BLD-Final | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | PASS |
Mike Jordan
|
|
|
HEATH PLEASE CALL 45 MIN BEFORE GOING OUT AS HE IS IN CALDWELL Phone #: ###-####
|
FIRE-Final Inspection | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. No materials (gases) are on site for storage arrangement verification.
|
Permanent Occupancy | | | 1/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 1/18/2013 | | 1/29/2013 | | PASS |
Tim L. Woodard
|
|
|
HM Has been approved through Fire Dept. and the building is now approved as a B and S-1 occupancy. Reissued permit. TLW
|
Routing - FIRE | | | 1/29/2013 | | PASS |
Scott Arellano
|
|
|
Plans approved based on revised Hazardous Materials storage plans. Refer to attached documents specifiying storage locations for Hazardous Materials.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/29/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 1/29/2013 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/29/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 12/19/2012 | | 1/29/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 1/28/2013 | | |
|
|
|
Received revised compressed gas storage plan from Air Gas (Heath Plaisance). Revised plan indicates all compressed gas cylinders, in excess of maximum allowable quantities within the building, to be stored exterior of the building. Flammable gases (ie propane & acetylene) will be stored in the lot adjacent to the building on steel storage pallets. Refer to attached documents for details.
|
Routing - FIRE | 1/17/2012 | | 1/18/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed IFC plan review report to applicant.
Additonal information is needed on the submitted plan which demonstrates the facility complies as an H-2 occupancy. Routed back to IBC plan reviewer for communication with permit applicant regarding the necessary information. Due to the change to a Hazardous occupancy classification; a registered design professional is required to perform the necessary building analysis and to confirm building and fire code compliance with the tenants proposed business operation as the Hazardous occupancy. Compliance with appliable provisions of the IBC and IFC shall be shown on the submitted plans.
|
Plan Reviewer's activity | | | 1/18/2013 | | DONE |
Tim L. Woodard
|
|
|
Sent this case to the Hot Topics Committee to discuss. TLW
|
Routing - PLAN CHECK | 12/19/2012 | | 12/21/2012 | | FAIL |
Tim L. Woodard
|
|
|
Sent this email to Heath on 12-21-12 to inform him of situation.
Good mourning Heath,
The Fire Dept. (Scott Arellano) has reviewed the submitted storage and gas list. He has indicated that the allowable quantities for much of the gas you store is exceeded. The next step to making this building comply with what you want to store within it is to work with an architect to reclassify the building to meet H2 and H3 requirements or reduce the gas stored on site and separate into multiple containment areas. Utilizing either of these options will take involving an Idaho Licensed Architect and having plans submitted for review. If you have additional questions in regards to the gas storage I would recommend discussing them with Scott Arellano; if you have questions in regards to what is required to submit a Tenant Improvement for review please contact me to discuss.
Best regards,
Tim Woodard
Plans Examiner II / City of Boise
###-####
twoodard@cityofboise.org
|
Routing - FIRE | 12/19/2012 | | 12/19/2012 | | FAIL |
Scott Arellano
|
|
|
Based on the classification and quantities of the submitted Hazardous Materials Inventory Statement (HMIS) the occupancy shall be grouped as an H-2 & H-3 per IFC table 2703.1.1(1).
|
BLD-Conference | 11/29/2012 | 11/30/2012 | 11/30/2012 | A | FAIL |
Mike Jordan
|
|
|
heath Phone #: ###-####. Building is only partiallysprinklered, warehouse only. Resubmit plan to match actual building layout. lever action hardware at exits on warehouse.
|
BLD-Final | 11/29/2012 | 11/30/2012 | 11/30/2012 | A | CANC |
Mike Jordan
|
|
|
will call to set up time, they are in Caldwell//Heath Plaisance Phone #: ###-####
|
FIRE-Final Inspection | 11/29/2012 | 11/29/2012 | 11/29/2012 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit plans to Tim Woodard indicating gas type, quantity and storage arrangement. Resubmit plans showing the actual wall layout (two additional rooms in warhouse). Provide single action hardware on the warehouse exit doors (see IFC 1008.1.9.1). Provide fire extinguishers as discussed. Provide annual inspection for the fire sprinkler system. Repair the fire alarm system and provide a dedicated electrical circuit (see IFC 107.5). Repair the exit signs. Provide knox key box for fire dept access (contact boise fire ###-####). Provide sticker at the main exit "Door to remain unlocked when building is occupied". Contact the boise city fire dept. for operational permit (###-####). Also the building is only partialy sprinklered. The warehouse and outside canopy has sprinkler protection but the office area does not. It appears fire rated doors are installed between the two.
|
Issue PAID IN FULL permit | | | 11/29/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
Caled Jeffrey to advise permit is ready for pick up
|
Print Occupancy Form | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 11/20/2012 | | 11/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/20/2012 | | 11/27/2012 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 11/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 11/27/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 11/20/2012 | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/20/2012 | | DONE |
Tisha Gallop
|
|
|
|
First Notice | | 2/9/2013 | | | |
|
|
|
|