Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD12-02418
StatusFinaled
Name RRC CONTRACTORS
Site Address 6945 W OVERLAND RD
Project NameD & B SUPPLY
Customer Number 
ePlanReviewNo
Description
D & B Supply - Storage Addition - To construct a 2,040 square foot, one story, wood framed storage building addition at the rear (south side) of the main retail building. The addition will have three separate 680 square foot storage areas. The addition will be fully fire sprinkled. The sprinklers are used for area increase. The main building is being remodeled for occupancy under BLD12-02323. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/27/20134/23/2013 DONE
mailed
Second Notice 3/1/20133/22/2013 DONE
First Notice 2/14/20132/19/2013 DONE
faxed 2-19-13
BLD-Final2/4/20132/4/20132/4/2013PPASS
DetailsTom Arcoraci
brian Phone #: ###-####
Permanent Occupancy  2/4/2013 DONE
FIRE-Final Inspection2/1/20132/1/20132/1/2013PPASS
DetailsForrest France
Fire life safety inspection passed.
BLD-Framing/Rough-in1/9/20131/9/20131/9/2013PPASS
DetailsTom Arcoraci
brian Phone #: ###-####
Plan Reviewer's activity  11/14/2012 DONE
DetailsJohn Menard
Reviewed and verified that submitted revised Statement of Special Inspection form did not required special inspection of the concrete foundation. JCM
BLD-Footing11/13/201211/13/201211/13/2012PNR
DetailsTom Arcoraci
derek Phone #: ###-#### needs spec insp
Issue PAID IN FULL permit  10/26/2012 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK10/18/2012 10/19/2012 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  10/19/2012 DONE
DetailsJohn Menard
Print Occupancy Form  10/19/2012 DONE
DetailsTisha Gallop
Telephone call  10/19/2012 DONE
LM for Derek permit ready fees due, need ACHD letter
Permit Ready to Issue  10/19/2012 DONE
Plan assigned to (JCM)9/11/2012 10/19/2012 PASS
DetailsJohn Menard
Routing - FIRE10/11/2012 10/18/2012 PASS
DetailsScott Arellano
Attached Comments to plans.
Routing - PLAN CHECK10/2/2012 10/11/2012  
DetailsJohn Menard
Plan resubmittals received  10/10/2012 DONE
DetailsTisha Gallop
received response to building review, response to Fire review, one copy of 8 1/2" x 11" copies of plan sheets A3.1.1, A3.0.1, A3.2.1, A4.0.0, two copies of Structural Calcs, and three copies of plan sheets A3.0.1, A3.1.1, A3.2.1, A4.0.0; inserted into plans by arch. rep. and taken back to John Menard.
Route to Impact Fee Review10/2/201210/5/201210/5/2012 PASS
DetailsCindy M. Gould
Route to Impact Fee Review9/11/20129/14/201210/5/2012 PASS
DetailsCindy M. Gould
Routing - FIRE10/2/201210/2/201210/2/2012 FAIL
DetailsScott Arellano
Emailed and faxed resubmittal items to architect.
Routing - PLAN CHECK9/14/2012 10/2/2012 PASS
DetailsJohn Menard
1st review completed  10/2/2012 FAIL
Failed Public Works, Structural, and Fire.
Plan resubmittals requested  9/24/2012 DONE
DetailsJohn Menard
e-mailed the architect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL9/13/2012 9/21/2012 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requestng revisions. JCM
Routing PW Drainage9/14/2012 9/18/2012 PASS
DetailsBrian Murphy
need o and m, geotech and 5 copies of drainage plan
Routing - PLANNING9/14/2012 9/14/2012 PASS
DetailsAndrea Tuning
DRH12-00223 Andrea
Routing - Erosion and Sediment9/13/2012 9/14/2012 PASS
DetailsKimberly M. Johnson
Routing - PUBLIC WORKS9/13/2012 9/13/2012 PASS
DetailsConnie Baumgartner
Routing - Addressing9/13/2012 9/13/2012 PASS
DetailsTerry Records
Routing - PLANNING Land Div  9/12/2012 PASS
DetailsTodd Tucker
Application received 9/10/20129/11/2012 DONE
DetailsTisha Gallop
Pending Assignment by JCM9/11/2012 9/11/2012 DONE
DetailsJohn Menard
Plans ACCEPTED BY PLAN TECH  9/10/2012 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  9/10/2012 DONE
DetailsTisha Gallop