BLD-Final | 8/9/2013 | 8/12/2013 | 8/12/2013 | A | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-####
|
DOC - Permit Finaled | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 8/8/2013 | 8/8/2013 | 8/8/2013 | | DONE |
Jason C. Taylor
|
|
|
Grading and drainage approval letter recieved from civil engineer (KM). Roof drainage was routed to a seepage bed in the rear sideyard (east side). Occupancy approved. Jason Taylor ###-####.
|
BLD-Conference | 8/6/2013 | 8/7/2013 | 8/7/2013 | P | DONE |
Dave Hannah
|
|
|
chad call for access Phone #: ###-####
|
BLD-Other | 6/3/2013 | 6/3/2013 | 6/4/2013 | P | PASS |
Dave Hannah
|
|
|
fire rated wood - Chad Phone #: ###-#### 2x6 deck ok
|
BLD-Other | 4/23/2013 | 4/23/2013 | 4/23/2013 | P | PASS |
Dave Hannah
|
|
|
sheetrock soffits ok to cover
|
BLD-Energy code compliance | 4/22/2013 | 4/23/2013 | 4/23/2013 | A | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-####
|
BLD-Framing/Rough-in | 4/19/2013 | 4/19/2013 | 4/19/2013 | P | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-####
|
BLD-Wall Bracing | 4/19/2013 | 4/19/2013 | 4/19/2013 | P | PASS |
Dave Hannah
|
|
|
chad Phone #: ###-####
|
BLD-Wall Bracing | 4/12/2013 | 4/12/2013 | 4/15/2013 | P | FAIL |
Dave Hannah
|
|
|
chad Phone #: ###-#### c/n on site
|
Plan resubmittals received | | | 4/5/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 4/5/2013 | | 4/5/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Foundation | 12/26/2012 | 12/27/2012 | 12/28/2012 | P | PASS |
Dave Hannah
|
|
|
bob Phone #: ###-####
|
BLD-Footing | 12/12/2012 | 12/13/2012 | 12/13/2012 | P | PASS |
Dave Hannah
|
|
|
early afternoon - Bob Phone #: ###-####
|
Routing PW Grading-Hillside | 12/12/2012 | | 12/12/2012 | | PASS |
Jim Wyllie
|
|
|
Received letter from geotechnical engineer regarding footing subgrade. Okay to schedule a footing inspection. Jim Wyllie (###-####)
|
Issue PAID IN FULL permit | | | 11/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 11/1/2012 | | |
|
|
|
|
Plan assigned to (CDM) | 9/25/2012 | 9/25/2012 | 11/1/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Addressing | 9/25/2012 | | 11/1/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | | | 11/1/2012 | | PASS |
Carl D Madsen
|
|
|
Carl Madsen
|
Telephone call | | | 11/1/2012 | | DONE |
Tisha Gallop
|
|
|
called Chad and told him permit is ready and fees.
|
1st review completed | | | 11/1/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2012 | | |
|
|
|
|
Case Summary (BLD) | | | 11/1/2012 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 11/1/2012 | | 11/1/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Inspection Record Card- Bld | | | 11/1/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/1/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 10/26/2012 | | 10/26/2012 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 10/9/2012 | | 10/12/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - Erosion and Sediment | 10/8/2012 | | 10/9/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 10/4/2012 | | 10/8/2012 | | FAIL |
Troy James
|
|
|
emialed corrections to Teds Heating
|
Routing - PLANNING | 10/3/2012 | | 10/4/2012 | | FAIL |
Colleen T Carroll
|
|
|
Deck in rear setback
Driveway width exceeds 33' wide in front setback
retaining walls exceeds 3' in front setback
|
Routing - PLANNING | 10/4/2012 | | 10/4/2012 | | PASS |
Colleen T Carroll
|
|
|
An unroofed balcony is permitted to extend 4' into the rear yard setback. Driveway width will be seperated by a landscape island
|
Routing PW Grading-Hillside | 9/26/2012 | | 10/3/2012 | | PASS |
Jim Wyllie
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2012 | | 10/3/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jim Wylie for hillside
|
Route to Impact Fee Review | 9/25/2012 | 9/28/2012 | 9/27/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 9/26/2012 | | 9/26/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 9/25/2012 | 9/25/2012 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/25/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/25/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 9/25/2012 | | PASS |
Barbara Stitt
|
|
|
|