BLD-Final | 5/20/2014 | 5/21/2014 | 5/21/2014 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
DOC - Permit Finaled | 5/21/2014 | 5/21/2014 | 5/21/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PEND |
Tony Young
|
|
|
Larry Phone #: ###-####,, inside all ok,, just need hillside
|
PubWorks Occupancy Approval | 5/20/2014 | 5/20/2014 | 5/20/2014 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading/revegetation/ and driveway has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 5/19/2014 | 5/19/2014 | 5/19/2014 | P | NR |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Final | 5/15/2014 | 5/19/2014 | 5/19/2014 | A | NR |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Final | 5/16/2014 | 5/16/2014 | 5/16/2014 | P | NR |
Tony Young
|
|
|
Larry Phone #: ###-####,, walkthrough only,, need trades, handrail per code,, hillside
|
BLD-Final | 5/15/2014 | 5/15/2014 | 5/15/2014 | P | NR |
Tony Young
|
|
|
Larry Phone #: ###-####.. need trades,, hillside 1st
|
BLD-Footing | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PASS |
Jim Sly
|
|
|
james - pouring at 1 Phone #: ###-#### For stairway.
|
BLD-Energy code compliance | 2/6/2014 | 2/7/2014 | 2/7/2014 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Energy code compliance | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 2/5/2014 | 2/6/2014 | 2/6/2014 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 1/24/2014 | 1/27/2014 | 1/27/2014 | P | PART |
Tony Young
|
|
|
larry Phone #: ###-####,, ok to start insulation,, will do seal pack from foam,, NEEDS FURTHER APPROVALS FROM TRADES PRIOR TO COVER
|
BLD-Framing/Rough-in | 10/17/2013 | 10/17/2013 | 10/17/2013 | P | PASS |
Jim Storey
|
|
|
Shear insepction please--Larry Phone #: ###-####
|
BLD-Foundation | 7/25/2013 | 7/26/2013 | 7/25/2013 | P | PART |
Tony Young
|
|
|
basement wall - james Phone #: ###-####
|
BLD-Other | 7/24/2013 | 7/25/2013 | 7/25/2013 | A | PART |
Tony Young
|
|
|
basement wall - james Phone #: ###-####,, work in progress,, ok house walls including retaining walls
|
BLD-Footing | 7/17/2013 | 7/18/2013 | 7/18/2013 | A | PART |
Tony Young
|
|
|
james Phone #: ###-####,, house and garage ftgs
|
PubWorks Subgrade Approval | 7/18/2013 | 7/18/2013 | 7/18/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer for entire building footprint. Building department may be scheduled for footing inspections. Jason Taylor ###-####.
|
CHANGE STATUS TO (ISS) | | | 7/2/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 6/11/2013 | 6/11/2013 | 6/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/11/2013 | | 6/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2013 | | DONE |
|
|
|
|
FEE PAYMENT ACTIONS | | | 6/25/2013 | | DONE |
Barbara Stitt
|
|
|
No fees charged on plan modification of revised site plan per Carl Madsen//BAS 6-25-13 there are only 2 sheets for the plan mod C1.0 Site Plan & C2.0 Grading Plan
|
Routing PW Grading-Hillside | 6/24/2013 | | 6/24/2013 | | PASS |
Jason C. Taylor
|
|
|
New grading plan approved. Jason Taylor ###-####
|
Routing - PLANNING | 6/17/2013 | | 6/17/2013 | | PASS |
David Moser
|
|
|
Talked with Larry Keller and they will increase turn around area in front of garage doors to over 20 feet.
|
Issue PAID IN FULL permit | | | 6/4/2013 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 4/23/2013 | 5/14/2013 | 4/23/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 12/18/2012 | 12/18/2012 | 4/15/2013 | | PASS |
Carl D Madsen
|
|
|
ePlan review
|
Routing - PLAN CHECK | 4/15/2013 | | 4/15/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 4/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 4/11/2013 | | 4/11/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 4/4/2013 | | 4/4/2013 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 4/1/2013 | | 4/1/2013 | | PASS |
David Moser
|
|
|
|
Routing PW Grading-Hillside | 4/1/2013 | | 4/1/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing - MECHANICAL | 2/20/2013 | | 2/20/2013 | | FAIL |
Troy James
|
|
|
corrections from previous review has not been addressed
EPLAN
|
Routing PW Grading-Hillside | 2/20/2013 | | 2/20/2013 | | FAIL |
Jason C. Taylor
|
|
|
Geotechnical report needs updated, grading plan shows fill outside property boundaries, retaining walls need engineering. Call Jason Taylor at ###-#### for details.
|
Routing - PLAN CHECK | 12/18/2012 | | 1/7/2013 | | FAIL |
Carl D Madsen
|
|
|
Engineering has used a soil bearing pressure of 4000 PSF Geotechnical report indicates a soil bearing of 1200 PSF. 1-7-13 CDM
|
1st review completed | | | 1/7/2013 | | FAIL |
|
|
|
|
Route to Impact Fee Review | 12/18/2012 | 12/21/2012 | 12/31/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 12/18/2012 | | 12/21/2012 | | FAIL |
Troy James
|
|
|
eplan
|
Routing PW Grading-Hillside | 12/18/2012 | | 12/20/2012 | | FAIL |
Jason C. Taylor
|
|
|
Category 1 Hillside appplication needed. Revised plans are to be submitted via ePlan Review per Larry Keller.
|
Routing - Addressing | 12/18/2012 | | 12/19/2012 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 12/18/2012 | | 12/19/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - FIRE | 12/19/2012 | | 12/19/2012 | | PASS |
Scott Arellano
|
|
|
Plans are approved with the shown fire sprinkler system as an acceptable code alternate to IFC 503.1.1. The Fire Sprinker system shall be designed in accordance with NFPA 13D and permitted separately.
|
Routing - Erosion and Sediment | 12/18/2012 | | 12/18/2012 | | CANC |
Kimberly M. Johnson
|
|
|
No review needed. See ESC12-00768
|
Routing - PLANNING | 12/18/2012 | | 12/18/2012 | | FAIL |
David Moser
|
|
|
Requires Cat I Planning application
|
Plans ACCEPTED BY PLAN TECH | | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/7/2012 | | PASS |
Barbara Stitt
|
|
|
Failed for Structural calcs and geo-technical report needed//12-7-12//BAS
|
Application received | | | 11/14/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 14 2012 1:03PM
|