PubWorks Occupancy Approval | 6/12/2013 | 6/12/2013 | 6/12/2013 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 6/12/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 6/11/2013 | 6/11/2013 | 6/11/2013 | P | PASS |
Mike Jordan
|
|
|
fred Phone #: ###-####. ok for perm occ.
|
BLD-Final | 5/28/2013 | 5/28/2013 | 5/28/2013 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. ok for perm temp occ. Needs to post permanent signage when it arrives.
|
BLD-Final | 5/23/2013 | 5/24/2013 | 5/24/2013 | P | FAIL |
Mike Jordan
|
|
|
mike Phone #: ###-####handrail into pool is not code compliant.
|
FIRE-Final Inspection | 5/22/2013 | 5/23/2013 | 5/23/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide the panic hardware on the pool gates as per the approved plans prior to a building sign off.
|
BLD-Concrete | 12/12/2012 | 12/13/2012 | 12/13/2012 | A | PASS |
Mike Jordan
|
|
|
Rebar inspection please-Kelly Cherryman Phone #: ###-####
|
BLD-Concrete | 12/13/2012 | 12/13/2012 | 12/13/2012 | P | PASS |
Mike Jordan
|
|
|
|
Issue PAID IN FULL permit | | | 11/26/2012 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 10/4/2012 | 10/4/2012 | 11/21/2012 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2012 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/21/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/21/2012 | | DONE |
|
|
|
|
Telephone call | | | 11/21/2012 | | DONE |
|
|
|
LM permit ready fees given
|
Routing - PLAN CHECK | 10/31/2012 | | 11/21/2012 | | PASS |
Dan Stuart
|
|
|
|
Plan resubmittals received | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
Received two copies of response, Alternate approval, pool equipment specs, structural calcs, 11"x17" pool plans by Aquatech (sheets cover, 1.1, 1.2, 1.3, 1.4, S-1, S-2, C1, C2), and full size plan sheets A-0.1, A-0.2, A-1.1; inserted into plans by permit tech and taken back to Dan Stuart.
|
Plan resubmittals requested | | | 11/2/2012 | | DONE |
Dan Stuart
|
|
|
Copy of Plan Review e-mailed to architect.
|
1st review completed | | | 10/30/2012 | | FAIL |
Dan Stuart
|
|
|
Failed IBC Plan Review
|
Routing - PLAN CHECK | 10/25/2012 | | 10/30/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required.
|
Routing - FIRE | 10/23/2012 | | 10/25/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans. *NOTE* If any hazardous materials will be stored in the mechanical room (ie: oxidizers or sodium hypo-chlorite), quantities shall not exceed 250 pounds.
|
Routing - PLAN CHECK | 10/9/2012 | | 10/22/2012 | | FAIL |
Dan Stuart
|
|
|
10/22/12 Questions on scope of work for applicant submittals.
Routing to fire code analyst.
10/30/12 Copy of plan review e-mailed to architect.
|
Routing - PLUMBING | 10/9/2012 | | 10/9/2012 | | PASS |
Daryl Spivey
|
|
|
No plumbing on this permit. Plan review was done for plumbing in mechanical room for pool under Bld 12-00676.
|
Routing - PLANNING | 10/9/2012 | | 10/9/2012 | | PASS |
Josh Wilson
|
|
|
DRH12-00111 Josh Wilson
|
Routing - Erosion and Sediment | 10/8/2012 | | 10/9/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Scope of ESC12-00288 extended to include construction of inground pool. Noted on ESC permit
|
Routing - PUBLIC WORKS | 10/5/2012 | | 10/8/2012 | | PASS |
Connie Baumgartner
|
|
|
Noted on plans. drs
|
Routing - Addressing | 10/8/2012 | | 10/8/2012 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 10/8/2012 | | 10/8/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 10/4/2012 | | 10/5/2012 | | PASS |
Dave Abo
|
|
|
Lot 7, Block 14, Union Square Subdivision No. 2
|
Application received | | 9/28/2012 | 10/4/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2012 | | DONE |
Tisha Gallop
|
|
|
|
First Notice | | 6/22/2013 | | | |
|
|
|
|