PubWorks Occupancy Approval | 10/21/2013 | 10/21/2013 | 10/21/2013 | | DONE |
Jason C. Taylor
|
|
|
Project completed.
|
BLD-Final | 10/17/2013 | 10/18/2013 | 10/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
mike or Josh ###-#### Phone #: ###-####
|
DOC - Permit Finaled | 10/18/2013 | 10/18/2013 | 10/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 10/16/2013 | 10/17/2013 | 10/18/2013 | P | NR |
Dave Hannah
|
|
|
MIKE CALL FOR ACCESS Phone #: ###-#### needs hill side sign off
|
BLD-Wall Bracing | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-#### int sheetrock shear ok
|
BLD-Energy code compliance | 4/12/2013 | 4/15/2013 | 4/15/2013 | P | PASS |
Dave Hannah
|
|
|
Late afternoon please - MIKE Phone #: ###-####
|
BLD-Wall Bracing | 4/11/2013 | 4/11/2013 | 4/15/2013 | P | PASS |
Dave Hannah
|
|
|
Mike-Please call 30 mins prior to inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Dave Hannah
|
|
|
Mike-Please call 30 mins prior to inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | NR |
Mike Jordan
|
|
|
call 1/2 hr before to meet//Mike Phone #: ###-####
|
BLD-Wall Bracing | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | DEFR |
Mike Jordan
|
|
|
call 1/2 hr before to meet//Mike Phone #: ###-####
|
Plan assigned to (CDM) | 3/19/2013 | 3/19/2013 | 4/10/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/3/2013 | | 4/10/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 4/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/10/2013 | | DONE |
Tisha Gallop
|
|
|
Called Roth Const and told them plan mod is ready, fee due.
|
CHANGE STATUS TO (ISS) | | | 4/10/2013 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 4/10/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 4/9/2013 | | 4/9/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to Ingo
|
Routing - MECHANICAL | 4/9/2013 | | 4/9/2013 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 4/2/2013 | | 4/3/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to Building Energy
|
Routing - PLANNING | 4/1/2013 | | 4/2/2013 | | PASS |
Sue Cummings
|
|
|
|
Plan resubmittals received | | | 3/28/2013 | | |
|
|
|
Received 2 copies of sheets S-I, 1, S-2, S-3, E-I, and 2 manual J's all taken to Carl Madsen's desk
|
BLD-Other | 3/18/2013 | 3/21/2013 | 3/21/2013 | P | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-#### ok to cover eves and soffits
|
Plan resubmittals received | | | 3/19/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 3/19/2013 | | 3/19/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
Plan resubmittals received | | | 3/19/2013 | | DONE |
Tisha Gallop
|
|
|
received plan modification: two copies plan sheets A-1, A-2, A-3, A-4, S-0, S-1, S-2, S-3, E-1, E-2, AD-1 and one copy of plan sheet 1 and lateral calcs; taken to Carl Madsen.
|
BLD-Wall Bracing | 3/13/2013 | 3/13/2013 | 3/13/2013 | P | FAIL |
Dave Hannah
|
|
|
mike Phone #: ###-#### c/n on site
|
BLD-Foundation | 1/7/2013 | 1/8/2013 | 1/10/2013 | P | DONE |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Foundation | 1/9/2013 | 1/9/2013 | 1/10/2013 | P | PASS |
Dave Hannah
|
|
|
mana Phone #: ###-####
|
BLD-Footing | 1/8/2013 | 1/8/2013 | 1/9/2013 | P | PART |
Dave Hannah
|
|
|
Mana Phone #: ###-#### told crew to use cold weather protection
|
BLD-Footing | 1/7/2013 | 1/7/2013 | 1/7/2013 | P | CANC |
Dave Hannah
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 1/3/2013 | 1/3/2013 | 1/3/2013 | P | CANC |
Dave Hannah
|
|
|
mana Phone #: ###-#### to cold to place concrete
|
BLD-Foundation | 12/7/2012 | 12/7/2012 | 12/7/2012 | P | PART |
Dave Hannah
|
|
|
found wall//Mana Phone #: ###-#### ok to place concrete on lower section and basement walls
|
BLD-Footing | 11/30/2012 | 11/30/2012 | 12/3/2012 | P | PASS |
Dave Hannah
|
|
|
MANA Phone #: ###-####
|
Routing PW Grading-Hillside | 11/13/2012 | | 11/13/2012 | | PASS |
Jim Wyllie
|
|
|
Received footing subgrade approval from geotechnical engineer. Okay to schedule a footing inspection. Jim Wyllie (###-####)
|
Plan assigned to (CDM) | 10/9/2012 | 10/9/2012 | 11/6/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 11/6/2012 | | 11/6/2012 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/6/2012 | | DONE |
|
|
|
|
Telephone call | | | 11/6/2012 | | DONE |
Christina Prado
|
|
|
Called and spoke to Joe at Roth Homes - Verified ACHD credit was requested and gave fees due
|
Permit Ready to Issue | | | 11/6/2012 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 11/6/2012 | | DONE |
Barbara Stitt
|
|
|
|
1st review completed | | | 11/1/2012 | | FAIL |
|
|
|
|
Case Summary (BLD) | | | 11/1/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/19/2012 | | 11/1/2012 | | FAIL |
Carl D Madsen
|
|
|
Deck ledger attachement detail is required. Called Joe at Roth homes. 11-1-12 CDM
|
Plan resubmittals received | | | 10/23/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of ResCheck; took to Carl Madsen
|
Routing - FIRE | 10/16/2012 | | 10/19/2012 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Route to Impact Fee Review | 10/8/2012 | 10/11/2012 | 10/16/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 10/16/2012 | | 10/16/2012 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/15/2012 | | 10/15/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 10/11/2012 | | 10/15/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Building Energy
|
Routing - PLANNING | 10/11/2012 | | 10/11/2012 | | PASS |
Sue Cummings
|
|
|
10 day appeal period is completed. O.K. to issue SAC 11/1/12
|
Routing PW Grading-Hillside | | | 10/11/2012 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2012 | | 10/11/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 10/8/2012 | 10/9/2012 | | DONE |
|
|
|
|
Routing - Addressing | 10/9/2012 | | 10/9/2012 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/9/2012 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/9/2012 | | DONE |
|
|
|
|
Intake Approval | | | 10/9/2012 | | PASS |
|
|
|
|