First Notice | 6/10/2013 | 6/10/2013 | 7/1/2013 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 6/7/2013 | 6/10/2013 | 6/10/2013 | A | PASS |
Jim Storey
|
|
|
gary Phone #: ###-####
|
DOC - Permit Finaled | 6/10/2013 | 6/10/2013 | 6/10/2013 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | FAIL |
Jim Storey
|
|
|
gary Phone #: ###-#### need exit sign and ele permit grouped
|
FIRE-Final Inspection | 5/31/2013 | 6/3/2013 | 6/3/2013 | A | PASS |
Forrest France
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/3/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - FIRE | | | 3/21/2013 | | PASS |
|
|
|
Approved by Jason Blais - Building Code Offical and approved by Romeo Gervais - Fire Code Offical. Approval based on a letter 03-11-2013, additional information from prior evaluations and contact with Paul Marcolina - Micron. Review processed for the above parties by Tim Frost
|
Plan assigned to (JCM) | 3/4/2013 | | 3/21/2013 | | |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2013 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 3/21/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 3/21/2013 | | DONE |
Tisha Gallop
|
|
|
Issue permit per JCM
|
1st review completed | | | 12/14/2012 | | FAIL |
Tim Frost
|
|
|
|
Routing - PLAN CHECK | 10/12/2012 | | 12/14/2012 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 10/12/2012 | | 12/14/2012 | | FAIL |
Tim Frost
|
|
|
|
Meeting | | | 12/14/2012 | | DONE |
|
|
|
Meeting with Paul Marcoline, John Menard, Tim Frost 12-13-12
The meeting discussed the hallway in which HPM will be transported.
This is the fourth meeting. The first three times the plans were denied due to eggress and service corridor requirments.
In this meeting Paul explained his concept of the entire building is a H5 occupancy. There are no service corridors. Paul, said there was a similar project a number of years ago, where the entire building was classified as a H5. Paul, is to provide the BLD number. There was apparently an independent consultant hired to review the concept of treating the entire building as an H5. Paul, said the city approved the prior project based upon this research. At this time, I have nothing in writing to support this concept. The project is on hold until Paul supplies the BLD number or the documentation.
|
Application received | | | 10/12/2012 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|
Plan assigned from Web | 10/12/2012 | 10/22/2012 | | | |
|
|
|
|