First Notice | | 1/7/2013 | 1/28/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/28/2012 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 12/27/2012 | 12/27/2012 | 12/27/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Final | 12/27/2012 | 12/27/2012 | 12/27/2012 | P | PASS |
Jim Storey
|
|
|
Dennis Phone #: ###-#### plm n/a ok final ok
|
FIRE-Sprinkler Rough-in | 12/17/2012 | 12/18/2012 | 12/18/2012 | A | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work at the drop ceiling.
|
FIRE-Sprinkler Rough-in | 12/17/2012 | 12/17/2012 | 12/17/2012 | A | PART |
Forrest France
|
|
|
|
BLD-Framing/Rough-in | 11/29/2012 | 11/30/2012 | 11/30/2012 | A | PASS |
Tom Arcoraci
|
|
|
Dennis Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/27/2012 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/27/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/26/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 11/13/2012 | | 11/20/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/13/2012 | | 11/20/2012 | | PASS |
Tim L. Woodard
|
|
|
approved with notes on plans in eplan review. TLW
|
Routing PW Sewer Rating | 11/13/2012 | | 11/20/2012 | | PASS |
Connie Baumgartner
|
|
|
Approved in eplan review. TLW
|
1st review completed | | | 11/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 11/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Addressing | 11/13/2012 | | 11/15/2012 | | PASS |
April Wing
|
|
|
|
Payment Received | | | 11/13/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 11/13/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 11/13/2012 | | 11/13/2012 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 11/9/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 9 2012 3:50PM
|