Third Notice | | 6/8/2013 | 6/7/2013 | | DONE |
Christina Prado
|
|
|
complete 6-7-13
|
Third Notice | | 4/28/2013 | 6/3/2013 | | DONE |
|
|
|
mailed to Lodman
|
Third Notice | | 3/27/2013 | 4/23/2013 | | DONE |
|
|
|
faxed to Lodman
|
Second Notice | | 3/1/2013 | 3/22/2013 | | DONE |
|
|
|
|
First Notice | | 2/15/2013 | 2/19/2013 | | DONE |
Christina Prado
|
|
|
mailed 02-20-13
|
BLD-Final | 2/1/2013 | 2/5/2013 | 2/5/2013 | P | PASS |
Tom Arcoraci
|
|
|
requesting approval pending CDHD inspection at 1:00 pm on 2/5. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
|
Permanent Occupancy | | | 2/5/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/1/2013 | 2/4/2013 | 2/4/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 2/1/2013 | 2/1/2013 | 2/1/2013 | P | DONE |
Forrest France
|
|
|
Conference regarding main door hardware and exit discharge egress lighting.
|
FIRE-Conference | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | DONE |
Troy Cobbley
|
|
|
John and I went over life safety requirements.
|
BLD-Ceiling Grid Inspection | 1/22/2013 | 1/23/2013 | 1/23/2013 | P | PASS |
Tom Arcoraci
|
|
|
Please call for access code. thank you. Phone #: ###-#### >> Inspection requested via web by John Lodman
|
BLD-Wall cover | 12/28/2012 | 12/31/2012 | 12/31/2012 | P | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by John Lodman
|
OVERRIDE | | | 12/13/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/13/2012 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 12/13/2012 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 12/13/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 12/12/2012 | | 12/12/2012 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with corrections made. TLW
|
Routing - FIRE | 12/12/2012 | | 12/12/2012 | | PASS |
Scott Arellano
|
|
|
Approved in eplan review. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Solid Waste | 12/10/2012 | | 12/12/2012 | | PASS |
Peter J. McCullough
|
|
|
Approved in e-plan review. TLW
|
Routing PW Environmental | 12/10/2012 | | 12/12/2012 | | PASS |
Walt Baumgartner
|
|
|
Approved in E-plan review. TLW
|
Plan assigned to (TLW) | 11/7/2012 | | 12/12/2012 | | PASS |
Tim L. Woodard
|
|
|
Failed 1st review
|
Routing PW Sewer Rating | 12/10/2012 | | 12/10/2012 | | PASS |
Connie Baumgartner
|
|
|
|
1st review completed | | | 11/23/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/7/2012 | | 11/23/2012 | | FAIL |
Tim L. Woodard
|
|
|
Needs second exit. TLW
|
Routing - Addressing | 11/7/2012 | | 11/23/2012 | | PASS |
April Wing
|
|
|
verified correct address by site visit. Passed by April.
|
Routing Off Site - C.D.H | 11/7/2012 | | 11/21/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 11/7/2012 | | 11/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 11/7/2012 | | 11/13/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - FIRE | 11/7/2012 | | 11/9/2012 | | PASS |
Scott Arellano
|
|
|
No comments attached. Plans are approved as shown.
|
Routing - PLUMBING | 11/7/2012 | | 11/9/2012 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Intake Approval | | | 11/7/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 10/31/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 31 2012 10:58AM
|
Intake Approval | | | 10/31/2012 | | FAIL |
|
|
|
Project needs to be submitted as a Major Tenant TI, please fill out #520 checklist and upload into the documents folder. Please call Carl Madsen with any questions.
|