Second Notice | | 5/3/2013 | 5/28/2013 | | DONE |
|
|
|
|
Print Statement | | | 5/28/2013 | | DONE |
Tisha Gallop
|
|
|
mailed to Burton Friesz
|
First Notice | | 3/28/2013 | 4/23/2013 | | DONE |
|
|
|
Mailed 4-24-13
|
FIRE-Final Inspection | 3/15/2013 | 3/18/2013 | 3/18/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Final | 3/15/2013 | 3/18/2013 | 3/18/2013 | P | PASS |
Dave Hannah
|
|
|
Burton Phone #: ###-####
|
FIRE-Conference | 3/15/2013 | 3/18/2013 | 3/18/2013 | A | DONE |
Forrest France
|
|
|
On site discussion with tenant and building representative regarding conditions for fire life safety final approval.
|
Permanent Occupancy | | | 3/18/2013 | | DONE |
|
|
|
|
FIRE-Sprinkler Rough-in | 2/27/2013 | 2/27/2013 | 2/27/2013 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work is approved for cover at the grid ceilings.
|
BLD-Ceiling Grid Inspection | 2/20/2013 | 2/20/2013 | 2/21/2013 | P | PASS |
Dave Hannah
|
|
|
adrian Phone #: ###-####
|
BLD-Framing/Rough-in | 2/14/2013 | 2/15/2013 | 2/15/2013 | A | NR |
Dave Hannah
|
|
|
Ceiling cover inspection-Abraham Phone #: ###-####
|
BLD-Framing/Rough-in | 1/15/2013 | 1/15/2013 | 1/16/2013 | P | PASS |
Dave Hannah
|
|
|
Adrian Roberts Phone #: ###-#### fire proofing patched ok to cover walls
|
BLD-Framing/Rough-in | 1/11/2013 | 1/11/2013 | 1/14/2013 | P | PART |
Dave Hannah
|
|
|
Adrian Phone #: ###-#### ok to cover walls but need to replace fire proofing that has been removed from columns and beams
|
Issue PAID IN FULL permit | | | 10/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 10/22/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/22/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/22/2012 | | DONE |
Barbara Stitt
|
|
|
Called and told Meagan that permit is ready and fees due on 10-22-12 @ 9:15am//BAS
|
Plan assigned to (TLW) | 10/3/2012 | | 10/19/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/3/2012 | | 10/19/2012 | | PASS |
Tim L. Woodard
|
|
|
Tim Woodard
|
1st review completed | | | 10/19/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 10/19/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 10/2/2012 | 10/2/2012 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 10/2/2012 | | PASS |
Tim L. Woodard
|
|
|
|