BLD-Final | 6/5/2015 | 6/8/2015 | 6/8/2015 | P | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
FIRE-Final Inspection | 6/5/2015 | 6/8/2015 | 6/8/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Issue PAID IN FULL permit | | | 9/27/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/27/2013 | | |
|
|
|
|
Routing PW Sewer Rating | 10/17/2012 | | 9/25/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Expiration Notice | 9/16/2013 | 10/7/2013 | 9/16/2013 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 4/2/2013 | | DONE |
Christina Prado
|
|
|
Jason blais approved 180 day extension 4-2-13
|
Routing - PLAN CHECK | 3/26/2013 | | 3/26/2013 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 3/22/2013 | | |
|
|
|
Received letter to Jason Blais from Brook Thornton, New certificate of value, 2 copies of sheets, A-2.1, A-3.1 and taken to Tim Woodards desk
|
Expiration Notice | 3/18/2013 | 4/8/2013 | 3/18/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 10/19/2012 | 10/19/2012 | 10/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 10/25/2012 | | DONE |
|
|
|
|
Routing - FIRE | | | 10/25/2012 | | PASS |
|
|
|
Verify in field CDM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2012 | | |
|
|
|
|
Routing - PLAN CHECK | 10/17/2012 | | 10/25/2012 | | PASS |
Carl D Madsen
|
|
|
|
Permit Ready to Issue | | | 10/25/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 10/17/2012 | | 10/19/2012 | | DEFR |
Tim L. Woodard
|
|
|
Review deffered to Carl M.
|
Routing - Addressing | 10/17/2012 | | 10/17/2012 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 10/17/2012 | | 10/17/2012 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 10/15/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 10/11/2012 | | FAIL |
Tim L. Woodard
|
|
|
Brook,
Please upload the Submittal Checklist and form # 304 into the documents folder of the case. With those two things the routing can proceed. FYI: in order to downgrade and existing rated corridor in a sprinklered building a letter from a fire sprinkler company must be submitted verifying quick responce heads thoughout the building. Thanks, Tim Woodard ###-#### or twoodard@cityofboise.org
|
Application received | | | 10/8/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2012 7:48AM
|