Third Notice | | 3/27/2013 | 4/4/2013 | | DONE |
|
|
|
|
Third Notice | | 2/24/2013 | 3/22/2013 | | DONE |
|
|
|
faxed
|
Second Notice | | 2/7/2013 | 2/19/2013 | | DONE |
|
|
|
|
First Notice | | 1/20/2013 | 1/28/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/10/2013 | | DONE |
|
|
|
|
BLD-Final | 1/3/2013 | 1/4/2013 | 1/4/2013 | A | PASS |
Mike Jordan
|
|
|
dave Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 1/2/2013 | 1/3/2013 | 1/3/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. New address to be posted prior to building inspection as discussed.
|
BLD-Energy code compliance | 11/27/2012 | 11/27/2012 | 11/27/2012 | P | PASS |
Mike Jordan
|
|
|
dave Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | PART |
Mike Jordan
|
|
|
dave Phone #: ###-####. Foam seal all penetrations in top plates for airseal an fireblock. Provide the additional grab bar in restroom and lower mirror to meet ada requirements. correction notice posted, ok to insulate.
|
Permit Ready to Issue | | | 10/29/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/29/2012 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/29/2012 | | DONE |
Christina Prado
|
|
|
|
Plan Reviewer's activity | | | 10/18/2012 | | DONE |
Tim L. Woodard
|
|
|
Updated revised restroom access sheet A2.1 and approved. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 10/5/2012 | | 10/10/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 10/3/2012 | | 10/9/2012 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 10/9/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/5/2012 | | 10/5/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 10/3/2012 | | 10/4/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 10/4/2012 | | 10/4/2012 | | PASS |
April Wing
|
|
|
Change address to 929 S Allante Pl from 931 S Allante Pl. See Address doc.
|
Intake Approval | | | 10/3/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2012 | | 10/3/2012 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 9/27/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2012 10:31AM
|