Second Notice | | 11/10/2013 | 11/5/2013 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | | 10/10/2013 | 10/31/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/27/2013 | 9/30/2013 | 9/30/2013 | A | PASS |
Forrest France
|
|
|
Remainder of fire life safety inspection items completed and passed.
|
Permanent Occupancy | | | 9/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 9/23/2013 | 9/24/2013 | 9/24/2013 | A | FAIL |
Troy Cobbley
|
|
|
This was just a conference for today. I noted that both smoke detectors at the door are not centered and one exceeds 5' from the door. Unable to test the exit signs and emergency lights due to patients. All other items appear ok. Bob Phone #: ###-####
|
BLD-Final | 9/23/2013 | 9/24/2013 | 9/24/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-####
|
Zoning Approval | 9/5/2013 | 9/5/2013 | 9/5/2013 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | PART |
Troy Cobbley
|
|
|
The Prep/Rec rooms and the west entry life safety has passed.
|
BLD-Ceiling Grid Inspection | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-####
|
FIRE-Conference | 6/25/2013 | 6/26/2013 | 6/26/2013 | A | DONE |
Troy Cobbley
|
|
|
Bob Wheeler and I discussed what I would need a cover inspection on.
|
BLD-Framing/Rough-in | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bob Phone #: ###-#### wip ok
|
FIRE-Final Inspection | 5/23/2013 | 5/24/2013 | 5/24/2013 | A | PART |
Troy Cobbley
|
|
|
Life safety is complete in the Clean Room and the Procedure Room
|
CHANGE STATUS TO (ISS) | | | 5/23/2013 | | DONE |
Tisha Gallop
|
|
|
issued and paid for plan mod
|
(F) Reprint permit | | | 5/23/2013 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 4/30/2013 | | |
|
|
|
|
OVERRIDE | | | 4/30/2013 | | |
|
|
|
|
Routing - PLAN CHECK | 3/20/2013 | | 4/30/2013 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2013 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 4/30/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 4/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/30/2013 | | DONE |
Tisha Gallop
|
|
|
called Sam Burrows and left vm permit is ready and fee.
|
Plan assigned to (JCM) | 3/15/2013 | | 4/30/2013 | | PASS |
John Menard
|
|
|
1st Review for Plan Mod completed 3/21/2013 JCM
|
Plan resubmittals received | | | 4/29/2013 | | DONE |
Christina Prado
|
|
|
received three sets of revised structural calcs ; handed to John Menard for further review
|
Routing - PLAN CHECK | 3/20/2013 | | 3/21/2013 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 3/21/2013 | | DONE |
John Menard
|
|
|
E-mailed the architect requesting calculations and roof framing for the new mechanical equipment on the roof. JCM
|
Routing - PUBLIC WORKS | 3/19/2013 | | 3/20/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - FIRE | 3/20/2013 | | 3/20/2013 | | PASS |
Scott Arellano
|
|
|
|
Routing - PLAN CHECK | 3/15/2013 | | 3/19/2013 | | |
John Menard
|
|
|
|
Plan Modification Accepted | | | 3/15/2013 | | |
|
|
|
Plan modification accepted to reconstruct the existing entry vestibule enclosure to 1-hour, and separate the waiting/reception into two spaces with a 1-hour wall to underside of structure. In addition, there is some minor remodel work to provide access to an existing toilet room from the clinic waiting room. Also, this job includes an upgrade to the esixting mechanical system. Submitted on plan sheets 0.0, A0.1, A1.0, A2.0, A2.1, A3.0, A3.1, A4.0, A4.2, A6.0, A7.0, A7.1, M0.0, M0.1, M1.1, P1.0, P1.1, E2.0, E2.1, E2.2, E3.0 and door hardware schedule; routed to John Menard.
|
CHANGE STATUS TO (ISS) | | | 3/1/2013 | | DONE |
Tisha Gallop
|
|
|
issued plan mod
|
(F) Reprint permit | | | 3/1/2013 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 2/26/2013 | | |
|
|
|
|
Plan assigned to (JCM) | 2/11/2013 | 2/11/2013 | 2/26/2013 | | PASS |
John Menard
|
|
|
|
Telephone call | | | 2/26/2013 | | DONE |
Barbara Stitt
|
|
|
Called Brandon and told him that permit is ready and fees due on 2-26-13 @ 2:45pm//BAS
|
Routing - Design Review | 2/25/2013 | | 2/26/2013 | | PASS |
Josh Wilson
|
|
|
Modification of per DRH12-00334
|
Routing - PLAN CHECK | 2/26/2013 | | 2/26/2013 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2013 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 2/26/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - FIRE | 2/20/2013 | | 2/25/2013 | | PASS |
Scott Arellano
|
|
|
Plans are approved. No change in original plan review comments.
|
Routing - PLUMBING | 2/15/2013 | | 2/20/2013 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 2/15/2013 | | 2/15/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Sewer Rating | 2/15/2013 | | 2/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2013 | | 2/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 2/11/2013 | | 2/13/2013 | | PASS |
John Menard
|
|
|
John Menard
|
Plan Modification Accepted | | | 2/11/2013 | | |
|
|
|
Plan modification accepted to enlarge vestibule to create two seperate entries (1 for out pt surgery & 1 for Dr clinic), also included is a 1 hr wall seperating the waiting and reception areas. In addition the soiled utility area is being modified to accomodate new washers, consequently changing cabinets & sink locations. Submitted application, 3 sets of sheets 0.0, A0.1, A1.0, A2.0, A2.1, A3.0, A3.1, A4.0, A4.2, A6.0, A7.0, A7.1, S2.1, P1.0, P1.1, E2.0, E2.1, E2.2, E3.0, a new certificate of value, 3 copies of structural calcs, 3 copies of Fire lite glazing calcs, 3 copies of Door hardware calcs, given to John Menard
|
OVERRIDE | | | 11/2/2012 | | |
|
|
|
|
Telephone call | | | 11/2/2012 | | DONE |
Barbara Stitt
|
|
|
Called Sam Burrows and told him that permit is ready, fees due, need GC info, RP, and ACHD on 11-2-12 @ 9:15am//BAS
|
Issue PAID IN FULL permit | | | 11/2/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/2/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 10/15/2012 | | 11/1/2012 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 11/1/2012 | | DONE |
Christina Prado
|
|
|
Received three sets of revised sheets marked S2.0 & S3.1. Also received three sets of revised structural calcs, plans inserted by Arch Rep and taken back to John Menard for further review
|
Plan Reviewer's activity | | | 11/1/2012 | | PASS |
John Menard
|
|
|
Reviewed and approved structural revisions. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2012 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 11/1/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JCM) | 9/10/2012 | | 11/1/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 10/30/2012 | | 10/30/2012 | | PASS |
Dave Abo
|
|
|
Parcel "B" on Record of Survey #5847.
|
Route to Impact Fee Review | 10/10/2012 | 10/15/2012 | 10/19/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 10/10/2012 | 10/10/2012 | 10/15/2012 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 10/15/2012 | | FAIL |
|
|
|
Failed public works.
|
Routing - PLAN CHECK | 9/26/2012 | | 10/10/2012 | | PASS |
John Menard
|
|
|
Approved with attached clarifications. JCM
|
Routing PW Sewer Rating | 9/26/2012 | | 9/26/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 9/24/2012 | | 9/26/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 9/26/2012 | | 9/26/2012 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 9/19/2012 | | 9/24/2012 | | |
John Menard
|
|
|
|
Routing - PLANNING | 9/19/2012 | | 9/19/2012 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 9/17/2012 | | 9/19/2012 | | PASS |
Daryl Spivey
|
|
|
Per plans and 2003 UPC.
|
Routing Off Site - STRUCTURAL | 9/10/2012 | | 9/18/2012 | | FAIL |
John Menard
|
|
|
9-10-12 called Action couriers for pick up - Received comment list from consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 9/18/2012 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Plan resubmittals received | | | 9/18/2012 | | DONE |
Tisha Gallop
|
|
|
received three additional copies of plan sheet A1.0 (existing site plan) for Brian Murphy; taken to Brian.
|
Routing PW Drainage | 9/12/2012 | | 9/17/2012 | | FAIL |
Brian Murphy
|
|
|
NEED DRAINAGE LETTER
|
Routing - PUBLIC WORKS | 9/12/2012 | | 9/17/2012 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/17/2012 | | 9/17/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - Addressing | 9/11/2012 | | 9/11/2012 | | PASS |
Terry Records
|
|
|
|
Pending Assignment by JCM | 9/10/2012 | | 9/10/2012 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 9/7/2012 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | 9/7/2012 | | | |
|
|
|
|