Second Notice | | 5/2/2013 | 5/20/2013 | | DONE |
|
|
|
|
First Notice | | 4/15/2013 | 4/22/2013 | | DONE |
|
|
|
mailed to David Madvin at Spokane, WA address.
|
Print Occupancy Form | | | 4/5/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permanent Occupancy | | | 4/5/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 3/22/2013 | 3/28/2013 | 3/28/2013 | P | PASS |
Dave Hannah
|
|
|
David Phone #: ###-####6
|
BLD-Aging Inspection | 3/8/2013 | 3/8/2013 | 3/13/2013 | | PEND |
Dave Hannah
|
|
|
|
Change Expiration Date Only | | | 3/12/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 12/21/2012 | 12/31/2012 | 1/2/2013 | P | PART |
Dave Hannah
|
|
|
rusty Phone #: ###-#### ok for temp occ needs to finish ada door hardwaer on sliding doors and grab bars in restrooms
|
FIRE-Final Inspection | 12/21/2012 | 12/31/2012 | 12/31/2012 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
Temporary Occupancy | 12/31/2012 | 3/31/2013 | 12/31/2012 | | DONE |
Tisha Gallop
|
|
|
pending plumbing and structural ///changed name from "Elite Spa" to "The Studio an Elite Salon and Spa"
|
FIRE-Conference | 12/28/2012 | 12/28/2012 | 12/28/2012 | A | DONE |
Forrest France
|
|
|
Regarding fire sprinkler permit work.
|
FIRE-Conference | 12/26/2012 | 12/26/2012 | 12/27/2012 | P | DONE |
Forrest France
|
|
|
On site conference with tenant completed 12/26 regarding project related fire alarm work, life safety conditions, and modifications to the existing fire sprinkler system required due to the remodel.
|
Issue PAID IN FULL permit | | | 11/23/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 11/5/2012 | | 11/21/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/21/2012 | | 11/21/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 11/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 11/21/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 11/21/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/21/2012 | | |
|
|
|
|
Telephone call | | | 11/21/2012 | | |
|
|
|
11-21-12 called Stan Cole left message permit ready and fee given ///dld
|
Routing - MECHANICAL | 11/6/2012 | | 11/16/2012 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/16/2012 | | DONE |
Tisha Gallop
|
|
|
received two coipes of plan sheets A0.0, A1.0, A5.0; taken to Tim Woodard.
|
Plan resubmittals received | | | 11/15/2012 | | |
|
|
|
11-15-12 received 2 copies of sheets M0.0,M2.1,M3.0,E2.0 sent to Tim W.
|
Routing - MECHANICAL | 11/6/2012 | | 11/6/2012 | | FAIL |
Troy James
|
|
|
fax correction to DC engineering
|
Plan assigned to (CDM) | 10/17/2012 | 10/17/2012 | 11/5/2012 | | DEFR |
Carl D Madsen
|
|
|
Deffered review to Tim W.
|
Routing - PLAN CHECK | 10/19/2012 | | 11/5/2012 | | FAIL |
Tim L. Woodard
|
|
|
Need resubmittals.
|
1st review completed | | | 11/5/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 11/5/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets M2.1, M3.0, E2.0; taken to Carl Madsen
|
Plan resubmittals received | | | 11/2/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheet A5.0; taken to Tim Woodard.
|
Plan resubmittals received | | | 11/1/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets A0.0, A1.0, A5.0; taken to Carl Madsen
|
Routing - MECHANICAL | 10/19/2012 | | 10/19/2012 | | FAIL |
Troy James
|
|
|
emailed correction to engineer
|
Routing - PLUMBING | 10/18/2012 | | 10/19/2012 | | PASS |
Bill VanDegrift
|
|
|
120 deg. max to shower and lavs
|
Routing - PUBLIC WORKS | 10/17/2012 | | 10/18/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 10/18/2012 | | 10/18/2012 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 10/18/2012 | | 10/18/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 10/17/2012 | 10/17/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/17/2012 | | DONE |
Tisha Gallop
|
|
|
|