Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-02741
StatusFinaled
Name JEFF REAM
Site Address 6121 W FRANKLIN RD
Project NameFRANKLIN AUTO SALES
Customer Number 
ePlanReviewNo
Description
FRANKLIN AUTO SALES - Shell Only Permit - To construct a new 2,065 square foot, one story, wood pole structure shell and related site improvements. The applicant has indicated that this building will be finished as an automobile detail shop. This is a shell permit only and no occupancy is allowed under this permit. A separate tenant improvement permit is required to finish this building for occupancy. No plumbing, electrical or mechanical work is approved under this permit. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Zoning Approval8/6/20138/6/20138/6/2013 PASS
DetailsJosh Wilson
Landscaping completed. Bond can be released.
Letter of compliance/Occupancy  8/6/2013 DONE
DetailsBarbara Stitt
DOC - C/O Approved  8/6/2013 DONE
DetailsBarbara Stitt
Temporary Occupancy6/11/20139/9/20136/11/2013 DONE
DetailsJason Blais
Temporary occupancy extension granted for 90 days see scanned documents
BLD-Aging Inspection6/10/20136/10/20136/10/2013 PEND
DetailsTom Arcoraci
Change Expiration Date Only  4/10/2013 DONE
DetailsBarbara Stitt
BLD-Aging Inspection4/8/20134/8/20134/8/2013 PASS
DetailsTom Arcoraci
Change Expiration Date Only  3/12/2013 DONE
DetailsBarbara Stitt
BLD-Final2/4/20132/4/20132/4/2013PPASS
DetailsTom Arcoraci
Temporary Occupancy2/4/20135/5/20132/4/2013 DONE
DetailsBarbara Stitt
Zoning Approval Temp2/4/20132/4/20132/4/2013 PASS
DetailsJosh Wilson
180 day temp for landscaping. Bond has been submitted.
Change Expiration Date Only  2/4/2013 DONE
DetailsBarbara Stitt
PubWorks Occupancy Approval1/28/20131/28/20131/28/2013 DONE
DetailsTiffany Lowery
BLD-Final1/24/20131/24/20131/24/2013PNR
DetailsTom Arcoraci
Dave Phone #: ###-#### needs zoning and public works sign off
FIRE-Final Inspection1/23/20131/23/20131/23/2013PPASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in12/12/201212/13/201212/13/2012APASS
DetailsMike Jordan
Dave Phone #: ###-####
BLD-Footing11/27/201211/28/201211/28/2012PPASS
DetailsTom Arcoraci
Dave Phone #: ###-####
OVERRIDE  11/13/2012  
Telephone call  11/13/2012 DONE
DetailsTisha Gallop
called Dave @ Cleary Bldg Corp and told him permit is ready, fees due, need RP, ACHD, GC form.
Issue PAID IN FULL permit  11/13/2012 DONE
DetailsTisha Gallop
Routing - PLAN CHECK11/9/2012 11/13/2012 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  11/13/2012 DONE
DetailsJohn Menard
Inspection Record Card- Bld  11/13/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  11/13/2012 DONE
DetailsTisha Gallop
Plan assigned to (JCM)10/15/2012 11/13/2012 PASS
DetailsJohn Menard
Routing - FIRE11/6/201211/6/201211/9/2012 PASS
DetailsScott Arellano
Attached plan review comments to plans.
1st review completed  11/9/2012 FAIL
Failed Planning
Routing - PLAN CHECK11/9/2012 11/9/2012  
DetailsJohn Menard
Routing - PLANNING11/9/2012 11/9/2012 PASS
DetailsJosh Wilson
Ok per resubmitted plans
Route to Impact Fee Review11/6/201211/9/201211/8/2012 PASS
DetailsCindy M. Gould
Route to Impact Fee Review10/15/201210/18/201211/8/2012 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK10/30/2012 11/6/2012 PASS
DetailsJohn Menard
John Menard
Plan Reviewer's activity  11/6/2012 PASS
DetailsJohn Menard
Shell permit approved as submitted. JCM
Plan resubmittals received  11/5/2012  
received two copies of plan sheets 1 of 8 and 2 of 8; inserted by arch. rep. and taken back to John Menard.
Routing - PLUMBING10/26/2012 10/30/2012 PASS
DetailsDaryl Spivey
no plumbing
Routing - PLANNING10/30/2012 10/30/2012 FAIL
DetailsJosh Wilson
No landscape plan submitted and building elevations do not match approved. Applicant contacted 10/30/12.
Routing - PUBLIC WORKS10/16/2012 10/26/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment10/26/2012 10/26/2012 PASS
DetailsKimberly M. Johnson
Routing PW Sewer Rating10/26/2012 10/26/2012 PASS
DetailsConnie Baumgartner
Routing PW Drainage10/17/2012 10/25/2012 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL10/15/2012 10/24/2012 PASS
DetailsJohn Menard
Called Action Couriers for pick up @ 9:40am//BAS
Routing - PLANNING Land Div10/16/2012 10/16/2012 PASS
DetailsDave Abo
Approved. Existing structure on parcel that was approved by prior Design Review.
Routing - Addressing10/15/2012 10/16/2012 PASS
DetailsDave Abo
Changed address to reflect current site plan
Pending Assignment by JCM10/15/2012 10/15/2012 DONE
DetailsJohn Menard
Recd Pcfee & Taken To Pln CK  10/12/2012 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  10/12/2012 DONE
DetailsBarbara Stitt
Intake Approval  10/12/2012 FAIL
DetailsTim L. Woodard
Intake Approval  10/12/2012 PASS
DetailsCarl Westfall
Application received 10/12/2012