PASS |
Jim Sly
|
|
|
jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 1/10/2013 | 1/10/2013 | 1/11/2013 | P | PART |
Jim Sly
|
|
|
Jeff phone Engineer provided fix for cross bracing installed in 2pcs on shear panels. South 3rd of bldg OK to cover on exterior after fix.
|
BLD-Framing/Rough-in | 1/8/2013 | 1/9/2013 | 1/10/2013 | A | PEND |
Jim Sly
|
|
|
Jeff ###-#### Waiting for fix from Engineer of record for shear bracing.
|
BLD-Framing/Rough-in | 1/7/2013 | 1/8/2013 | 1/8/2013 | A | FAIL |
Jim Sly
|
|
|
Jeff Phone #: ###-#### Structural engineer to OK cross bracing at shear panels.....in 2 pieces in lieu of 1 pc. If no approval....provide fix.
|
BLD-Footing | 11/6/2012 | 11/6/2012 | 11/7/2012 | P | PART |
Jim Sly
|
|
|
Jeff Phone #: ###-#### East (wall) footing only OK pending MTI special inspection, tests and approvals.
|
Issue PAID IN FULL permit | | | 9/18/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/17/2012 | | DONE |
Tisha Gallop
|
|
|
e-mailed Brandon/Kreizenbeck permit is ready and fees due.
|
Application received | | 9/7/2012 | 9/7/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (LEG) Tisha | 9/7/2012 | | 9/7/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 9/7/2012 | | 9/7/2012 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLUMBING | 9/7/2012 | | 9/7/2012 | | PASS |
Ron Hill
|
|
|
These samd plans were reviewed and approved under BLD12-02045. These were broken out just for Grading and Utilities. RmH
|
Routing - PLANNING | 9/7/2012 | | 9/7/2012 | | PASS |
Josh Wilson
|
|
|
Landscape plan not for construction- to be revised per BLD12-02045
|
Routing - PUBLIC WORKS | | | 9/7/2012 | | PASS |
|
|
|
These samd plans were reviewed and approved under BLD12-02045. These were broken out just for Grading and Utilities. RmH
|
Routing - Erosion and Sediment | 9/7/2012 | | 9/7/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Ref ESC12-00783
|
Routing - FIRE | | | 9/7/2012 | | PASS |
Scott Arellano
|
|
|
|
Routing - PLANNING Land Div | 9/7/2012 | | 9/7/2012 | | PASS |
Dave Abo
|
|
|
Parcel "A" on Record of Survey 9020.
|
Routing PW Drainage | 9/7/2012 | | 9/7/2012 | | PASS |
Brian Murphy
|
|
|
see previos odi approval
|
Case Summary (BLD) | | | 9/7/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/7/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/7/2012 | | DONE |
Tisha Gallop
|
|
|
called Brandon/Kreizenbeck Const. and told him need cert of value for g/d and revised cert of value for building, then can tell him the fees due.
|