Second Notice | | 11/24/2012 | 11/15/2012 | | DONE |
|
|
|
|
First Notice | 11/9/2012 | 11/9/2012 | 11/14/2012 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 11/8/2012 | 11/9/2012 | 11/9/2012 | P | PASS |
Jim Sly
|
|
|
Jon ###-#### Had Craig from AJH Eng. OK for final approval.
|
DOC - Permit Finaled | 11/9/2012 | 11/9/2012 | 11/9/2012 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/7/2012 | 11/8/2012 | 11/8/2012 | P | PEND |
Jim Sly
|
|
|
Jon Phone #: ###-#### Need Structural Eng to approve.
|
BLD-Framing/Rough-in | 10/29/2012 | 10/31/2012 | 10/31/2012 | A | PART |
Tony Young
|
|
|
John Williams Phone #: ###-####,,, roof structure ok,, engineer also approved it
|
Permit Ready to Issue | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 10/15/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 10/3/2012 | | 10/8/2012 | | PASS |
Dan Stuart
|
|
|
Pending approval of structural resubmittals. 10-5-12 Confirmation of structural review approval received. Plans approved per engineering design data and plan sheets.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2012 | | PASS |
Dan Stuart
|
|
|
|
Routing Off Site - STRUCTURAL | 10/4/2012 | | 10/5/2012 | | PASS |
Jeffrey Neberman
|
|
|
Structural resubmittals routed to outsource engeineers for review
Received ePlan review review report 10-5-12 approving structural resubmittals of 10-4-12.
|
Plan assigned to (DRS) | 9/24/2012 | 9/24/2012 | 9/27/2012 | | FAIL |
Dan Stuart
|
|
|
ePlanReview case - TRICA Roof Repair
Failed outsource strucutral plan review. Requires resubmittals.
|
Routing - PLAN CHECK | 9/24/2012 | | 9/27/2012 | | FAIL |
Dan Stuart
|
|
|
Failed structural plan review.
|
Telephone call | | | 9/27/2012 | | DONE |
Dan Stuart
|
|
|
Talked with Richard Honsinger, Erstadt Architects, concerning the structural resubmittals required and reminder that there is no occupancy approval or use allowed for this building. There are remaining structural issues for the overall building that have not been addressed to date.
|
1st review completed | | | 9/27/2012 | | FAIL |
Dan Stuart
|
|
|
|
Routing Off Site - STRUCTURAL | 9/19/2012 | | 9/25/2012 | | FAIL |
Dan Stuart
|
|
|
Structural e-plan review completed by outsource engineering firm. Resubmittals are required. Copy of report to Design professional of Record, Richard Honsinger, Erstad Architects for response.
|
Routing - PLAN CHECK | 9/19/2012 | | 9/24/2012 | | DEFR |
Jason Blais
|
|
|
Reassigned to Dan Stuart.
|
Plan assigned to (JCB) | 9/19/2012 | | 9/22/2012 | | DEFR |
Jason Blais
|
|
|
Reassigned to Dan Stuart.
|
Payment Received | | | 9/19/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Pending Assignment by JCB | 9/19/2012 | | 9/19/2012 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 9/19/2012 | | PASS |
Jason Blais
|
|
|
Tim Woodard approved prescreen on 9/18/12. Plan Review Fees paid on 9/19/12.
|
Telephone call | | | 9/18/2012 | | |
|
|
|
9-18-12 sent email to Richard H initial fees need to be paid before plans can move on.
|
Application received | | | 9/14/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 14 2012 10:24AM
|