Second Notice | | 5/10/2013 | 5/17/2013 | | DONE |
|
|
|
|
First Notice | | 4/4/2013 | 4/30/2013 | | DONE |
|
|
|
Faxed 4-30-13
|
Permanent Occupancy | | | 3/25/2013 | | DONE |
|
|
|
|
BLD-Final | 3/18/2013 | 3/18/2013 | 3/18/2013 | P | PASS |
Tony Young
|
|
|
Brandy--PLease call at least 30 mins prior to inspection Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2013 | 3/18/2013 | 3/18/2013 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
Zoning Approval | 3/18/2013 | 3/18/2013 | 3/18/2013 | | DONE |
Joshua Johnson
|
|
|
|
Print Occupancy Form | | | 3/18/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Other | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | PART |
Mike Jordan
|
|
|
Jim ###-#### // bracket insp. Work in progress. tube steel structure erected with A-325 bolts as per approved plans. Contractor in progress on installing treated boards prior to slats. Noted to contractor that tec screws need to be installed at 12" o.c. not 16 " o.c.
|
BLD-Footing | 12/13/2012 | 12/14/2012 | 12/14/2012 | A | PASS |
Tony Young
|
|
|
jim Phone #: ###-####,, per plan,, ok
|
OVERRIDE | | | 12/10/2012 | | |
|
|
|
|
Application received | | 12/10/2012 | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 12/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 11/26/2012 | | 11/27/2012 | | PASS |
Kimberly M. Johnson
|
|
|
Waiver approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2012 | | DONE |
John Menard
|
|
|
|
MISC ACTIONS | | | 11/27/2012 | | DONE |
Christina Prado
|
|
|
Approved plans will look different as all plans and documents are only 8 1/2 X 11 with the only exception being the Site plan (Cover sheet). Any questions ask Rita or Christina
|
Plan assigned to (JCM) | 11/19/2012 | | 11/27/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 11/19/2012 | | 11/21/2012 | | PASS |
John Menard
|
|
|
|
Routing PW Grading-Hillside | 11/19/2012 | | 11/21/2012 | | PASS |
Jim Wyllie
|
|
|
|
1st review completed | | | 11/21/2012 | | FAIL |
John Menard
|
|
|
Failed erosion
|
Route to Impact Fee Review | 11/19/2012 | 11/23/2012 | 11/20/2012 | | PASS |
Cindy M. Gould
|
|
|
Open sided picnic shelter no impact fees
|
Routing - FIRE | 11/19/2012 | 11/19/2012 | 11/20/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached with plans.
|
Routing PW Drainage | 11/19/2012 | | 11/20/2012 | | PASS |
Brian Murphy
|
|
|
LESS THAN 500 SQ FT
|
Routing - PLANNING | 11/19/2012 | | 11/20/2012 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PLANNING Land Div | 11/19/2012 | | 11/20/2012 | | PASS |
Dave Abo
|
|
|
Structure to be built on Lot 27 of Eyrie Canyon #6. Structure must be completed prior to City Engineer's signature on Final Plat as per conditions of the Conditional Use.
|
Routing - Addressing | 11/19/2012 | | 11/20/2012 | | PASS |
April Wing
|
|
|
|
Routing - Erosion and Sediment | 11/19/2012 | | 11/20/2012 | | FAIL |
Kimberly M. Johnson
|
|
|
Before a determination can be made, the waiver letter needs more detail on the BMPs to protect the adjacent riparian area and water conveyance. Waiver letter needs to elaborate on the anticipated non storm water discharges the project expects to have (may be a typo). Left message for Linda 11/20 12:15 PM
|
Intake Approval | | | 11/19/2012 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCM | 11/19/2012 | | 11/19/2012 | | DONE |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2012 | | 11/19/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | | 10/23/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 23 2012 2:07PM
|