BLD-Final | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
DOC - Permit Finaled | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 2/27/2013 | 2/28/2013 | 2/28/2013 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
BLD-Framing/Rough-in | 2/21/2013 | 2/22/2013 | 2/22/2013 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
BLD-Wall Bracing | 2/22/2013 | 2/22/2013 | 2/22/2013 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by SHANE JAYO
|
Plan resubmittals received | | | 2/14/2013 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 2/14/2013 | | 2/14/2013 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
CHANGE STATUS TO (ISS) | | | 2/14/2013 | | DONE |
|
|
|
|
BLD-Foundation | 12/27/2012 | 12/28/2012 | 1/3/2013 | P | DONE |
Tony Young
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 12/26/2012 | 12/26/2012 | 12/31/2012 | P | DONE |
Tony Young
|
|
|
Bill Phone #: ###-#### - around 2 ish
|
BLD-Footing | 12/26/2012 | 12/27/2012 | 12/27/2012 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-#### - around noon
|
BLD-Footing | 12/20/2012 | 12/26/2012 | 12/26/2012 | P | PART |
Tony Young
|
|
|
Bill Phone #: ###-#### - around noon/// work in progress,,
|
Routing PW Grading-Hillside | 12/26/2012 | | 12/26/2012 | | PASS |
Jason C. Taylor
|
|
|
Recieved geotechnical engineers approval for footing subgrade inspection. See MTI report dated 12/26/2012.
|
Issue PAID IN FULL permit | | | 12/19/2012 | | DONE |
|
|
|
|
OVERRIDE | | | 12/17/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/17/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 12/17/2012 | | DONE |
|
|
|
lm for shane permit ready fees given need rp
|
Permit Ready to Issue | | | 12/17/2012 | | DONE |
|
|
|
|
Plan assigned to (CDM) | | 10/18/2012 | 12/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/14/2012 | | 12/14/2012 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/14/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2012 | | |
|
|
|
|
Plan resubmittals received | | | 12/13/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 12/3/2012 | | 12/4/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Plan resubmittals received | | | 11/29/2012 | | DONE |
Christina Prado
|
|
|
Received two ESC Narratives as well as two ESC plans;routed to Carl Madsen
|
Routing - FIRE | | | 11/21/2012 | | PASS |
Scott Arellano
|
|
|
No fire sprinkler per Scott 11-21-12 CDM
|
1st review completed | | | 11/21/2012 | | FAIL |
|
|
|
|
Routing - PLANNING | 11/21/2012 | | 11/21/2012 | | PASS |
Susan Riggs
|
|
|
Roof overhang may not extend more than 2' into the required setbacks.
|
Routing - PLAN CHECK | 11/8/2012 | | 11/21/2012 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 11/20/2012 | | 11/20/2012 | | FAIL |
Kimberly M. Johnson
|
|
|
Need ESC Plan
|
Plan resubmittals received | | | 11/15/2012 | | DONE |
Tisha Gallop
|
|
|
received modified plans to reflect change in roof overhang; received two copies of reduced site plan and plan sheets 1-12. taken to Carl Madsen
|
Routing - PUBLIC WORKS | 11/6/2012 | | 11/8/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 11/6/2012 | | 11/8/2012 | | PASS |
Jim Wyllie
|
|
|
Prior to scheduling a footing inspection, applicant's geotechnical engineer must provide a letter to Public Works indicating that the footing subgrade is acceptable. Jim Wyllie (###-####)
|
Routing - MECHANICAL | 10/30/2012 | | 10/30/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 10/22/2012 | | 10/23/2012 | | FAIL |
Troy James
|
|
|
emailed correction to Idaho HVAC
|
Routing - PLANNING | 10/19/2012 | | 10/22/2012 | | FAIL |
Susan Riggs
|
|
|
There are portion of the roof that overhang 3' into the setback where only 2' is allowed. I called the applicant on 10-19-12 and left a message regarding my concers and reminded Dough Jayo today that revisions are required.
|
Route to Impact Fee Review | 10/18/2012 | 10/23/2012 | 10/19/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | | | 10/19/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 10/18/2012 | 10/18/2012 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/18/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 10/18/2012 | | PASS |
Christina Prado
|
|
|
|
Routing - Addressing | 10/18/2012 | | 10/18/2012 | | PASS |
April Wing
|
|
|
|