Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-02971
StatusFinaled
Name DOUG LASHER CONSTRUCTION
Site Address 2810 E HARDROCK DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 3,052 sq. ft., two story (basement 707 sq. ft., main level 1,759 sq. ft., upper level 586 sq. ft.) single family dwelling with 6 bedrooms, 3.5 bathrooms, approximately 336 sq. ft. of covered patio/porch and a 888 sq. ft. attached garage per the approved plans, plan review report and any notations. R1A/DA zoning and setbacks per planning. A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/29/20137/30/20137/31/2013PPASS
DetailsDave Hannah
Bryan Phone #: ###-####
DOC - Permit Finaled7/31/20137/31/20137/31/2013PPASS
DetailsDave Hannah
PubWorks Occupancy Approval7/31/20137/31/20137/31/2013 DONE
DetailsJason C. Taylor
Recieved engineers approval for site grading and drainage. Project is approved for occupancy. Jason Taylor ###-####
BLD-Energy code compliance5/2/20135/3/20135/3/2013APASS
DetailsTom Arcoraci
bryan Phone #: ###-####
BLD-Framing/Rough-in4/30/20135/1/20135/1/2013PPASS
DetailsTom Arcoraci
Bryan Phone #: ###-####
BLD-Foundation3/6/20133/8/20133/8/2013PPASS
DetailsDave Hannah
eric Phone #: ###-####
BLD-Footing2/25/20132/26/20132/26/2013PPASS
DetailsDave Hannah
eric Phone #: ###-####
PubWorks Subgrade Approval2/25/20132/25/20132/25/2013 DONE
DetailsJason C. Taylor
Recieved engineers approval for subgrade. OK to schedule footing inspection with building department. Jason Taylor ###-####.
OVERRIDE  1/17/2013  
Plan assigned to (CDM)11/14/201211/14/20121/17/2013 PASS
DetailsCarl D Madsen
Issue PAID IN FULL permit  1/17/2013 DONE
DetailsChristina Prado
Inspection Record Card- Bld  1/17/2013 DONE
DetailsChristina Prado
Routing - PLAN CHECK1/15/2013 1/17/2013 PASS
DetailsCarl D Madsen
Routing - PLANNING1/17/2013 1/17/2013 PASS
DetailsJoshua Johnson
Routing PW Grading-Hillside1/17/2013 1/17/2013 PASS
DetailsJason C. Taylor
Plan resubmittals received  1/17/2013 DONE
DetailsChristina Prado
received three sets of plans marked C1; taken to Carl Madsen
Routing - PUBLIC WORKS1/17/2013 1/17/2013 PASS
DetailsConnie Baumgartner
PLANS/APPL TAKEN TO FRONT DESK  1/17/2013  
Permit Ready to Issue  1/17/2013 DONE
DetailsChristina Prado
Routing - PLANNING12/26/2012 1/15/2013 FAIL
DetailsDavid Moser
The site plan needs to match the floor plan and need to show the 3 foot landscape buffer next to driveway. Will route to PW Hillside for review.
Routing - PUBLIC WORKS GRADING1/15/2013 1/15/2013 FAIL
DetailsConnie Baumgartner
Failed by Jason Taylor for hillside.
Routing PW Grading-Hillside1/15/2013 1/15/2013 FAIL
DetailsJason C. Taylor
The grading plan needs to be revised to match the floor plan and to address the landscape area next to the concrete retaining wall, the slab slope in the back yard, and the grading of the area between the garage wall and the retaining wall for hte patio. Jason Taylor (###-####)
Routing - Erosion and Sediment1/3/2013 1/3/2013 PASS
DetailsKimberly M. Johnson
Plan submitted on 11/14/12 re-reviewed and approved with same redlines
Case Summary (BLD)  1/2/2013 DONE
Routing - PLAN CHECK12/5/2012 1/2/2013 PASS
DetailsCarl D Madsen
Routing - PUBLIC WORKS12/26/2012 12/26/2012 PASS
DetailsConnie Baumgartner
Routing PW Grading-Hillside12/26/2012 12/26/2012 PASS
DetailsJason C. Taylor
CFH application CFH12-00042 approved for retaining walls, cut/fill, ect. Jason Taylor (###-####)
Plan resubmittals received  12/20/2012 DONE
DetailsChristina Prado
Received three sets of plans marked C1 as well as one 8 1/2 X 11 site plan; gave to Carl for review
Plan resubmittals received  12/18/2012 DONE
DetailsChristina Prado
Received one set of Wood Beam calcs, two set of plans marked C1 and two revised sets of building plans marked A-101, A-102, A-103, A-104, A-105, A-201, A-202, A-203, S-101 & S-102; routed to Carl for additional review
Routing - PLAN CHECK11/26/2012 12/5/2012 FAIL
DetailsCarl D Madsen
Engineeering, trusss details, handrails and beam. Sent E-Mail to the applicant. 12-5-12 CDM
1st review completed  12/5/2012 FAIL
Routing - FIRE11/23/2012 11/26/2012 PASS
DetailsScott Arellano
Approved as shown.
Plan resubmittals received  11/23/2012 DONE
DetailsChristina Prado
received two sets of plans marked C1 & A-101; gave to Carl Madsen for further review
Routing - MECHANICAL11/19/2012 11/23/2012 PASS
DetailsTroy James
Routing - Erosion and Sediment11/21/2012 11/21/2012 PASS
DetailsKimberly M. Johnson
ESC12-01119
Routing - PUBLIC WORKS11/14/2012 11/16/2012 PASS
DetailsConnie Baumgartner
Route to Impact Fee Review11/14/201211/19/201211/15/2012 PASS
DetailsCindy M. Gould
Routing - Addressing11/14/2012 11/15/2012 PASS
DetailsApril Wing
Application received 11/8/201211/14/2012 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  11/14/2012 DONE
DetailsTisha Gallop
Intake Approval  11/14/2012 PASS
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  11/14/2012 DONE
DetailsTisha Gallop
Intake Approval  11/8/2012 PASS
DetailsTisha Gallop
need CFH
Routing - PLANNING11/16/2012   FAIL
Does not meet side yard setback of 10'
Routing - PLANNING12/5/2012   FAIL
DetailsColleen T Carroll
Still failed for back up area. Came in for a pre-app conferance and will be submitting for a variance.