First Notice | | 2/2/2015 | 7/29/2019 | | DONE |
|
|
|
sent in 306 form for final values
|
Print Statement | | | 7/29/2019 | | DONE |
|
|
|
|
Print Statement | | | 7/29/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/20/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Zoning Approval | 1/23/2015 | 1/23/2015 | 1/23/2015 | | PASS |
Josh Wilson
|
|
|
Fencing complete and bond can be released.
|
Permanent Occupancy | | | 1/23/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/22/2015 | 1/22/2015 | 1/22/2015 | P | PASS |
Dave Hannah
|
|
|
###-#### Kent
|
FIRE-Final Inspection | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | PASS |
Forrest France
|
|
|
C/N items completed. Fire life safety finaled.
|
BLD-Final | 1/6/2015 | 1/13/2015 | 1/15/2015 | P | PEND |
Dave Hannah
|
|
|
call from Kent to change to tuesday afternoon 1-9-15 blh // Kent Phone #: ###-####
|
BLD-Final | 1/14/2015 | 1/14/2015 | 1/15/2015 | A | PART |
Dave Hannah
|
|
|
call from Kent to change to tuesday afternoon 1-9-15 blh // Kent Phone #: ###-#### ok for temp
|
FIRE-Final Inspection | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PART |
Forrest France
|
|
|
Fire life safety inspection completed. Previous correction items finished. Okayed for TCO.
|
Temporary Occupancy | 1/15/2015 | 4/15/2015 | 1/15/2015 | | DONE |
Kristal Soland
|
|
|
|
Zoning Approval Temp | 1/14/2015 | 1/14/2015 | 1/14/2015 | | PASS |
Josh Wilson
|
|
|
90-day temp occ.- bond in is place for incomplete fencing
|
FIRE-Alarm Testing | 1/12/2015 | 1/13/2015 | 1/13/2015 | A | PART |
Forrest France
|
|
|
Kent Phone #: ###-####
|
Case Summary (BLD) | | | 1/13/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Conference | 1/9/2015 | 1/12/2015 | 1/12/2015 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
FIRE-Final Inspection | 1/6/2015 | 1/8/2015 | 1/8/2015 | A | NR |
Forrest France
|
|
|
Need project related fire alarm and sprinkler permit finals, refer to fire code review notes for details regarding signage at fire lanes and area of refuge requirements.
|
PubWorks Occupancy Approval | 1/7/2015 | 1/7/2015 | 1/7/2015 | | DONE |
Jason C. Taylor
|
|
|
Drainage completed. Ok for occupancy. Jason Taylor ###-####
|
FIRE-Final Inspection | 1/5/2015 | 1/6/2015 | 1/6/2015 | P | CANC |
Forrest France
|
|
|
Kent-Kent would like to know if you can please do at noon when you do your fire final Phone #: ###-####
|
BLD-Final | 12/31/2014 | 1/2/2015 | 1/5/2015 | A | NR |
Dave Hannah
|
|
|
Kent-partial Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/24/2014 | 12/24/2014 | 12/24/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-#### 3rd and 4th fl corr
|
BLD-Ceiling Grid Inspection | 12/23/2014 | 12/23/2014 | 12/24/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### 1st and 2nd floor corr ok to cover
|
BLD-Framing/Rough-in | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-#### hard lid ground floor around elevator ok to cover
|
BLD-Framing/Rough-in | 12/15/2014 | 12/15/2014 | 12/16/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-#### hard lids around elevators 2,3,4 floors
|
BLD-Footing | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Dave Hannah
|
|
|
possibly 11// Kent Phone #: ###-#### car port ftgs
|
FIRE-Conference | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | DONE |
Forrest France
|
|
|
Regarding egress at stairways.
|
BLD-Energy code compliance | 10/22/2014 | 10/22/2014 | 10/22/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 10/16/2014 | 10/16/2014 | 10/16/2014 | P | PASS |
Dave Hannah
|
|
|
1st fl - Kent Phone #: ###-####
|
BLD-Energy code compliance | 10/9/2014 | 10/10/2014 | 10/10/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 10/7/2014 | 10/7/2014 | 10/7/2014 | P | PASS |
Dave Hannah
|
|
|
4th fl - Tim Phone #: ###-####
|
BLD-Energy code compliance | 10/3/2014 | 10/6/2014 | 10/6/2014 | A | PASS |
Dave Hannah
|
|
|
units 409, 410, 411, 412, 413 // kent Phone #: ###-#### also 414 true 418 ok to cover
|
BLD-Energy code compliance | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-#### - units 401, 402, 405, 406 ok to cover
|
BLD-Energy code compliance | 9/30/2014 | 10/1/2014 | 10/1/2014 | A | CANC |
Dave Hannah
|
|
|
UNITS 408 & 410 - KEN Phone #: ###-#### ok to cover 408 and 409
|
BLD-Energy code compliance | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### foru more rooms on the forth floor ok to rock
|
BLD-Energy code compliance | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 9/22/2014 | 9/22/2014 | 9/23/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 9/18/2014 | 9/19/2014 | 9/19/2014 | A | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 9/16/2014 | 9/16/2014 | 9/17/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Framing/Rough-in | 9/15/2014 | 9/15/2014 | 9/16/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-#### ok to insulate rest of second floor and cover two more rooms on third
|
BLD-Energy code compliance | 9/10/2014 | 9/10/2014 | 9/11/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### ok to cover the two rooms onwest end second floor and west 8 rooms on 3rd floor
|
BLD-Energy code compliance | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### four westerly rooms on third floor ok to cover
|
BLD-Energy code compliance | 9/4/2014 | 9/5/2014 | 9/5/2014 | A | PART |
Dave Hannah
|
|
|
kent Phone #: ###-#### ok to cover second floor all but four aprt on ends
|
BLD-Energy code compliance | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Energy code compliance | 9/2/2014 | 9/2/2014 | 9/3/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### west half of 4th floor ok to inslate
|
BLD-Energy code compliance | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | PART |
Dave Hannah
|
|
|
KENT Phone #: ###-#### ok to insulate 3rd floor and east half of forth floor
|
BLD-Energy code compliance | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Framing/Rough-in | 8/22/2014 | 8/22/2014 | 8/22/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####-2nd and 1st floor on north end
|
BLD-Energy code compliance | 8/22/2014 | 8/22/2014 | 8/22/2014 | P | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####-2nd and 1st floor on north end
|
BLD-Framing/Rough-in | 8/18/2014 | 8/19/2014 | 8/20/2014 | P | PART |
Dave Hannah
|
|
|
4th fl corrider - Kent Phone #: ###-#### ok to cover ceiling
|
BLD-Energy code compliance | 8/18/2014 | 8/19/2014 | 8/20/2014 | P | PART |
Dave Hannah
|
|
|
1 & 2 floor - Kent Phone #: ###-#### east half ok to cover
|
BLD-Energy code compliance | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Dave Hannah
|
|
|
kent Phone #: ###-#### ok to cover four rooms see first floor plan
|
BLD-Energy code compliance | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | NR |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Framing/Rough-in | 8/7/2014 | 8/7/2014 | 8/8/2014 | P | PART |
Dave Hannah
|
|
|
1/2 1st fl & 1/2 2nd fl - Kent Phone #: ###-#### ok to insulate
|
BLD-Wall Bracing | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Jim Storey
|
|
|
4th floor shear // Kent Phone #: ###-#### exterior ok to cover
|
BLD-Framing/Rough-in | 7/15/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Jim Storey
|
|
|
Kent-Roof Phone #: ###-#### roof and corridors and shafts ok to start per rock.
|
BLD-Wall Bracing | 6/19/2014 | 6/20/2014 | 6/24/2014 | A | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### first floor ok
|
BLD-Framing/Rough-in | 6/19/2014 | 6/20/2014 | 6/24/2014 | A | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-#### first floor corr. ok to top with sheetrock so trades can do thier rough ins
|
BLD-Wall cover | 6/3/2014 | 6/4/2014 | 6/4/2014 | A | NR |
Dave Hannah
|
|
|
Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 4/22/2014 | 4/23/2014 | 4/24/2014 | P | PART |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Conference | 2/5/2014 | 2/6/2014 | 2/6/2014 | A | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
BLD-Footing | 1/30/2014 | 1/31/2014 | 2/3/2014 | A | PART |
Dave Hannah
|
|
|
kent Phone #: ###-#### foundation south half mti on site testing concrete
|
BLD-Other | 1/24/2014 | 1/27/2014 | 1/27/2014 | A | PART |
Dave Hannah
|
|
|
rebar - kent Phone #: ###-####
|
Case Summary (BLD) | | | 1/24/2014 | | DONE |
|
|
|
|
BLD-Footing | 1/16/2014 | 1/17/2014 | 1/17/2014 | P | NR |
Dave Hannah
|
|
|
rebar - chance Phone #: ###-####
|
OVERRIDE | | | 11/26/2013 | | |
|
|
|
|
Print Occupancy Form | | | 11/26/2013 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/26/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Expiration Notice | 10/4/2013 | 10/25/2013 | 10/4/2013 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
|
Change Expiration Date Only | | | 10/4/2013 | | DONE |
Christina Prado
|
|
|
marked wrong year
|
Telephone call | | | 9/17/2013 | | DONE |
Christina Prado
|
|
|
emailed Glenn Levie giving fees due based on revised cert of value. Also advised GC form, RP & ACHD for issuance
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2013 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 1/4/2013 | | 8/26/2013 | | PASS |
John Menard
|
|
|
1st Review completed 2/13/2013. JCM
|
Routing - PLUMBING | 8/21/2013 | | 8/23/2013 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
Will check Water heaters on final to make sure they meet 1st hour rating.
|
Routing - PLAN CHECK | 8/21/2013 | | 8/21/2013 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 7/29/2013 | | 8/14/2013 | | FAIL |
John Menard
|
|
|
|
Routing PW Sewer Design | 7/30/2013 | | 8/5/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 7/30/2013 | | 8/1/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLUMBING | 7/29/2013 | | 8/1/2013 | | FAIL |
Daryl Spivey
|
|
|
1) provide suds relief per Idaho State Plumbing code.
2) provide first hour rating for WH-1 and WH-2.
3) pipe t&p and pan drains to washer box. t&p line is not allowed to connect to sink tailpiece.
|
Change Expiration Date Only | | | 6/12/2013 | | DONE |
Jason Blais
|
|
|
A 180 day extension from 4/28/13 has been granted for a permit application under review. This is the first extension request.
|
Plan Reviewer's activity | | | 6/11/2013 | | DONE |
John Menard
|
|
|
E-mailed the architect a letter indicating that his project application was expiring and advising an extension request would be required to keep project open. JCM
|
Routing - PLANNING Land Div | 3/25/2013 | | 4/8/2013 | | PASS |
Dave Abo
|
|
|
|
Routing - PLAN CHECK | 3/25/2013 | | 4/2/2013 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 3/25/2013 | | 3/29/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing Off Site - STRUCTURAL | 3/25/2013 | | 3/26/2013 | | PASS |
John Menard
|
|
|
|
Routing - PLUMBING | 3/25/2013 | | 3/26/2013 | | FAIL |
Daryl Spivey
|
|
|
Provide expansion sized adequately for water system.
50 gal. water heaters for 2 bath units not 30 gal.
Provide suds relief as required per 711.0 ISPC
|
Routing - Erosion and Sediment | 3/25/2013 | | 3/26/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved with redlines
|
Routing PW Drainage | 3/19/2013 | | 3/19/2013 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 2/13/2013 | | DONE |
John Menard
|
|
|
|
Route to Impact Fee Review | 1/4/2013 | | 2/13/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 1/4/2013 | | 2/9/2013 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 1/4/2013 | | 1/16/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed correction items to archtitect. Attached plan review report to case.
|
Routing Off Site - STRUCTURAL | 1/4/2013 | | 1/16/2013 | | FAIL |
John Menard
|
|
|
|
Routing - Addressing | 1/4/2013 | | 1/11/2013 | | PASS |
April Wing
|
|
|
Address changed from 916 E Park Blvd to 951 E Front St. See Address Doc./ Applicant was notified
|
Routing PW Flood Plain | 1/4/2013 | | 1/11/2013 | | PASS |
Jim Wyllie
|
|
|
|
Routing PW Sewer Design | 1/4/2013 | | 1/9/2013 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Coordinate removal of existing main and manhole with the city.
Not enough information provided.
|
Routing PW Drainage | 1/4/2013 | | 1/7/2013 | | FAIL |
Brian Murphy
|
|
|
|
Routing - Design Review | 1/4/2013 | | 1/7/2013 | | PASS |
Josh Wilson
|
|
|
OK per CUP11-00103, CVA11-00056, and DRH12-00227
|
Routing - PLUMBING | 1/4/2013 | | 1/7/2013 | | FAIL |
Daryl Spivey
|
|
|
1. Civil utility plan does not match plumbing plans.
2. Provide suds relief per ISPC 711.0.
3. Install a DCVA on water service line.
4. Provide for expansion adequate for water system.
|
Routing - Erosion and Sediment | 1/4/2013 | | 1/7/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
PD must provide signature; provide description and detail for temporary sediment basin; provide info on receiving waters for storm drains on Park, Front and Morrison; concrete wahout liner must be impermeable; temporary stabilization required for all disturbed inactive areas (not only stockpiles); include minimum control measures for spill prevention and containment; not compliant with EPA 2012 CGP. See changemarks in ePlan.
|
Routing - PLANNING Land Div | 1/4/2013 | | 1/7/2013 | | FAIL |
Dave Abo
|
|
|
Prior to issuing building permit, a Record of Survey for a parcel consolidation must be completed.
|
Pending Assignment by JCM | 1/4/2013 | | 1/4/2013 | | DONE |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 1/4/2013 | | 1/4/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 1/4/2013 | | 1/4/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 1/4/2013 | | 1/4/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 1/4/2013 | | 1/4/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Routing PW Street Lights | 1/4/2013 | | 1/4/2013 | | PASS |
Mike D Hedge
|
|
|
|
Payment Received | | | 1/2/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/30/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 30 2012 12:51PM
|