Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD12-02737
StatusFinaled
Name BLU STATIONS
Site Address 9100 S EISENMAN RD
Project NameBlu Transfuels
Customer Number 
ePlanReviewNo
Description
Blu Transfuels - Natural Gas Fueling Station - To construct a seven island LNG self service fueling station with fuel tanks and equipment. The north fueling islands will be covered by a 2,898 square foot steel moment frame canopy. The south fueling islands are not being covered with a canopy under this permit. There are two small modular equipment support buildings associated with project (8' x 10' and 8' x 20') that are not approved for installation until they have been approved by the State of Idaho. The concrete tank support and containment area and the modular building foundations were constructed under building permit BLD12-02907. There was a rough grading permit issued under BLD12-02662. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
MISC ACTIONS  11/14/2014 DONE
Attached final cert of value with e-mail as is. No response to get Jason from Transfuels to sign certs and never a response to mechanical values questions.
Print Statement  6/2/2014 DONE
DetailsTisha Gallop
e-mailed to Jason Evans at Blu Transfuels
Third Notice 2/8/20143/5/2014 DONE
Third Notice 12/4/20132/3/2014 DONE
e-mailed to Jason Evans at Blu Trans
PubWorks Occupancy Approval1/30/20141/30/20141/30/2014 DONE
DetailsTiffany Lowery
Third Notice 11/4/201311/29/2013 DONE
faxed to Benchmark
Second Notice 10/14/201310/30/2013 DONE
DetailsChristina Prado
First Notice 9/6/201310/4/2013 DONE
Permanent Occupancy  8/27/2013 DONE
BLD-Final8/26/20138/26/20138/26/2013PPASS
DetailsJim Storey
Chad Phone #: ###-####
BLD-Aging Inspection7/2/20137/2/20137/2/2013 DEFR
DetailsJim Storey
pending others sign offs.
Temporary Occupancy6/25/20139/23/20136/25/2013 DONE
DetailsDarla L Downs
Temporary Occupancy6/25/20139/23/20136/25/2013 DONE
DetailsDarla L Downs
BLD-Final4/30/20135/1/20135/1/2013APASS
DetailsJim Storey
Trent Ames Phone #: ###-#### perm. final ok pending all other sign offs
Zoning Approval5/1/20135/1/20135/1/2013 PASS
DetailsJosh Wilson
BLD-Final4/25/20134/26/20134/30/2013PCANC
DetailsJim Storey
Trent Phone #: ###-####
FIRE-Final Inspection4/16/20134/16/20134/17/2013APASS
DetailsForrest France
Fire life safety inspection passed.
BLD-Final4/12/20134/15/20134/15/2013PNR
DetailsJim Storey
trent Phone #: ###-####
FIRE-Final Inspection4/12/20134/12/20134/12/2013PCANC
DetailsForrest France
Fire life safety inspection completed acceptable. Final pending project related fire alarm work.
FIRE-Conference3/25/20133/25/20133/25/2013ADONE
DetailsForrest France
Conversation with contractor on site regarding knox box, new hydrant, review notes, IFC ch. 22 and 34, project related fire alarm permit, etc.
FIRE-Conference3/19/20133/20/20133/21/2013ADONE
DetailsForrest France
call when go out//Chad Taylor ###-####
BLD-Framing/Rough-in3/13/20133/13/20133/13/2013APASS
DetailsJim Storey
Issue PAID IN FULL permit  2/12/2013 DONE
DetailsChristina Prado
Meeting  12/19/2012 DONE
DetailsTisha Gallop
fees paid; still need ACHD before issue permit
Routing - FIRE12/10/201212/10/201212/13/2012 PASS
DetailsScott Arellano
Attached comments to permit case.
Plan assigned to (JCM)10/12/2012 12/13/2012 PASS
DetailsJohn Menard
1st review completed  12/13/2012 FAIL
Failed Public Works
Routing - PLAN CHECK12/13/2012 12/13/2012 PASS
DetailsJohn Menard
Project Manager (Ron Hill) took plan to plan check.
PLANS/APPL TAKEN TO FRONT DESK  12/13/2012 DONE
DetailsJohn Menard
Print Occupancy Form  12/13/2012 DONE
Telephone call  12/13/2012 DONE
DetailsTisha Gallop
called Chad Taylor and told him permit is ready, fee due, need ACHD.
Permit Ready to Issue  12/13/2012 DONE
DetailsTisha Gallop
Route to Impact Fee Review12/10/201212/13/201212/11/2012 PASS
DetailsCindy M. Gould
No impact fees buildings are under the fee threshold, canapies are not assessed impact fees.
Routing - PLAN CHECK11/2/2012 12/10/2012  
DetailsJohn Menard
Routing Off Site - STRUCTURAL12/4/2012 12/10/2012 PASS
DetailsJohn Menard
E-mailed the response and revised calcs and plan to the consulting engineer for review. JCM
Plan resubmittals received  12/6/2012 DONE
rec'd three copies of sheet structrual sheet 1 and three copies of transmittal sheet and calcs - inserted by Ron and taken to John M
Plan resubmittals requested  11/23/2012 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the structural review for the canopy requesting revisions. JCM
Routing Off Site - STRUCTURAL11/13/2012 11/21/2012 FAIL
DetailsJohn Menard
Called Action Courier for pick up @ 10:45am - Received comment list from consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  11/16/2012 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the plan review requesting revisions. JCM
1st review completed  11/16/2012 DONE
DetailsJohn Menard
Failed building, structural and Public Works. JCM
Routing - PLAN CHECK11/2/2012 11/16/2012 FAIL
DetailsJohn Menard
Plan resubmittals received  11/9/2012 DONE
DetailsChristina Prado
Received three sets of structural calcs and three sets of sheets marked 1 of 1. Also received two sets of additional full set drawings for Brian Murphy. Gave to Ron Hill to insert
Routing PW Drainage11/1/2012 11/2/2012 PASS
DetailsBrian Murphy
Routing PW Solid Waste11/2/2012 11/2/2012 PASS
DetailsPeter J. McCullough
Routing PW Street Lights11/2/2012 11/2/2012 PASS
DetailsMike D Hedge
Routing - PUBLIC WORKS11/2/2012 11/2/2012 PASS
DetailsConnie Baumgartner
Plan resubmittals received  11/1/2012  
Received 3 complete sets of plans and 3 copies of sheets C4.3, C6.3, E-600
Routing - PLAN CHECK10/24/2012 11/1/2012  
DetailsJohn Menard
John Menard
Routing Off Site - STRUCTURAL10/15/2012 10/26/2012 PASS
DetailsJohn Menard
Received letter from consulting structural engineer approving the structural portion of the project. JCM
Routing - PLANNING10/23/2012 10/24/2012 PASS
DetailsJosh Wilson
DRH12-00245 Josh Wilson
Routing - PUBLIC WORKS10/16/2012 10/23/2012 FAIL
DetailsConnie Baumgartner
Routing - Erosion and Sediment10/23/2012 10/23/2012 PASS
DetailsKimberly M. Johnson
ref ESC12-01001
Routing PW Solid Waste10/22/2012 10/23/2012 FAIL
DetailsPeter J. McCullough
Trash enclosure needs to be minimum of 10' deep. Gates are required to open 120 deg. w/ wind stops.
P. McCullough: ###-####
Routing PW Drainage10/17/2012 10/22/2012 FAIL
DetailsBrian Murphy
need detail of pond to basalt
Route to Impact Fee Review10/15/201210/18/201210/19/2012 PASS
DetailsCindy M. Gould
Routing PW Street Lights10/17/2012 10/18/2012 FAIL
DetailsMike D Hedge
Project requires street lighting, nothing on plans.
Routing - Addressing10/17/2012 10/17/2012 PASS
DetailsApril Wing
Routing PW Sewer Rating10/17/2012 10/17/2012 PASS
DetailsConnie Baumgartner
Routing - PLANNING Land Div10/16/2012 10/16/2012 PASS
DetailsTodd Tucker
Telephone call  10/15/2012 DONE
DetailsTisha Gallop
called Action couriers for pick up
Plans ACCEPTED BY PLAN TECH  10/12/2012 DONE
DetailsTisha Gallop
Pending Assignment by JCM10/12/2012 10/12/2012 DONE
DetailsJohn Menard
Application received 10/12/2012