BLD-Final | 12/17/2013 | 12/17/2013 | 12/17/2013 | P | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
Zoning Approval | 12/17/2013 | 12/17/2013 | 12/17/2013 | | DONE |
Joshua Johnson
|
|
|
|
Permanent Occupancy | | | 12/17/2013 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety passed. *Signature card not available on site.
|
BLD-Energy code compliance | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | PASS |
Jim Storey
|
|
|
bob Phone #: ###-#### for all 3 units
|
BLD-Energy code compliance | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | NR |
Jim Storey
|
|
|
bob Phone #: ###-#### for all 3 units
|
BLD-Energy code compliance | 9/5/2013 | 9/6/2013 | 9/6/2013 | P | NR |
Tom Arcoraci
|
|
|
bobby Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2013 | 9/5/2013 | 9/5/2013 | A | PART |
Tony Young
|
|
|
Bobby Phone #: ###-####,, c/n posted,, ok to insulate,,also need sprinklers signed off prior to cover
|
Plan resubmittals received | | | 8/20/2013 | | DONE |
|
|
|
new manual j reports
|
Routing - MECHANICAL | 8/20/2013 | | 8/20/2013 | | PASS |
Troy James
|
|
|
resubmitted manaul j reports for units 12,13,14
|
BLD-Wall Bracing | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Jim Storey
|
|
|
bob Phone #: ###-####
|
BLD-Other | 8/6/2013 | 8/7/2013 | 8/7/2013 | A | PASS |
Jim Storey
|
|
|
bob - fire wall Phone #: ###-#### gyp in attic ok
|
BLD-Footing | 6/6/2013 | 6/7/2013 | 6/7/2013 | P | PASS |
Jim Sly
|
|
|
joe Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/29/2013 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 3/29/2013 | | DONE |
Christina Prado
|
|
|
180day extension granted 3/28/13
|
Expiration Notice | 3/21/2013 | 4/11/2013 | 3/21/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 12/10/2012 | | |
|
|
|
|
Telephone call | | | 12/10/2012 | | DONE |
Christina Prado
|
|
|
called Todd to advise permit is ready and Rp is needed. Also gave fees due
|
Permit Ready to Issue | | | 12/10/2012 | | DONE |
Christina Prado
|
|
|
|
Route to Impact Fee Review | 12/7/2012 | 12/12/2012 | 12/7/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Print Occupancy Form | | | 12/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 12/5/2012 | | 12/7/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2012 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 10/11/2012 | | 12/7/2012 | | PASS |
Sam Zahorka
|
|
|
1st Review completed.
|
Routing - PUBLIC WORKS | 12/4/2012 | | 12/5/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Design | 12/4/2012 | | 12/4/2012 | | PASS |
Mike Sheppard
|
|
|
Applicant added sewer main line connection to the plans
|
Plan resubmittals received | | | 12/4/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of plan sheet P; inserted into plans by permit tech and routed to PW
|
Routing - PLAN CHECK | 11/30/2012 | | 11/30/2012 | | FAIL |
Sam Zahorka
|
|
|
Failed Sewer design.
|
Telephone call | | | 11/30/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with Todd Blackwell. Explained permit issuance is pending corrections for Public Works. Emailed Mike Sheppards contact info to Mr. Blackwell. He said he would follow up on Monday.
|
1st review completed | | | 11/29/2012 | | FAIL |
|
|
|
Failed PW
|
Routing - PLAN CHECK | 11/29/2012 | | 11/29/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing - FIRE | 11/28/2012 | | 11/29/2012 | | PASS |
Scott Arellano
|
|
|
Attached plan review comments to plans.
|
Routing - PLAN CHECK | 10/23/2012 | | 11/28/2012 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 10/22/2012 | | 10/23/2012 | | PASS |
Joshua Johnson
|
|
|
|
Routing - MECHANICAL | 10/22/2012 | | 10/22/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | | | 10/22/2012 | | PASS |
Daryl Spivey
|
|
|
general sizing and routing ok, add risers for the second floors.
|
Routing - Erosion and Sediment | 10/19/2012 | | 10/22/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Sewer Rating | | | 10/19/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 10/11/2012 | | 10/19/2012 | | FAIL |
Beverly Mountain
|
|
|
Did not pass Sewer Design. Show sewer service connection to main line.
|
Routing PW Sewer Design | 10/15/2012 | | 10/18/2012 | | FAIL |
Mike Sheppard
|
|
|
Show connection to public sewer main.
|
Routing PW Drainage | 10/12/2012 | | 10/15/2012 | | PASS |
Brian Murphy
|
|
|
CONDOS
|
Routing - Addressing | 10/11/2012 | | 10/11/2012 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 10/11/2012 | | 10/11/2012 | | PASS |
Todd Tucker
|
|
|
|
Intake Approval | | | 10/11/2012 | | PASS |
Sam Zahorka
|
|
|
Applicant will email ESC waiver.
|
Plans ACCEPTED BY PLAN TECH | | | 10/11/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/11/2012 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCM | 10/11/2012 | | 10/11/2012 | | DONE |
John Menard
|
|
|
|
First Notice | | 12/27/2013 | | | |
|
|
|
|