Permit Information
Permit NumberBLD12-02848
StatusFinaled
Name BERKELEY BUILDING COMPANY INC
Site Address 1044 E INSIGNIA DR
Project NameKerner Residence
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 3256 sq. ft., two story (first story 1354 sq. ft., second story 1123 sq. ft., basement level 779 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately sq. ft. of covered patio/porch and a 846 sq. ft. attached garage per the approved plans, plan review report and any notations. R2-D zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/7/20135/7/20135/7/2013PPASS
DetailsJim Storey
Ray-Please call for access info Phone #: ###-####
DOC - Permit Finaled5/7/20135/7/20135/7/2013PPASS
DetailsJim Storey
PubWorks Occupancy Approval5/7/20135/7/20135/7/2013 DONE
DetailsJason C. Taylor
Recieved civil engineers acceptance letter for drainage conditions. A roof drainage pipe was placed on the east side of the house and was approved by P.W. C of O my be given. Jason Taylor ###-####.
BLD-Final5/3/20135/6/20135/6/2013APART
DetailsJim Storey
call for access - ray Phone #: ###-#### perimitor insulation computer rm crawl space pw sign off
BLD-Final4/26/20134/29/20134/29/2013PNR
DetailsJim Storey
ray please call for access Phone #: ###-#### pending hillside pw insp.
BLD-Final4/25/20134/26/20134/26/2013PDEFR
DetailsJim Storey
ray please call for access Phone #: ###-####
BLD-Energy code compliance3/7/20133/8/20133/8/2013APASS
DetailsJim Storey
Ray Phone #: ###-####
BLD-Framing/Rough-in3/7/20133/8/20133/8/2013APASS
DetailsJim Storey
Ray Phone #: ###-####
BLD-Framing/Rough-in3/4/20133/5/20133/5/2013PPART
DetailsJim Storey
Ray Phone #: ###-#### mech failled// no under floor accesses// mlb floor roof support need 2-117/8 under fire place.
Plan resubmittals received  3/5/2013 DONE
new manual j
Routing - MECHANICAL3/5/2013 3/5/2013 PASS
DetailsTroy James
resubmitted acca report
BLD-Other2/25/20132/25/20132/25/2013APART
DetailsJim Storey
double king studs needed for framing insp.
BLD-Wall Bracing2/25/20132/25/20132/25/2013APASS
DetailsJim Storey
exterior ok to cover
BLD-Other2/15/20132/19/20132/19/2013APASS
DetailsJim Storey
under floor inspection--Carlos Phone #: ###-####
BLD-Footing2/4/20132/5/20132/5/2013APASS
DetailsJim Storey
jared Phone #: ###-####
BLD-Other1/2/20131/2/20131/2/2013PPASS
DetailsJim Storey
jared- basement Phone #: ###-#### walls sealled ok to back fill.
BLD-Footing12/27/201212/28/201212/28/2012APASS
DetailsJim Storey
Jerad Phone #: ###-####
Routing PW Grading-Hillside12/20/2012 12/20/2012 PASS
DetailsJim Wyllie
Received footing subgrade approval from geotechnical engineer. Okay to schedule a footing inspection. Jim Wyllie (###-####)
BLD-Footing12/18/201212/18/201212/19/2012PPART
DetailsJim Storey
JEROD Phone #: ###-#### ft ok pendind pw sign off.
Plan assigned to (CDM)10/26/201210/26/201212/13/2012 DONE
DetailsCarl D Madsen
Project Dox
OVERRIDE  12/11/2012  
Inspection Record Card- Bld  12/11/2012 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  12/11/2012 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  12/11/2012 DONE
Routing - PLAN CHECK12/11/2012 12/11/2012 PASS
DetailsCarl D Madsen
Permit Ready to Issue  12/11/2012 DONE
DetailsBarbara Stitt
Routing - MECHANICAL11/29/2012 11/29/2012 PASS
DetailsTroy James
eplan
1st review completed  11/15/2012 FAIL
Routing - PLAN CHECK10/29/2012 11/15/2012 FAIL
DetailsCarl D Madsen
Shear wall engineering is required. 11-15-12 CDM
Route to Impact Fee Review10/26/201210/31/201211/5/2012 PASS
DetailsCindy M. Gould
Routing PW Grading-Hillside10/26/2012 11/2/2012 PASS
DetailsJim Wyllie
Retaining wall plans not provided. Drainage swale along east property line is too steep. Jim Wyllie (###-####) Approved in Eplan review CDM
Routing - MECHANICAL10/26/2012 10/30/2012 FAIL
DetailsTroy James
eplan, pressure losses for duct summary
Routing - FIRE10/29/2012 10/29/2012 PASS
DetailsScott Arellano
No comments.
Routing - Addressing10/26/2012 10/29/2012 PASS
DetailsApril Wing
Routing - PUBLIC WORKS10/26/2012 10/29/2012 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment10/26/2012 10/29/2012 PASS
DetailsKimberly M. Johnson
Routing PW Sewer Rating10/29/2012 10/29/2012 PASS
DetailsConnie Baumgartner
Payment Received  10/26/2012 DONE
Payment received via Govolutions
Plans ACCEPTED BY PLAN TECH  10/26/2012 DONE
DetailsChristina Prado
Intake Approval  10/26/2012 PASS
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  10/26/2012 DONE
DetailsChristina Prado
Routing - PLANNING  10/26/2012 PASS
Application received  10/25/2012 DONE
Application submitted via PDS Online on Oct 25 2012 10:27AM
Intake Approval  10/25/2012 FAIL