BLD-Final | 11/30/2012 | 12/3/2012 | 12/4/2012 | A | PASS |
Tony Young
|
|
|
|
BLD-Final | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
The House will be open. Thanks Phone #: ###-#### >> Inspection requested via web by Peter Harris
|
DOC - Permit Finaled | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 10/26/2012 | 10/30/2012 | 10/30/2012 | P | PASS |
Tony Young
|
|
|
Thanks Phone #: ###-#### >> Inspection requested via web by Peter Harris
|
BLD-Wall Bracing | 10/29/2012 | 10/30/2012 | 10/30/2012 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Peter Harris
|
BLD-Framing/Rough-in | 10/26/2012 | 10/29/2012 | 10/29/2012 | P | PASS |
Tom Arcoraci
|
|
|
Thanks Phone #: ###-#### >> Inspection requested via web by Peter Harris
|
BLD-Wall Bracing | 10/19/2012 | 10/22/2012 | 10/22/2012 | A | PART |
Tony Young
|
|
|
we will be ready first thing. Thanks Phone #: ###-#### >> Inspection requested via web by Peter Harris,, finish nailing off 4 panels ,, then ok to cover
|
BLD-Foundation | 10/8/2012 | 10/9/2012 | 10/9/2012 | A | DONE |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Foundation | 10/8/2012 | 10/9/2012 | 10/9/2012 | A | PART |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Footing | 10/8/2012 | 10/8/2012 | 10/9/2012 | P | PASS |
Tony Young
|
|
|
David Phone #: ###-####
|
OVERRIDE | | | 10/8/2012 | | |
|
|
|
|
Plan assigned to (CDM) | | 9/19/2012 | 10/8/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/25/2012 | | 10/8/2012 | | PASS |
Carl D Madsen
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/2012 | | DONE |
Barbara Stitt
|
|
|
|
1st review completed | | | 10/8/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 10/8/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/8/2012 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 10/8/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 9/28/2012 | | 10/1/2012 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 9/28/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of revised Manual J documents: Gave to Troy James for review
|
Route to Impact Fee Review | 9/19/2012 | 9/24/2012 | 9/25/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 9/20/2012 | | 9/25/2012 | | FAIL |
Troy James
|
|
|
no review, builder submitting falsified reports
|
Routing - PLANNING | 9/20/2012 | | 9/20/2012 | | PASS |
Sue Cummings
|
|
|
CUP05-164 & CUP07-130
|
Routing - Addressing | 9/19/2012 | | 9/20/2012 | | PASS |
Terry Records
|
|
|
|
Routing - PUBLIC WORKS | | | 9/20/2012 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | 9/19/2012 | 9/19/2012 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/19/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/19/2012 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2012 | | DONE |
Christina Prado
|
|
|
|