Permit Information
Permit NumberBLD12-03031
StatusFinaled
Name DOUG LASHER CONSTRUCTION
Site Address 1925 S TRAVERTINE WAY
Project NameBoulder Heights Lot22 Block2
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 4202 sq. ft., two story (first story 2448 sq. ft , unfinished basement1754 sf) single family dwelling with 3 bedrooms, 3 bathrooms, approximately 286 sq. ft. of covered patio/porch and a 768 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1A zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/31/20136/3/20136/3/2013PPASS
DetailsDave Hannah
BRYAN Phone #: ###-####
DOC - Permit Finaled6/3/20136/3/20136/3/2013PPASS
DetailsDave Hannah
PubWorks Occupancy Approval6/3/20136/3/20136/3/2013 DONE
DetailsJason C. Taylor
Recieved civil engineers approval letter for grading and drainage. Project is approved for occupancy from PW. Jason Taylor ###-####.
BLD-Other4/10/20134/11/20134/11/2013PDEFR
DetailsDave Hannah
exterior soffits - bryan Phone #: ###-####
BLD-Wall Bracing4/8/20134/8/20134/8/2013PPASS
DetailsDave Hannah
BLD-Energy code compliance4/5/20134/8/20134/8/2013APASS
DetailsDave Hannah
Bryan Phone #: ###-####
BLD-Framing/Rough-in4/3/20134/4/20134/8/2013PPASS
DetailsDave Hannah
Bryan Phone #: ###-####
BLD-Energy code compliance4/4/20134/5/20134/8/2013PCANC
DetailsDave Hannah
bryan Phone #: ###-####
BLD-Foundation2/14/20132/15/20132/15/2013APASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Footing2/5/20132/6/20132/7/2013PPASS
DetailsDave Hannah
Eric Phone #: ###-####
PubWorks Subgrade Approval2/4/20132/4/20132/4/2013 DONE
DetailsJason C. Taylor
Geotechnical engineer (Bob Arnold) has approved the subgrade material for this project as per the geotechnical report. Any fill material must be tested in accordance with the geotechnical report before footing are poured. Footing inspection may be scheduled by the building department. Jason Taylor ###-####
Routing - PLANNING1/17/2013 1/17/2013 PASS
DetailsJoshua Johnson
OVERRIDE  1/11/2013  
Issue PAID IN FULL permit  1/11/2013 DONE
Permit Ready to Issue  1/11/2013 DONE
Plan assigned to (CDM)12/6/201212/6/20121/8/2013 PASS
DetailsCarl D Madsen
Project Dox
Inspection Record Card- Bld  1/8/2013 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/8/2013  
Routing - PUBLIC WORKS GRADING1/3/2013 1/3/2013 PASS
DetailsJason C. Taylor
See Conditional approval letter for recommendations. Geotech and updated grading plans uploaded to Project Dox.
Routing - Erosion and Sediment1/3/2013 1/3/2013 PASS
DetailsKimberly M. Johnson
approved per redlines
Routing - Erosion and Sediment12/18/2012 12/18/2012 FAIL
DetailsKimberly M. Johnson
Must submit an ESC plan
Routing - PUBLIC WORKS GRADING12/18/2012 12/18/2012 FAIL
DetailsJason C. Taylor
This project needs a Category 1 Permit application. Also, the Grading & Drainage plan needs revised to account for runoff from driveway.
1st review completed  12/17/2012 FAIL
Routing - PLAN CHECK12/6/2012 12/17/2012 PASS
DetailsCarl D Madsen
Project Dox
Routing - MECHANICAL12/6/2012 12/10/2012 PASS
DetailsTroy James
eplan
Route to Impact Fee Review12/6/201212/11/201212/7/2012 PASS
DetailsCindy M. Gould
Route to Impact Fee Review12/6/201212/11/201212/7/2012 PASS
DetailsCindy M. Gould
Routing - Erosion and Sediment12/6/2012 12/7/2012 FAIL
DetailsKimberly M. Johnson
Need ESC Plan
Routing - Addressing12/6/2012 12/7/2012 PASS
DetailsApril Wing
Routing - PUBLIC WORKS12/6/2012 12/7/2012 PASS
DetailsConnie Baumgartner
Routing - FIRE12/6/201212/6/201212/6/2012 PASS
DetailsScott Arellano
No comments.
Recd Pcfee & Taken To Pln CK  12/6/2012 DONE
DetailsTisha Gallop
Routing - PLANNING12/6/2012 12/6/2012 PASS
DetailsSue Cummings
Intake Approval  12/5/2012 PASS
Application received  11/16/2012 DONE
Application submitted via PDS Online on Nov 16 2012 9:48PM
Routing PW Grading-Hillside12/6/2012   FAIL
DetailsJim Wyllie
e-mailed Jim to do review. Missed initial routing in Project dox so will not have task to sign off on until after Plan Check's Q & A.

Missing Geotechnical Report for hillside review. Pleae submit report dated November 30, 2012 by Bob Arnold. Jason Taylor (###-####)