Permit Information
Permit NumberBLD12-02483
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 1055 N CURTIS RD
Project NameSARMC
Customer Number 
ePlanReviewNo
Description
(SAINT ALPHONSUS ENDOSCOPY SUITE - 1ST STORY) The fire sprinkler system is used for high-rise and occupancy. To create a 9,589 square foot Endoscopy Suite (5,570 square foot remodel area plus 2,808 square foot future expansion area plus 1,211 square foot additional area) on the 1st story of Saint Alphonsus Regional Medical Center. Only the 5,570 square foot area will be remodeled under this permit. Work is to include smoke barriers / smoke partitions, 20 minute smoke and draft control door assemblies, interior nonbearing walls, 4 single user restrooms accessible to the disabled, interior windows, interior doors, millwork, suspended acoustical ceilings, gypsum board soffits, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Verify with the Fire Department whether quick-response sprinklers will be required to be installed throughout the smoke compartment containing the Endoscopy Suite. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/10/20135/8/2013 DONE
This permit finaled on the web by Brandon Byington
First Notice 4/1/20134/30/2013 DONE
Faxed 4/30/13
BLD-Final3/21/20133/22/20133/22/2013PPASS
DetailsTom Arcoraci
cecil Phone #: ###-####
Permanent Occupancy  3/22/2013 DONE
DetailsChristina Prado
FIRE-Final Inspection3/13/20133/13/20133/13/2013PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Framing/Rough-in1/4/20131/4/20131/4/2013PPASS
DetailsTom Arcoraci
Issue PAID IN FULL permit  11/27/2012 DONE
DetailsChristina Prado
Plan assigned to (CJW)9/17/20129/17/201211/26/2012 PASS
DetailsCarl Westfall
ST AL'S ENDOSCOPY SUITE (20 days - Oct 11)
Routing - PLUMBING11/19/2012 11/26/2012 PASS
DetailsBill VanDegrift
if the addition adversely impacts the preformance requirements of a system or component, additional upgrades shall be required.
Routing - PLAN CHECK11/26/2012 11/26/2012 DONE
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  11/26/2012 DONE
Print Occupancy Form  11/26/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  11/26/2012 DONE
Telephone call  11/26/2012 DONE
LM for Sam permit ready fees given
Routing - PLAN CHECK10/22/2012 11/19/2012 PASS
DetailsCarl Westfall
Drawings approved with "red lines" after the resubmittal review.
Plan resubmittals received  11/16/2012  
Received 1 cover transmittal, 2 copies of response comments dated 11-12-12 from Mike MIller to Sam Burrows, taken to Carl Westafall
Plan resubmittals received  11/14/2012  
Received 1 resp[onse letter dated 11-13-12 from Sam Burrows to Carl Westfall, 2 copies of door hardware calcs, 2 copies of sheets 0.0, A0.2, A2.0, A3.0, A7.0, M0.0, M1.2, M1.3, M2.1, M2.2, E2.1F, E2.1S, E4.0 and taken to Carl Westfall
Route to Impact Fee Review10/19/201210/24/201211/5/2012 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Meeting  11/1/2012 DONE
Meeting with Sam to discuss smoke barriers.
Routing - FIRE10/19/201210/19/201210/22/2012 PASS
DetailsScott Arellano
Attached fire code comments to plans.
Telephone call  10/22/2012 DONE
Discussed smoke dampers with the Mechanical Engineer.
1st review completed  10/22/2012 FAIL
Failed Plan Check and Plumbing.
Routing - PLAN CHECK9/19/2012 10/19/2012 FAIL
DetailsCarl Westfall
The IBC plan review was started on October 10 and finished on October 19. Revised drawings were required. See the plan review report.
Routing - PLUMBING9/18/2012 9/19/2012 FAIL
DetailsBill VanDegrift
Provide load data for existing and new medical gas piping.
2003 UPC 1312.2.2
Routing - PUBLIC WORKS  9/18/2012 PASS
Pending Assignment by JCB9/14/2012 9/17/2012 DONE
DetailsJason Blais
Routing - Addressing9/17/2012 9/17/2012 PASS
DetailsApril Wing
Application received 9/14/20129/14/2012 DONE
DetailsChristina Prado
Plans ACCEPTED BY PLAN TECH  9/14/2012 DONE
DetailsChristina Prado
Intake Approval  9/14/2012 PASS
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  9/14/2012 DONE
DetailsChristina Prado