Print Statement | | | 10/10/2013 | | DONE |
Barbara Stitt
|
|
|
|
Third Notice | | 9/3/2013 | 9/30/2013 | | DONE |
|
|
|
mailed to Fred Schuerman
|
Third Notice | | 8/6/2013 | 8/29/2013 | | DONE |
Tisha Gallop
|
|
|
faxed to Fred Schuerman
|
Second Notice | | 7/12/2013 | 8/1/2013 | | DONE |
|
|
|
Faxed 8/1/13
|
First Notice | | 6/13/2013 | 7/2/2013 | | DONE |
Barbara Stitt
|
|
|
faxed 7-2-13
|
BLD-Final | 6/3/2013 | 6/3/2013 | 6/3/2013 | P | PASS |
Tom Arcoraci
|
|
|
Dave Phone #: ###-####
|
BLD-Final | 6/3/2013 | 6/3/2013 | 6/3/2013 | P | PASS |
Tom Arcoraci
|
|
|
Dave Phone #: ###-#### ok for perm
|
Permanent Occupancy | | | 6/3/2013 | | DONE |
Christina Prado
|
|
|
|
Temporary Occupancy | 5/31/2013 | 8/29/2013 | 5/31/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan Reviewer's activity | | | 5/29/2013 | | DONE |
Sam Zahorka
|
|
|
Received completed parcel consolidation record of survey. Called the inspector and informed him it's ok to issue Final C.of O based on receiving approved R.O.S. and parcel consolidation.
|
Plan Reviewer's activity | | | 4/25/2013 | | DONE |
Sam Zahorka
|
|
|
Called the inspector Tom Arcoraci and let him know the interior lot lines have been Removed. We are still waiting for Planning and Land Division to pass ROS prior to Final occupancy.
|
BLD-Aging Inspection | 4/22/2013 | 4/22/2013 | 4/22/2013 | | PEND |
Tom Arcoraci
|
|
|
|
Temporary Occupancy | 2/21/2013 | 5/22/2013 | 2/21/2013 | | DONE |
Darla L Downs
|
|
|
|
BLD-Final | 2/20/2013 | 2/20/2013 | 2/20/2013 | P | PART |
Jim Storey
|
|
|
Dave Phone #: ###-#### ada signage to be on latch side of door/ papper desp. instaled// p/l to be resolved for perm. occ. per bo letter with card.
|
FIRE-Final Inspection | 2/20/2013 | 2/20/2013 | 2/20/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Sam and Bill Matter worked out the door hardware issues.
|
Plan Reviewer's activity | | | 2/20/2013 | | DONE |
Sam Zahorka
|
|
|
The sliding glass doors in offices #3, #4, #9, #10, and #11 are not required means of egress doors. The door hardware is not required to comply with the 2009 IBC section 1008.1.9. This decision is based on the travel distance being 75 feet or less to an exit door. A new floor plan showing the travel distances is attached to this permit. SRZ
|
Telephone call | | | 2/20/2013 | | DONE |
Sam Zahorka
|
|
|
Spoke with the architect and the Fire Inspector. Hardware on office sliding doors is not required to comply with means of egress hardware provisions or accessibility.
|
FIRE-Final Inspection | 2/15/2013 | 2/19/2013 | 2/19/2013 | A | FAIL |
Troy Cobbley
|
|
|
The door hardware issues for the sliding glass doors needs addressed. I spoke to the architect about the requirements and deferred him to plan review to revisit the requirements and if they want a re-assesment of the original plan reviewer interpretation.
|
FIRE-Final Inspection | 2/15/2013 | 2/15/2013 | 2/15/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Dave is going to reschedule for tuesday.
|
BLD-Framing/Rough-in | 12/19/2012 | 12/20/2012 | 12/20/2012 | A | PASS |
Jim Sly
|
|
|
dave Phone #: ###-####
|
Permit Ready to Issue | | | 12/19/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 12/19/2012 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/19/2012 | | |
|
|
|
|
Routing - PUBLIC WORKS | 11/21/2012 | | 12/19/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Plan assigned to (DRS) | 11/6/2012 | 11/6/2012 | 12/18/2012 | | PASS |
Dan Stuart
|
|
|
Failed 1st review - eplanreview
|
Routing - PLAN CHECK | 11/29/2012 | | 12/18/2012 | | PASS |
Dan Stuart
|
|
|
Approved with property line issue commitment letter from owner & approved by building official attached to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2012 | | PASS |
Dan Stuart
|
|
|
|
Plan resubmittals received | | | 11/29/2012 | | PEND |
|
|
|
Received new plan sheets A0.0, A1.1 and E1. Waiting for letter from architect and owner committing to address property line issues before a permanent C.O. can be issued.
|
Routing - PLAN CHECK | 11/27/2012 | | 11/29/2012 | | FAIL |
Dan Stuart
|
|
|
Plan resubmittals provided.Waiting for letter from owner acknowledging need for plat modification and agrement to proceed to make needed modifications as required for Planning land Div., Dave Abo. A final c.O. cannot be issued until the property line issues are resolved.
|
Plan resubmittals requested | | | 11/29/2012 | | DONE |
|
|
|
E-mail sent to Bill Matter , Architect, concerning required letter from owner, as jason Blais, Building Official had previously disgussed with Bill Matter. Bill Matter was directed to contact Jason directly if he needed clarification about what was to be included in the letter. A copy of the email is attached to this permit.
|
Routing - PLANNING Land Div | 11/26/2012 | | 11/27/2012 | | PASS |
Dave Abo
|
|
|
This is not a condominium. It is a subdivision (Emerald Professional Park). Prior to issuance of Certificate of Occupancy, a Record of Survey - Property Line Adjustment must be recorded for Building "B" that will include changes in 2009 and 2010.
|
1st review completed | | | 11/27/2012 | | FAIL |
Dan Stuart
|
|
|
Failed plan review.
|
Plan resubmittals requested | | | 11/27/2012 | | DONE |
|
|
|
Copy of agency comments plan review sent to architect.
|
Routing - FIRE | 11/21/2012 | | 11/26/2012 | | PASS |
Scott Arellano
|
|
|
Attached Comments to plans.
|
Routing - PLAN CHECK | 11/21/2012 | | 11/26/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review emailed to Bill Matter and attached to permit. Pending plan review by Planning Land Div.
|
Routing PW Sewer Rating | 11/23/2012 | | 11/23/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 11/21/2012 | | 11/21/2012 | | PASS |
April Wing
|
|
|
|
Intake Approval | | | 11/6/2012 | | PASS |
|
|
|
|
Application received | | | 10/19/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 19 2012 11:17AM
|