BLD-Final | 3/26/2014 | 3/31/2014 | 3/31/2014 | P | PASS |
Jim Sly
|
|
|
chad Phone #: ###-####
|
DOC - Permit Finaled | 3/31/2014 | 3/31/2014 | 3/31/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | DONE |
Jim Sly
|
|
|
chad Phone #: ###-####
|
BLD-Energy code compliance | 12/16/2013 | 12/18/2013 | 12/18/2013 | P | PASS |
Jim Sly
|
|
|
chad Phone #: ###-####
|
Plan Modification Accepted | | | 11/19/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 11/19/2013 | | 11/19/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Conference | 11/18/2013 | 11/18/2013 | 11/18/2013 | P | DONE |
Jim Sly
|
|
|
chad Phone #: ###-#### OK'd Contr. to sheetrock garage only.
|
BLD-Conference | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | DONE |
Jim Sly
|
|
|
Chad Phone #: ###-####
|
BLD-Wall Bracing | 10/28/2013 | 10/28/2013 | 10/28/2013 | P | PART |
Jim Sly
|
|
|
Chad Phone #: ###-#### Exterior shear nailing only........OK.
|
BLD-Framing/Rough-in | 10/23/2013 | 10/23/2013 | 10/23/2013 | P | NR |
Jim Sly
|
|
|
Shear inspection-Chad Phone #: ###-####
|
BLD-Conference | 10/14/2013 | 10/14/2013 | 10/14/2013 | P | DONE |
Jim Sly
|
|
|
Chad phone
|
BLD-Conference | 10/10/2013 | 10/14/2013 | 10/14/2013 | A | CANC |
Jim Sly
|
|
|
Chad phone.....
|
BLD-Conference | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | DONE |
Jim Sly
|
|
|
This is per your request JIm
|
BLD-Foundation | 8/15/2013 | 8/19/2013 | 8/19/2013 | P | PASS |
Jim Sly
|
|
|
Chad ###-####
|
BLD-Footing | 8/15/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Jim Sly
|
|
|
chad ###-####
|
OVERRIDE | | | 8/15/2013 | | |
|
|
|
|
Routing Walk-In (BLD) | 8/15/2013 | 8/15/2013 | 8/15/2013 | A | DONE |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 8/15/2013 | | |
|
|
|
|
Case Summary (BLD) | | | 8/15/2013 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
called Chad and told him revised plans are ready, new fees.
|
Routing - PLAN CHECK | 8/14/2013 | | 8/15/2013 | | PASS |
Perry Paine
|
|
|
|
Issue PAID IN FULL permit | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 8/14/2013 | | DONE |
Tisha Gallop
|
|
|
received revised manual J, two copies of lateral and tall wall calcs, two copies of full set plans. Routed to Planning, Mechanical, Plan Reveiw.
|
Routing - PLANNING | 8/14/2013 | | 8/14/2013 | | PASS |
Susan Riggs
|
|
|
revised site plan approved
|
Routing - MECHANICAL | 8/14/2013 | | 8/14/2013 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (BLD) | 7/25/2013 | 7/25/2013 | 7/30/2013 | P | PASS |
Perry Paine
|
|
|
|
Extend Review Timeline | | | 4/24/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 4/23/2013 | | DONE |
Christina Prado
|
|
|
called Chad to advise expiration date is fast approaching - he will sed email requesting extension to Jason by the end if the week
|
Expiration Notice | 4/9/2013 | 4/30/2013 | 4/9/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 11/30/2012 | | |
|
|
|
|
Plan assigned to (PEP) | 11/27/2012 | 11/27/2012 | 11/30/2012 | | PASS |
Perry Paine
|
|
|
sent e-mail and phone call requesting detail for wood stove flu through garage attic. 11-27-2012 pep detail approved 11-30-2010 pep
|
Case Summary (BLD) | | | 11/30/2012 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2012 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/30/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/30/2012 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/9/2012 | | 11/30/2012 | | PASS |
Carl D Madsen
|
|
|
|
Telephone call | | | 11/30/2012 | | DONE |
|
|
|
called chad permit ready fees given
|
1st review completed | | | 11/30/2012 | | DONE |
Carl D Madsen
|
|
|
|
Plan assigned to (CDM) | 11/5/2012 | 11/5/2012 | 11/27/2012 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 11/9/2012 | | 11/9/2012 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | | | 11/9/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Teds heating
|
Route to Impact Fee Review | 11/5/2012 | 11/8/2012 | 11/8/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 11/6/2012 | | 11/7/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 11/7/2012 | | 11/7/2012 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 11/5/2012 | | 11/6/2012 | | PASS |
April Wing
|
|
|
|
Application received | | 10/31/2012 | 11/5/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/5/2012 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/5/2012 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 11/5/2012 | | PASS |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/31/2012 | | FAIL |
Tisha Gallop
|
|
|
need tall wall eng and wall bracing, see checklist
|