BLD-Final | 9/5/2013 | 9/5/2013 | 9/5/2013 | P | PASS |
Jim Sly
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 9/5/2013 | 9/5/2013 | 9/5/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 5/2/2013 | 5/2/2013 | 5/2/2013 | P | PASS |
Jim Storey
|
|
|
Raul Phone #: ###-####
|
BLD-Framing/Rough-in | 5/2/2013 | 5/2/2013 | 5/2/2013 | P | PASS |
Jim Storey
|
|
|
Raul Phone #: ###-####
|
BLD-Framing/Rough-in | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | FAIL |
Mike Jordan
|
|
|
Rollo Phone #: ###-####. NAil ply G@ and C1 hip trussed per truss engineering, complete lateral bracing on C3 and C6 trusses. Fireblock window popout @ ceiling level upstairs bedroom. Provide a 7 by 7 inch column to provide full bearing for the (4) 1.75x11.875 micro lam. Correction notice posted. Ok to insulate.
|
Plan resubmittals received | | | 4/16/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 4/16/2013 | | 4/16/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Dave Hannah
|
|
|
rollo Phone #: ###-####
|
BLD-Foundation | 2/28/2013 | 3/5/2013 | 3/5/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 2/28/2013 | 3/4/2013 | 3/5/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 11/21/2012 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 11/20/2012 | | |
|
|
|
|
Plan assigned to (CDM) | 10/23/2012 | 10/23/2012 | 11/20/2012 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 11/20/2012 | | 11/20/2012 | | PASS |
Susan Riggs
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 11/20/2012 | | DONE |
Christina Prado
|
|
|
Called Bryan to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 11/20/2012 | | DONE |
Christina Prado
|
|
|
|
Case Summary (BLD) | | | 11/19/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/19/2012 | | 11/19/2012 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 11/15/2012 | | DONE |
Christina Prado
|
|
|
Received two full sets of revised plans marked A0.0, A1.0, A1.1, BW1.0, BW1.1, A2.0, A2.1, S1.0, S1.1, S2.0, S2.1, E1.0 & E1.1; Gave plans to Carl Madsen for further review
|
Routing - PLAN CHECK | 11/15/2012 | | 11/15/2012 | | FAIL |
Carl D Madsen
|
|
|
Updated shear wall engineering and wrightsoft is required. Called Brian at Boise Hunter. 11-15-12 CDM
|
Routing - PLAN CHECK | 11/2/2012 | | 11/9/2012 | | FAIL |
Carl D Madsen
|
|
|
New plans will be resubmitted. Failed in planning. 11-9-12 CDM
|
1st review completed | | | 11/9/2012 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 10/24/2012 | | 11/2/2012 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/23/2012 | 10/26/2012 | 10/25/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 10/23/2012 | | 10/24/2012 | | FAIL |
Susan Riggs
|
|
|
22' of back-up is required for parking. the garage bay on the west has only a 17'-2' setback. Additonally there is a 3' landscape setback required along the along the rear (south) property line. The applicant has been notified.
|
Application received | | 10/23/2012 | 10/23/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Addressing | 10/23/2012 | | 10/23/2012 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2012 | | 10/23/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2012 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 10/23/2012 | | PASS |
Barbara Stitt
|
|
|
|