Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD12-03024
StatusFinaled
Name DEBELLOY CONSTRUCTION
Site Address 9196 W BARNES DR
Project NameRaise the Bottom
Customer Number 
ePlanReviewYes
Description
(RAISE THE BOTTOM COUNSELING & CONSULTATION – Caribou Building – Ste #9196 – Adding private offices) Permit is to remodel an existing 7,410 square foot tenant space by adding private offices to 341 square feet of previously open office area. Work to include: construction of interior non-bearing walls to create three offices, new electrical switching only, installation of new doors / accessible hardware, and finishes in compliance with chapter 8 of the 2009 IBC. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  12/23/2015 DONE
BLD-Final5/16/20135/16/20135/16/2013APASS
DetailsMike Jordan
Please call ###-#### before arrival for entry Phone #: ###-#### >> Inspection requested via web by kevin debelloy
FIRE-Final Inspection5/15/20135/15/20135/15/2013PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final5/14/20135/15/20135/15/2013ANR
DetailsMike Jordan
Please call Kevin at ###-####- for entry Phone #: ###-#### >> Inspection requested via web by kevin debelloy. Life/safety inspection failed.
FIRE-Final Inspection5/14/20135/15/20135/15/2013AFAIL
DetailsTroy Cobbley
Remove the double dead bolts from the door in the egress path and provide annual inspection for the fire extinguishers.
BLD-Framing/Rough-in4/3/20134/4/20134/4/2013APART
DetailsMike Jordan
If inspector could please call 30 min before arrival we can meet the inspector there to let him in. Thanks Wayne ###-#### Phone #: ###-#### >> Inspection requested via web by kevin debelloy. Interior steel stud framed walls for new offices ok. Noted the doors added previusly with out a permit will need to be shown on plans and show compliance with ada and submitted as a plan mod or need to be removed.
Print Occupancy Form  3/28/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  3/28/2013 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  3/28/2013 DONE
DetailsChristina Prado
Payment Received  11/21/2012 DONE
Payment received via Govolutions
Intake Approval  11/21/2012 PASS
DetailsTim L. Woodard
Plan assigned to (TLW)11/21/2012 11/21/2012 DONE
DetailsTim L. Woodard
Routing - PLAN CHECK11/21/2012 11/21/2012 PASS
DetailsTim L. Woodard
1st review completed  11/21/2012 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  11/21/2012 DONE
DetailsTim L. Woodard
Application received  11/15/2012 DONE
Application submitted via PDS Online on Nov 15 2012 12:40PM