BLD-Final | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 6/27/2014 | 7/1/2014 | 7/1/2014 | A | NR |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Final | 6/26/2014 | 6/27/2014 | 6/27/2014 | A | NR |
Tony Young
|
|
|
David Phone #: ###-####,, needs mech 1st
|
BLD-Final | 6/26/2014 | 6/26/2014 | 6/27/2014 | P | PEND |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Final | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | NR |
Tony Young
|
|
|
David Phone #: ###-####,, needs mec 1st
|
BLD-Energy code compliance | 4/1/2013 | 4/2/2013 | 4/2/2013 | A | PASS |
Tony Young
|
|
|
holly Phone #: ###-####
|
BLD-Energy code compliance | 3/26/2013 | 3/27/2013 | 3/28/2013 | P | PART |
Tony Young
|
|
|
david Phone #: ###-####,, seal package ok
|
BLD-Framing/Rough-in | 3/26/2013 | 3/27/2013 | 3/27/2013 | A | PASS |
Tony Young
|
|
|
david Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2013 | 3/26/2013 | 3/26/2013 | P | PART |
Tony Young
|
|
|
david Phone #: ###-####,, need seal package and straps on plates,, point load studs
|
BLD-Foundation | 10/19/2012 | 10/19/2012 | 10/22/2012 | P | DONE |
Tony Young
|
|
|
tim Phone #: ###-####
|
BLD-Foundation | 10/18/2012 | 10/19/2012 | 10/19/2012 | A | PART |
Tony Young
|
|
|
tim Phone #: ###-####,, in progress
|
BLD-Footing | 10/17/2012 | 10/18/2012 | 10/18/2012 | P | PASS |
Tony Young
|
|
|
tim Phone #: ###-####
|
Plan assigned to (CDM) | 9/19/2012 | 9/19/2012 | 10/15/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/15/2012 | | DONE |
|
|
|
|
Telephone call | | | 10/15/2012 | | |
|
|
|
spoke with david permit ready fees given
|
Issue PAID IN FULL permit | | | 10/15/2012 | | DONE |
|
|
|
|
Routing - MECHANICAL | 10/11/2012 | | 10/12/2012 | | PASS |
Troy James
|
|
|
|
Case Summary (BLD) | | | 10/11/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/27/2012 | | 10/11/2012 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 10/8/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of revised wall bracing and footing details: gave to Carl Madsen for further review
|
1st review completed | | | 10/5/2012 | | FAIL |
|
|
|
Needs to have detais from engineering package ransfeered to plans. Called and spoke to contractor and also emailed contractor.
|
Route to Impact Fee Review | 9/18/2012 | 9/21/2012 | 9/25/2012 | | PASS |
Cindy M. Gould
|
|
|
CREDIT FOR DEMO BLD12-00538
|
Routing - MECHANICAL | 9/24/2012 | | 9/24/2012 | | FAIL |
Troy James
|
|
|
emailed correction to TML
|
Routing - PLANNING | 9/20/2012 | | 9/21/2012 | | PASS |
Joshua Johnson
|
|
|
CZC11-00206
Driveway and apron must be paved
|
Routing - Addressing | 9/19/2012 | | 9/20/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | | | 9/20/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 9/18/2012 | 9/18/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 9/18/2012 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/18/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 10/11/2012 | | | | FAIL |
Troy James
|
|
|
emailed TML again, informing them I still need revised acca report
|