Permit Information
Permit NumberBLD12-02637
StatusFinaled
Name SAUCERMAN CONSTRUCTION
Site Address 9272 N PIERCE PARK LN
Project NamePierce Park Gulch Horse Barn
Customer Number1208
ePlanReviewYes
Description
Pierce Gulch Farm - Horse Barn - To construct a new 2,650 square foot, one story, pre-engineered metal horse barn building and related site improvements. This barn will including electrical and water. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  7/25/2013 DONE
DetailsTisha Gallop
mailed to Saucerman Const
Second Notice 7/12/20137/22/2013 DONE
Final value done in combination with Bld12-02766 (grading), 02857 (hay shed). Additional final value and fee put on this permit.
First Notice 6/3/20137/2/2013 DONE
DetailsBarbara Stitt
Faxed 7-2-13
Permanent Occupancy  5/24/2013 DONE
DetailsTisha Gallop
BLD-Final5/23/20135/23/20135/23/2013PPASS
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Shane Treasure
FIRE-Final Inspection5/23/20135/23/20135/23/2013PPASS
DetailsTroy Cobbley
life safety passed
Zoning Approval5/23/20135/23/20135/23/2013 DONE
DetailsSusan Riggs
BLD-Footing1/25/20131/28/20132/1/2013PPEND
DetailsTony Young
Special inspection by Idaho mountain inspection Phone #: ###-#### >> Inspection requested via web by Shane Treasure
BLD-Foundation1/25/20131/28/20131/29/2013PPEND
DetailsTony Young
Special inspection by Idaho mountain inspection. To place at 3:00 pm weather permitting. Phone #: ###-#### >> Inspection requested via web by Shane Treasure,, pening special inspection reports
BLD-Foundation1/11/20131/11/20131/14/2013PPEND
DetailsTony Young
Exterior foundation walls are set and ready to be placed. Waiting on weather but looking for inspection tomorrow. May place Friday or next week. Special inspection will be coordinated on day of placement. Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
BLD-Foundation1/9/20131/10/20131/11/2013APEND
DetailsTony Young
Exterior foundation walls are set and ready to be placed. Waiting on weather but looking for inspection tomorrow. May place Friday or next week. Special inspection will be coordinated on day of placement. Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
BLD-Framing/Rough-in12/21/201212/24/201212/24/2012ANR
DetailsTony Young
robert - call 30 mins prior Phone #: ###-####
BLD-Footing12/18/201212/19/201212/19/2012APASS
DetailsJim Storey
Pier footing inspection / Special inspection contacted also / placement at 11:00 a.m. Phone #: ###-#### >> Inspection requested via web by Paul Saucerman
CHANGE STATUS TO (ISS)  12/5/2012 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  12/5/2012 DONE
DetailsTisha Gallop
e-mailed permit and occupancy sign off card to Paul Saucerman
Print Occupancy Form  12/5/2012 DONE
DetailsTisha Gallop
e-mailed to Paul Saucerman
Meeting  11/30/2012 DONE
DetailsTisha Gallop
GC in office provided all info and paid fees. Still need ACHD.
PLANS/APPL TAKEN TO FRONT DESK  11/23/2012 DONE
DetailsJohn Menard
Routing - PLAN CHECK11/16/2012 11/23/2012 PASS
DetailsJohn Menard
Permit Ready to Issue  11/23/2012 DONE
DetailsTisha Gallop
Plan assigned to (JCM)10/12/2012 11/23/2012 PASS
DetailsJohn Menard
Routing - FIRE11/16/2012 11/19/2012 PASS
DetailsScott Arellano
Attached Fire Comments to plans.
1st review completed  10/30/2012 FAIL
DetailsJohn Menard
Failed Building, Fire and Structural
Routing - PLAN CHECK10/12/2012 10/30/2012 FAIL
DetailsJohn Menard
Routing - PLANNING10/12/2012 10/30/2012 PASS
DetailsSusan Riggs
Routing PW Grading-Hillside10/15/2012 10/26/2012 PASS
DetailsJim Wyllie
Routing Off Site - STRUCTURAL10/12/2012 10/22/2012 FAIL
DetailsJohn Menard
Route to Impact Fee Review10/12/2012 10/19/2012 PASS
DetailsCindy M. Gould
Routing - FIRE10/12/2012 10/19/2012 FAIL
DetailsScott Arellano
Emailed architect and attached resubmittal items to case.
Routing - PLUMBING10/12/2012 10/16/2012 PASS
DetailsDaryl Spivey
Provide DCVA backflow on water service.
Routing PW Sewer Rating10/15/2012 10/15/2012 PASS
DetailsConnie Baumgartner
Routing - PLANNING Land Div10/12/2012 10/15/2012 PASS
DetailsTodd Tucker
Routing - Addressing10/12/2012 10/15/2012 PASS
DetailsApril Wing
Routing - PUBLIC WORKS10/12/2012 10/15/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment10/12/2012 10/12/2012 PASS
DetailsKimberly M. Johnson
approved per redlines and conditions
Pending Assignment by JCM10/12/2012 10/12/2012 DONE
DetailsJohn Menard
Intake Approval  10/11/2012 PASS
DetailsJohn Menard
Telephone call  10/10/2012 DONE
DetailsBarbara Stitt
Email sent to notify plan check fees are due on 10-10-12 @ 4:20pm//BAS
Intake Approval  10/8/2012 FAIL
DetailsJohn Menard
Intake Approval  10/5/2012 FAIL
DetailsJohn Menard
Application received  10/2/2012 DONE
Application submitted via PDS Online on Oct 2 2012 10:45AM